Kavango Resources: Hillside project processing plant commissioned

· Issued by Kavango Resources PLC via RNS

Summary by 6ix AI

Kavango Resources plc, a Southern Africa-focused metals exploration and gold development company, said Zimbabwe's Ministry of Mines & Mining Development Matabeleland South declared its 50 tonne per day pilot gold processing plant and tailings storage facility (where processing waste is stored) at the Hillside Gold Project commissioned and operational on October 30, 2026.

Key details

  • Both units were found to meet the applicable mining, safety and environmental requirements after a review of documentation and site visits in the week of October 26.
  • The plant processes ore through crushing, milling, gravity concentration (separating heavier gold particles) and a carbon-in-leach circuit, where dissolved gold is captured on carbon. Gold production rose from 397g at the first elution (removing gold from the carbon) in August to 539g in September.
  • The plant is a proof-of-concept facility meant to validate the processing flowsheet and support the design, manufacture and installation of a larger commercial-scale processing plant.
  • Bill's Luck Underground hosts a JORC-compliant (Australian reporting standard) Mineral Resource of 33,900 ounces of gold (Measured, Indicated and Inferred) at 2.68 grammes per tonne. Test work announced on May 20, 2026 on blends of Nightshift and Bill's Luck ore achieved gold recoveries of greater than 95% under laboratory conditions.
  • Infrastructure work underway includes installing a 13-metre headframe at the Bill's Luck Main Vertical Shaft, upgrading power and water supply, planning future exploration programmes and developing an enhanced employee accommodation camp.

What’s still pending

  • Kavango expects gold recoveries of between 90% and 93% under commercial plant conditions.
  • Kavango expects operational and metallurgical data from the pilot plant to inform future development and expansion decisions.

6ix AI wrote this summary from the release below and checked it against the release.

Kavango Resources PLC
02 November 2026
 

02 November 2026

Kavango Resources plc

(“Kavango” or the “Company”)

Hillside Gold Project processing plant successfully commissioned and operational

Kavango Resources plc (LSE: KAV, VFEX: KAV.VX), the Southern Africa-focused metals exploration and gold development company, is pleased to announce the successful statutory commissioning of its concept phase 50 tonne per day (“tpd”) gold processing plant (“the Plant”) at the Hillside Gold Project (“Hillside”) in Zimbabwe.

Highlights

  • The Ministry of Mines & Mining Development on 30 October 2026 permitted the commissioning of the 50tpd Hillside pilot processing plant and Tailings Storage Facility (“TSF”)
  • Plant processing ore through crushing, milling, gravity concentration and carbon-in-leach (“CIL”) circuit
  • Plant operating as a proof-of-concept facility to optimise processing performance and support design, manufacture and installation of a larger commercial scale processing plant
  • Bill's Luck hosts a JORC Mineral Resource of 33,900 ounces (“oz”) gold at 2.68 grammes per tonne (“g/t”), with expected plant recoveries of 90-93%
  • Development infrastructure upgrades are underway to support future production growth at Hillside

Jasper Musadaidzwa, Chief Executive Officer, commented:

“Achieving statutory commissioning of the processing plant and TSF is a significant milestone for Hillside and an important step towards commercial-scale operations.

“The concept phase plant enables us to optimise processing performance, confirm metallurgical recoveries under operating conditions and further refine our understanding of the orebody ahead of larger-scale development. With expected gold recoveries of 90-93% from Hillside, we believe the project has the potential to become a meaningful and scalable gold production centre within our portfolio.

“Alongside commissioning, we are continuing to upgrade site infrastructure to support future growth and expansion. Our focus is now on improving operational efficiencies and generating the technical and operating data required to support the design and development of a commercial-scale processing facility. Through this work, we are establishing the foundations to unlock the full value of the Hillside Gold Project.”

Statutory commissioning achieved for Plant and TSF

The Plant and TSF were both declared commissioned and operational by the Ministry of Mines & Mining Development Matabeleland South on 30 October 2026. Both units were found to meet compliance for the applicable mining, safety and environmental requirements after a review of appropriate documentation and site visits w/c 26th October.

The plant has been processing a combination of Run-of-Mine (“ROM”) ore, previously stockpiled gold-bearing sands and freshly milled sands from Hillside during commissioning. Gold continues to be successfully absorbed within the pilot CIL circuit, with gold production increasing from 397g at the first elution in August to 539g in September.

The Hillside pilot processing plant was developed as a proof-of-concept project to validate the Company's processing flowsheet and confirm expected metallurgical performance. The operational and metallurgical data generated are expected to inform future development and expansion decisions as Kavango advances Hillside toward larger-scale production.

Bill’s Luck Underground hosts a JORC-compliant Mineral Resource of 33,900 ounces of gold (Measured, Indicated and Inferred) at a grade of 2.68g/t. As announced on 20 May 2026, metallurgical test work undertaken on blends of Nightshift and Bill’s Luck ore achieved gold recoveries of greater than 95% under laboratory conditions, with expected operating recoveries of between 90% and 93% under commercial plant conditions.

Development work continues at Hillside

The Company is pleased to update the market on significant infrastructure development at Hillside as it prepares for the next phase of production growth. Several key workstreams are advancing, including the installation of a 13-metre headframe at Bill’s Luck Main Vertical Shaft, upgrades to power and water supply infrastructure, planning of future exploration programmes and the development of an enhanced employee accommodation camp.

Further information in respect of the Company and its business interests is provided on the Company's website at www.kavangoresources.com 

For further information, please contact:

Kavango Resources plc
Executive Chairman

Donald McAlister

+44 7887 481228

SP Angel Corporate Finance LLP

(Corporate Broker)
Ewan Leggat
ewan.leggat@spangel.co.uk

+44 203 470 0470

BlytheRay Ltd
(Financial PR)
Megan Ray/Said Izagaren
kavango@blytheray.com
+44 207 138 3204

Inter-Horizon Group
(Sponsoring Broker - Zimbabwe)
Lloyd Mlotshwa

lmlotshwa@ih-group.com

This information is provided by RNS, the news service of the London Stock Exchange. RNS is approved by the Financial Conduct Authority to act as a Primary Information Provider in the United Kingdom. Terms and conditions relating to the use and distribution of this information may apply. For further information, please contact rns@lseg.com or visit www.rns.com.

RNS may use your IP address to confirm compliance with the terms and conditions, to analyse how you engage with the information contained in this communication, and to share such analysis on an anonymised basis with others as part of our commercial services. For further information about how RNS and the London Stock Exchange use the personal data you provide us, please see our Privacy Policy.
 
END
 
 

Kavango Resources PLC on 6ix

Story so far

Earlier from Kavango Resources

All Kavango Resources news releases