Mirabela Nickel LimitedTSX: MNB

Mirabela Nickel Limited - Quarterly Activity Report for the Period Ended 30 September 2011

· Issued by Mirabela Nickel Limited via CNW

Key figures

  • Record production of nickel in concentrate for the quarter of 4,605 tonnes (up 36% from Q2 2011: 3,395 tonnes)
  • Record sales of nickel in concentrate for the quarter of 4,228 tonnes (up 8% from Q2 2011: 3,909 tonnes)
  • 15% decrease in unit cash costs for the quarter to US$6.71/lb (Q2 2011: US$7.85/lb) and expected to continue to decrease further during the fourth quarter
  • Record total mining material movement of 10.4 million tonnes (up 14% from Q2 2011) and ore production of 1.7 million tonnes (up 31% from Q2 2011)
  • Processing plant upgrade to 7.2 million tonnes per annum remains on budget and ahead of schedule

On 6ix: 6ix.com/news/mirabela-nickel-limited-quarterly-activity-report-for-the-period-ended-30-september-2011

PERTH, Australia, Oct. 24, 2011 /CNW/ - Mirabela Nickel Limited ("Mirabela" or the "Company") (ASX: MBN, TSX: MNB) is pleased to announce its unaudited third quarter results for the period ended 30 September 2011.

HIGHLIGHTS

  • Record production of nickel in concentrate for the quarter of 4,605 tonnes (up 36% from Q2 2011: 3,395 tonnes)
  • Record sales of nickel in concentrate for the quarter of 4,228 tonnes (up 8% from Q2 2011: 3,909 tonnes)
  • 15% decrease in unit cash costs for the quarter to US$6.71/lb (Q2 2011: US$7.85/lb) and expected to continue to decrease further during the fourth quarter
  • Record total mining material movement of 10.4 million tonnes (up 14% from Q2 2011) and ore production of 1.7 million tonnes (up 31% from Q2 2011)
  • Record processing plant performance with mill throughput of 1.4 million tonnes for the quarter at an average nickel recovery of 62% (Q2 2011: 1.3 million tonnes at 56% recovery)
  • Processing plant upgrade to 7.2 million tonnes per annum remains on budget and ahead of schedule
  • Close out of all outstanding copper (8,844 tonnes) nickel (10,626 tonnes) hedges at a total cost of approximately US$20 million
  • Cash on hand and on deposit of US$117 million at quarter end (Q2 2011: US$143 million)

OPERATIONS

Mirabela remains on track to achieve the production guidance of between 15,500 and 16,500 tonnes of nickel in concentrate for 2011. The Company is targeting full production levels by the end of December 2011 with the completion of the project ramp-up activities.

Safety

During the third quarter Mirabela had three LTI's, increasing the 12 month moving average Lost Time Injury Frequency Rate to 1.50 at the end of the third quarter.  Two LTI's were related to drilling activities and one LTI to maintenance.  Preventative measures have been implemented.  Mirabela continues its strong focus on safety training and the implementation of best practices to reduce the risk of injuries and to improve the Company's safety performance.

Production Statistics

Three months
ended
30 Sep 2011
Three months
ended
30 Jun 2011
% changeYear to Date
2011
Mining
Total Material MinedTonnes10,435,1629,119,8311428,597,291
Ore MinedTonnes1,693,0491,294,774313,963,599
Nickel Grade%0.480.48-0.48
Processing
Total Ore ProcessedTonnes1,441,3991,294,550113,806,316
Nickel Grade%0.520.47110.49
Copper Grade%0.140.1380.13
Cobalt Grade%0.020.011000.02
Nickel Recovery%62561158
Copper Recovery%6865568
Cobalt Recovery%3533634
Production
Nickel in Concentrate ProducedDMT4,6053,3953610,825
Copper in Concentrate ProducedDMT1,3681,065283,375
Cobalt in Concentrate ProducedDMT766517194
Sales
Nickel in Concentrate SoldDMT4,2283,909810,220
Copper in Concentrate SoldDMT1,2621,262-3,192
Cobalt in Concentrate SoldDMT77744189

Mining

Mirabela achieved a record mining performance during the third quarter of 2011, with 10.4 million tonnes of material movement and 1.7 million tonnes ore production. Ore was mined at an average nickel grade of 0.48% and a strip ratio of 5.2:1.

With the pre-strip of the mine completed in the second quarter, fresh ore production was available from all three zones of the open pit enabling the ramp-up of ore production.  The majority of ore produced during the third quarter came from the central and southern zones in accordance with the mine plan.

Mirabela strengthened the drilling fleet late in the third quarter with the addition of an Atlas Copco Pit Viper 271 and an Atlas Copco L8 drill rig. Mirabela continues to work with its drilling contractors to improve drilling performance, with their performance improving during the quarter but still underperforming compared to owner operated drilling. Mirabela is expecting delivery of two drill rigs at the end of the first quarter 2012.

Truck availability and utilisation improved during the quarter due to improved tyre availability and performance.  A twelve month supply of tyres was secured at the end of the second quarter. Loader productivity improved with the change over from backhoe to front shovel configurations delivering the expected results.

Processing

During the quarter a record of 1.4 million tonnes of ore was milled at an average grade of 0.52% nickel with an average recovery of 62%. The record recovery result for the quarter was due to the improved quality and consistency of ore presented to the plant as this was the first quarter where fresh ore was available from all three zones. Monthly plant shutdowns are continuing to allow for the necessary tie-in work for the plant upgrade project to 7.2Mtpa.

Nickel in concentrate production was up 36% to a record 4,605 tonnes from the second quarter 2011 (3,395 tonnes), with contained copper in concentrate increasing to 1,368 tonnes and contained cobalt in concentrate increasing to 76 tonnes.  Nickel in concentrate sold to Mirabela's customers, Votorantim Metais Niquel S.A. and Norilsk Nickel increased to 4,228 tonnes, an increase of 8% compared to the second quarter 2011 (3,909 tonnes). One export shipment of 11,389 tonnes of concentrate to Norilsk Nickel was completed during the quarter with the next shipment expected to be completed by late October 2011. Steady deliveries to Votorantim continued throughout the quarter.

7.2Mtpa Processing Plant Upgrade

The processing plant upgrade remains ahead of schedule and on budget. Installation of the second ball mill, second pebble crusher and second Larox filter have been completed.  The civil works and the installation of the de-sliming plant and crusher upgrade are underway.  The de-sliming plant is on target to be completed by the end of 2011 and the crusher upgrade by the end of January 2012.

Exploration

Exploration activity for the quarter was focused on tenement maintenance only.  Open pit extension drilling under the North pit is expected to start during the fourth quarter, targeting an increase in Open pit resources.

Unit Cash Costs

Three months
ended
30 Sep 2011
Three months
ended
30 Jun 2011
% changeYear to Date
2011
Payable Nickel Production(1)Lbs9,035,3186,662,0013621,240,380
Production Costs
Mining CostUS$/lb3.663.8343.67
Processing CostsUS$/lb1.892.51252.13
Administration CostUS$/lb0.661.05370.89
SubtotalUS$/lb6.217.39166.69
Selling Costs
Transport/Shipping CostUS$/lb0.230.06(283)0.16
By-Product Credit(2)US$/lb(1.21)(1.64)(26)(1.37)
Smelter ChargesUS$/lb1.482.04271.65
SubtotalUS$/lb0.500.46(9)0.44
C1 Unit Cash CostUS$/lb6.717.85157.13
Unit Royalty CostUS$/lb0.510.65220.58
Realised Nickel Price(3)US$/lb9.2211.48(20)10.10
Realised Copper Price(3)US$/lb3.624.23(14)4.01
Realised Cobalt Price(3)US$/lb14.8817.72(16)17.00
Average US$/Real Exchange Rate1.641.6031.63

(1) Average payability of 89%.
(2) Including prior period QP adjustments and excludes hedging
(3) Including prior period QP adjustments and realised hedging.

The unit cash costs for the quarter decreased by 15% to US$6.71/lb compared to the second quarter (US$7.85/lb) primarily due to higher nickel production volumes and improved mining efficiencies.  Mobile fleet availability improved due to the procurement of a twelve month tyre supply and the improved contractor drilling fleet performance resulted in record drilling meters during the quarter.   Unit costs were still adversely affected by a strong Real / USD exchange rate which averaged 1.64 for the quarter (Q2 2011: 1.60).

Unit production cash costs, in Brazilian Real, are expected to continue to fall over the next three quarters due to: increasing production levels with the expected achievement of full production rates by year end; ongoing incremental improvements in plant recovery; the arrival of new drill rigs expected at the end of Q1 2012; and the achievement of steady state operations.

CORPORATE

Funding

As at 30 September 2011, Mirabela held balances of cash on hand and on deposit of US$117 million. The decrease of US$26 million from 30 June 2011 is mainly due to the project capital expenditure programme. All project capital expenditure is on budget with the remaining capital expenditure expected to be completed by the end of the first quarter 2012.

The US$25 million held as cash collateral by the hedge financiers was released upon the perfection of the security on the mineral rights in their favour. The Company negotiated a release of a further US$25 million held in a Contingency Support Account ("CSA") by the hedge financiers. As a result of the release of the cash collateral and the CSA, Mirabela has now removed all liquidity covenants relating to the Company's hedge book.

The Company made the first bi-annual interest payment of US$17.3 million on the US$395 million of senior unsecured notes ("Notes") on 14 October 2011.  The Notes have a coupon rate of 8.75% and are due 2018.

Hedging

During September and October 2011, Mirabela closed all outstanding copper (8,844 tonnes) and nickel (10,626 tonnes) hedges for a cost of approximately US$20 million.  The Company now has no hedge positions.

Share Capital

As at 30 September 2011 the Company's issued share capital consisted of 491,781,237 ordinary shares, and a balance of 4,800,000 unlisted options and 1,568,276 performance rights were outstanding.

The Company issued 220,000 ordinary fully paid shares during the quarter as a result of the conversion of 220,000 Performance Rights in accordance with the Mirabela Nickel Ltd performance rights plan that was approved by Shareholders on 13 September 2010.

During the quarter 300,000 options were not exercised at the expiry date and have lapsed.