Lion Rock Resources IncTSXV: ROAR

King's Bay Gold Discovers New High-Grade Gold Zone at Bobjo Mine Project, South Bay Area, Red Lake

· Issued by Lion Rock Resources Inc

April 23, 2008- King's Bay Gold Corporation (TSX.V: KBG) and Mainstream Minerals Corporation (TSX.V-MJO) are pleased to announce that high grade gold intervals characteristic of a Red Lake vein type deposit have been intersected in Hole 25 at their joint-venture Bobjo Mine project, located in Earngey and Agnew Townships, Red Lake, Ontario.

Results Confirm Extension of Zones and Confirms Depth Extension

This project continues to be the site of new discoveries that so far included high-grade gold, strategic rare metals and rare earth elements. The partners are now pleased to report the discovery of a new high-grade gold zone located approximately 150 metres South of the main zones at a depth of 291.0 to 293.0 metres. The results extend existing mineralized zones and confirm depth extension.

Hole # 25   Interval From   Interval To   Interval Metres   Au (g/T)   
            1.50            4.50          3.00              5.77       
Incl.       1.50            2.50          1.00              14.55      
            241.50          242.20        0.70              1.94       
            291.00          293.00        2.00              19.61      
Incl.       292.00          293.00        1.00              43.73      
And         292.50          293.00        0.50              79.31      

The partners are also pleased to report that a third drill rig is now at work at this Bobjo project. A large 15,000 metre drilling program is well underway and more assay results will be announced very shortly when received and verified.

This Bobjo Mine project is located between the former South Bay Zinc / Copper Mine and Uchi Lake Gold Mine. It is noted that an existing power line passes through the southern part of the property and that it is within trucking distance to the Placer Dome / Goldcorp Mill in Red Lake, Ontario. It is comprised of 259 claim units totaling 10,360 acres. The area has a history of gold and base metal production dating back 80 years. The work presently being carried out by the partners represents the commencement of the first modern, systematic exploration of the property in the last 80 years when a two compartment shaft was sunk to 270 feet with two levels in 1929.

The partners are very pleased with the results of the holes reported to date on this Bobjo Mine Project. All zones are open in all directions and at depth. Included in the following table are the results of all holes received to date by the partners at this Bobjo Mine Project:

Hole        Dip   Interval From   Interval   Interval Metres   Au       
            To    (g/T)           
BJ07-01     -45   1.25            10.00      8.75              2.557    
including         1.50            2.00       0.50              5.056    
and               4.00            4.50       0.50              15.659   
and               9.50            10.00      0.50              18.184   
                                                                        
BJ07-02     -60   0.50            7.50       7.00              1.561    
including         3.90            4.40       0.50              2.958    
and               6.50            7.50       1.00              6.847    
                                                                        
BJ07-03     -85   2.00            6.40       4.40              2.235    
including         2.00            2.50       0.50              6.787    
and               5.00            5.40       0.40              4.289    
                  17.00           17.50      0.50              5.428    
                  24.50           25.00      0.50              2.517    
                                                                        
BJ07-04     -45   3.00            13.10      10.10             1.276    
including         8.30            13.10      4.80              2.051    
                  14.30           16.10      1.80              1.236    
                                                                        
BJ07-05     -45   12.20           12.80      0.60              1.332    
                  14.80           18.70      3.90              1.049    
including         18.20           18.70      0.50              4.448    
                  80.40           80.80      0.40              1.656    
                                                                        
BJ07-06     -50   2.00            3.10       1.10              32.950   
including         2.90            3.10       0.20              93.090   
                  3.10            3.50       0.40              1.450    
                  6.50            8.80       2.30              2.050    
                  9.20            9.80       0.60              1.150    
                  102.00          102.30     0.30              29.010   
Hole        Dip   Interval From   Interval   Interval Metres   Au       
            To    (g/T)           
BJ07-07     -60   1.60            2.70       1.10              8.701    
including         2.20            2.70       0.50              20.030   
                  5.50            6.50       1.00              1.731    
                  9.20            11.00      1.80              3.690    
including         9.20            10.00      0.80              6.290    
and               10.00           11.00      1.00              1.100    
                  13.80           14.20      0.40              1.460    
                  65.00           65.30      0.30              3.001    
                                                                        
BJ07-08     -60   1.00            8.50       7.50              1.683    
including         2.20            2.50       0.30              5.001    
and               8.00            8.50       0.50              12.001   
                  13.00           13.30      0.30              1.690    
                  67.70           69.00      1.30              2.501    
                                                                        
BJ07-09     -60   12.80           13.10      0.30              2.660    
                  13.50           15.00      1.50              6.250    
including         13.50           14.30      0.80              11.301   
                  14.30           15.30      1.00              1.060    
                  16.30           16.80      0.50              2.140    
                  24.00           27.40      3.40              8.450    
including         26.00           27.40      1.40              10.950   
                                                                        
BJ07-10     -50   5.60            6.60       1.00              2.930    
                                                                        
BJ07-11     -50   1.50            3.50       2.00              3.271    
including         1.50            2.00       0.50              8.501    
                  12.50           13.00      0.50              5.060    
                  89.10           89.50      0.40              1.011    
                  191.30          192.00     0.70              2.970    
                                                                        
BJ07-12     -50   0.50            2.50       2.00              4.955    
including         1.50            2.00       0.50              9.711    
                                                                        
BJ07-13     -50                                                NSV      
Hole        Dip   Interval From   Interval   Interval Metres   Au        
            To    (g/T)           
BJ07-14     -45   0.60            3.05       2.45              53.610    
including         0.60            1.80       1.20              118.880   
                  10.60           10.90      0.30              7.040     
                                                                         
BJ07-15     -85                                                NSV       
                                                                         
BJ07-16     -60   0.50            1.70       1.20              4.590     
                  7.00            8.00       1.00              2.550     
                                                                         
BJ07-17     -85   0.00            0.50       0.50              1.551     
                  3.00            3.50       0.50              2.962     
                  6.00            6.50       0.50              3.711     
                                                                         
BJ07-18     -70                                                NSV       
                                                                         
BJ07-19     -60   11.25           11.50      0.25              14.600    
                  12.00           12.40      0.40              6.061     
                  14.50           15.00      0.50              1.011     
                                                                         
BJ07-20     -60   0.50            1.00       0.50              2.821     
                  1.00            1.50       0.50              2.322     
                                                                         
BJ07-21     -60   11.50           12.00      0.50              1.470     
                  23.00           23.20      0.20              5.081     
                                                                         
BJ07-22     -85   8.50            9.50       1.00              2.140     
                  13.50           15.50      2.00              1.531     
                  20.00           22.00      2.00              4.140     
                  57.50           58.50      1.00              9.452     
                                                                         
BJ07-23     -60   0.50            1.00       0.50              1.671     
                  1.00            1.50       0.50              4.470     
                  1.50            2.00       0.50              3.252     
                  5.50            6.00       0.50              1.311     
                  6.00            6.50       0.50              4.252     
                  8.50            9.00       0.50              4.060     
                  9.00            9.50       0.50              12.800    
Hole        Dip   Interval From   Interval   Interval Metres   Au       
            To    (g/T)           
BJ07-25     -45   1.50            4.50       3.00              5.771    
including         1.50            2.50       1.00              14.550   
                  241.50          242.20     0.70              1.941    
                  291.00          293.00     2.00              19.611   
including         292.00          293.00     1.00              43.732   
and               292.50          293.00     0.50              79.311   

True Widths are not known.

NSV = No Significant Values

Holes # 14, 16, 20 and 23 Rare Metal and Rare Earth Elements Intersections

These four holes are situated along a fault structure with an approximate ten-kilometre strike length.

Hole # 14

A 40 ft intersection with a grade of 13.54 g/t Gallium (Ga), 21.50 g/t Scandium (Sc), 12.98 g/t Rubidium (Rb), 20.27 g/t Cerium (Ce), 8.25 g/t Lanthanum (La), 12.03 g/t Yttrium (Y), 1.83 g/t Ytterbium (Yb), 3.23 g/t Selenium (Se), 6.76 g/t Lithium (Li), 3.58 g/t Cadmium (Cd), 4.28 g/t Niobium (Nb), 2.25 g/t Hafnium (Hf), 38.57 g/t Cobalt (Co), 79.29 g/t Vanadium (V), 83.61 g/t Strontium (Sr), and 96.53 g/t Zirconium (Zr) at depth of 153.0 metres.

Hole # 16

A 43.6 ft intersection with a grade of 11.01 g/t Gallium (Ga), 16.53 g/t Scandium (Sc), 25.85 g/t Rubidium (Rb), 15.36 g/t Cerium (Ce), 6.53 g/t Lanthanum (La), 9.30 g/t Yttrium (Y), 3.77 g/t Selenium (Se), 11.44g/t Lithium (Li), 1.00 g/t Cadmium (Cd), 1.35 g/t Thorium (Th), 2.94 g/t Niobium (Nb), 1.40 g/t Hafnium (Hf), 48.57 g/t Cobalt (Co), 86.55 g/t Vanadium (V), 70.51 g/t Strontium (Sr), and 52.15 g/t Zirconium (Zr) at a depth of 258.0 metres.

Hole # 20

This hole intersected a 126 ft mineralized quartz carbonate zone. The partners only sent a few small sections for a quick test. This zone was intersected from 194.8 metres to 233.0 metres. Sections sent included: From 194.8 to 197.4 metres, 203.8 to 204.1 metres, 216.5 to 217.0 metres, 220.0 to 221.0 metres, 224.0 to 224.4 metres, 226.4 to 227.0 metres and 232.7 to 233.0 metres.

The average grade was 18.72 g/t Gallium (Ga), 21.42 g/t Scandium (Sc), 13.76 g/t Rubidium (Rb), 28.18 g/t Cerium (Ce), 11.85 g/t Lanthanum (La), 16.00 g/t Yttrium (Y), 5.00 g/t Selenium (Se), 11.09 g/t Lithium (Li), 3.42 g/t Cadmium (Cd), 1.48 g/t Thorium (Th), 6.19 g/t Niobium (Nb), 3.33 g/t Hafnium (Hf), 2.04 g/t Ytterbium (Yb), 42.37 g/t Cobalt (Co), 62.63 g/t Vanadium (V), 44.86 g/t Strontium (Sr), and 128.80 g/t Zirconium (Zr).

Hole # 23

This hole intersected a 250 ft mineralized quartz carbonate zone. The partners are expecting results to come in very shortly.

Rare Metals and Rare Earth Elements - Demand and Uses

Demand for rare metals and rare earth elements is soaring because of consumer demand for more fuel-efficient cars, alternative energy technologies such as fuel cells, the nuclear power industry for both practical and experimental utilization, rechargeable batteries, lasers, hydrogen storage, superalloys as used in the aerospace industry, televisions, cellular telephones, computer screens, permanent magnets as used in electric-hybrid vehicles and in the conductor industry for many of the new "Green" technologies, etc. Currently, 97% of the world supply of the Rare Earth Materials (REM) comes from China. China recently announced a reduction in the exports of REMs coming out of their mines. This decision will considerably reduce the supply for buyers outside of China while world demand is in full growth.

The main consumers of rare earth materials are in South-East Asia (Japan, Korea, Thailand, China) and in the USA. The United States used to be the largest consumer of rare earth materials, about 27% of the world's total. However, in recent years, China became the number one global consumer, exceeding the American consumption. The United States currently imports nearly 100% of their needs in REM, and the American market for rare earth materials is valued at more than 1 billion US dollars per year. It will soon become critical to produce these resources outside of China.

It is reported that 77% of world production is currently coming from one mine in China. The United States used to produce approximately 6% of the world's supply from one of the only in-situ rare earth mines in the world, at Mountain Pass, California. However, Mountain Pass — the only producing mine in North America — ceased operations several years ago, creating a situation where there is no Rare Earth Elements production taking place in North America, or anywhere significant outside of China. Therefore prices and demand are expected to continue to rise drastically.

The joint venture is 50 % Mainstream Minerals (TSX-V: MJO) and 50 % Kings Bay Gold (TSX-V: KBG) with Mainstream Minerals being the Operator of the project. John Archibald, A.P.G.O. - Geologist is the Qualified Person under National Instrument 43-101. All of the samples herein were analyzed by SGS Canada Inc.'s and Accurassay Labs.

About Kings Bay Gold

King's Bay Gold is unique in the industry in that it owns most of the equipment required to carry out the various phases of exploration. This includes diamond drills, bulldozers and other exploration equipment, which gives the company the ability to quickly adjust work programs as exploration results are realized and company strategies change.

KBG Shares Outstanding: 38,654,350 Approximate Cash on hand: $2.2 million

King's Bay Gold Corporation Richard Rivet President & CEO (204) 253-4653info@kingsbaygold.comwww.kingsbaygold.com

The TSX Venture Exchange has not reviewed and does not accept responsibility for the adequacy or accuracy of this release. Some of the statements contained in this release are forward-looking statements, such as estimates and statements that describe KBG's future plans, objectives or goals, including words to the effect that KBG or management expects a stated condition or result to occur. Since forward-looking statements address future events and conditions, by their very nature, they involve inherent risks and uncertainties.

Copyright (c) 2008 TheNewswire.ca - All rights reserved.