Aminex PLCLSE: AEX

Aminex: Ntorya Operations Update

· Issued by Aminex PLC via RNS

Summary by 6ix AI

ARA Petroleum Tanzania Limited (APT), operator of the Ruvuma PSA (production sharing agreement), updated Aminex on the Ntorya gas development. Subject to contract finalisation and timely mobilisation of the gas processing unit, testing of the Ntorya-2 (NT-2) well is scheduled to start in December 2026, followed by production into the Ntorya-Madimba pipeline in late-December 2026.

Key details

  • Ntorya-3 (NT-3): the drilling rig, released by Maurel & Prom, is scheduled to arrive at the site in mid-December 2026, with spudding (the start of drilling) anticipated in late-December 2026. The rig is contracted for NT-3, with options for a workover (repair work) on NT-1 or a separate well, and two additional wells.
  • NT-3 civil works: the well pad is approximately 60% complete and access roads approximately 80% complete, with completion and site handover targeted for December 15, 2026. Rig base-camp preparation began on September 20, 2026.
  • NT-2: wellhead maintenance has been completed with no major findings. Removal of a bridge plug (a seal inside the well) is now scheduled for late November 2026, once the needed equipment is delivered.
  • Ntorya-1 (NT-1): wellhead maintenance and slickline work (tools lowered into the well on a wire) have been delayed pending delivery of replacement valves. Maintenance is expected to start in late-November 2026, with slickline work to follow. The results of this work will determine whether further work, including a rig-operated workover, is required.
  • The Tanzania Petroleum Development Corporation (TPDC) confirmed the Ntorya to Madimba pipeline remains on schedule for completion in December 2026, when it will be ready to carry gas from Ntorya to the Madimba Gas Processing Plant.

What’s still pending

  • NT-2 testing is subject to contract finalisation and the timely mobilisation of the gas processing unit.
  • NT-1 wellhead maintenance is subject to delivery of the valves and contractor mobilisation.
  • NT-3 spudding in late-December 2026 is anticipated after rig-up, commissioning and acceptance, and mobilisation of drilling services.
  • Pipeline completion is scheduled for December 2026.

6ix AI wrote this summary from the release below and checked it against the release.

Aminex PLC
09 November 2026

9 November 2026

AMINEX PLC
(“Aminex” or “the Company”)

Ntorya Operations Update

Aminex is pleased to provide the following operational update from ARA Petroleum Tanzania Limited ("APT"), operator of the Ruvuma PSA, on the Ntorya gas development.

Ntorya-3 (“NT-3”)

As previously announced, the contract for the supply of the drilling rig (“the Rig”) has been signed. The Rig has been released by Maurel & Prom and arrival at the NT-3 site is scheduled for mid-December 2026. Spudding of the well is anticipated in late-December 2026, following rig-up, commissioning and acceptance, and mobilisation of the required drilling services. The Rig has been contracted to drill NT-3, with an option to (a) carry out a workover on NT-1 or drill a separate well and (b) drill two additional wells.

Civil works to construct the NT-3 well pad and access roads are approximately 60% and 80% complete, respectively, with completion and site handover targeted for 15 December 2026. Rig base-camp preparation commenced on 20 September 2026, with handover targeted for later this month.

Ntorya-2 (“NT-2”)

Wellhead maintenance operations on NT-2 have recently been completed, with no major findings. The operator is awaiting delivery of the necessary equipment to commence bridge-plug removal operations, now scheduled for late November 2026. Subject to contract finalisation and the timely mobilisation of the gas processing unit, testing of NT-2 is scheduled to commence in December 2026, followed by production into the Ntorya-Madimba pipeline in late-December 2026.

Ntorya-1 (“NT-1”)

Wellhead maintenance and slickline operations on NT-1 have been delayed pending delivery of replacement valves required for those operations. Subject to delivery of the valves and contractor mobilisation, wellhead maintenance is expected to commence late-November 2026. Slickline operations will follow completion of the maintenance operations. As previously announced, the results of these operations will determine whether further work, including a rig-operated workover, is required.

Ntorya to Madimba Pipeline (“Pipeline”)

The Tanzania Petroleum Development Corporation (“TPDC”) has confirmed that the Pipeline remains on schedule for completion in December 2026, when it will be ready to transport gas from Ntorya to the Madimba Gas Processing Plant.

Charles Santos, Executive Chairman of Aminex, commented:

“We are pleased to receive this latest progress update from APT. Operations at Ntorya are ongoing and the next few months should see a further increase in operational activity.

Ntorya is well positioned to contribute materially to meeting Tanzania’s growing demand for reliable and affordable energy for many years. Domestic natural gas has an important role to play in supporting electricity generation, industrialisation and wider economic development.

We remain focused on maintaining the current momentum and delivering first gas in December.”

For further information:

Aminex PLC

+44 203 355 9909

Charles Santos, Executive Chairman

Knights Media & Public Relations

aminex@knightsmpr.com

Anthea Pitt

Davy

+353 1 679 6363

Brian Garrahy

Shard Capital

+44 20 7186 9952

Damon Heath

Axis Capital Markets

+44 203 026 0320

Richard Hutchison

This information is provided by RNS, the news service of the London Stock Exchange. RNS is approved by the Financial Conduct Authority to act as a Primary Information Provider in the United Kingdom. Terms and conditions relating to the use and distribution of this information may apply. For further information, please contact rns@lseg.com or visit www.rns.com.

RNS may use your IP address to confirm compliance with the terms and conditions, to analyse how you engage with the information contained in this communication, and to share such analysis on an anonymised basis with others as part of our commercial services. For further information about how RNS and the London Stock Exchange use the personal data you provide us, please see our Privacy Policy.

END

Aminex PLC on 6ix

Story so far

Earlier from Aminex

All Aminex news releases