Ref: MISIL/PSX-MISC/2026 April 28, 2026
The General ManagerPakistan Stock Exchange Limited Stock Exchange Building
Stock Exchange Road Karachi.
SUBJECT: MUGHAL ENERGY LIMITED (SUBSIDIARY COMPANY)
HYBRID POWER PLANT PROJECT STATUSDear Sir,
We are pleased to inform you the following Hybrid Power Plant Project status of Mughal Energy Limited (Subsidiary Company):
Turbine rolling has been initiated, marking the commencement of gradual power generation and load/reliability testing, including system stability and safety compliances.
Yours Sincerely,
For MUGHAL IRON & STEEL INDUSTRIES LIMITED
MUHAMMAD FAHAD HAFEEZ(Company Secretary)
CC: The Director Enforcement