Flames Well Operations
Filed with ASX · · 5 pages · English
• Circulation of drilling fluids to clean-up and remove any remaining debris from the milling of the isolation plugs and stimulation process has been completed successfully • Flames location has been connected to a gas sales pipeline and agas sales meter has been installed • Flowline manifold has been installed with the flowline connected from the well head to the tank battery and inspected Perth,