Dynacor Commences Processing First Ore at Pilot Plant in Senegal

· Issued by Dynacor Group Inc via GlobeNewswire

Summary by 6ix AI

Dynacor Group Inc., an ore processing company producing gold sourced from artisanal (small-scale) miners, has begun ore production at its Galam pilot plant in the Kédougou region of southeastern Senegal, in line with its schedule. It is also rehabilitating its Svetlana processing plant in Ecuador, targeting a restart in the fourth quarter of 2026.

Key details

  • The Galam pilot plant is over 95% complete. Commissioning of the laboratory and front-end process plant is complete and both are in use. Hot commissioning (start-up testing with ore) continues in the main process areas, including the grinding, leaching, gold refining and Merrill Crowe (gold recovery from solution) circuits.
  • An initial stockpile of gold-bearing ore has been built from local suppliers. The tailings storage facility cell, where processing waste is held, has been lined and is operational. Initial plant operator and maintenance positions are being filled.
  • Rehabilitation of the Svetlana plant has reached about 40% completion overall. The crushing circuit is 50% complete, the milling area is over 60% complete and the leaching area is almost halfway complete. Most replacement equipment has been secured.
  • Dynacor has submitted an application to the government of Ecuador for an Investment Protection Agreement and is advancing its commercialisation permit.

What’s still pending

  • Dynacor says Galam is on track for its first gold pour in August, and ore purchasing from additional supplier groups will continue in August.
  • Dynacor says all permits are on track for the fourth quarter of 2026.
  • A geotechnical review and laboratory testing of the Svetlana tailings pond, and an assessment of its laboratory, are ongoing.

6ix AI wrote this summary from the release below and checked it against the release.

MONTREAL, July 09, 2026 (GLOBE NEWSWIRE) -- Dynacor Group Inc. (TSX: DNG) ("Dynacor" or the "Corporation") is pleased to announce that ore production from its Galam pilot plant in the Kédougou region of southeastern Senegal has commenced, in line with its schedule.

Highlights

  • Pilot plant over 95% complete.

  • Commissioning of the laboratory and front-end process plant is complete, and both are in use.

  • Hot commissioning activities are ongoing in the main process areas, including the grinding, leaching, gold refining and Merrill Crowe circuits.

  • An initial stockpile of gold-bearing ore has been built from local suppliers, in line with our start-up target.

    • Purchasing of ore from additional supplier groups will continue in August

  • Initial plant operator and maintenance positions are being filled.

  • On track for first gold pour in August.

  • The tailings storage facility (TSF) cell has been lined and is operational.

Daniel Misiano, President & CEO of Dynacor, commented: "We are excited to highlight Galam's move from construction to commissioning. This is a significant achievement and a testament to the experience of the Dynacor team. So far, commissioning is proceeding to plan. When fully ramped-up, Galam will act as a blueprint for future commercial plants in Africa, which is expected to be the key driver of our expansion strategy.

Furthermore, rehabilitation of the Svetlana plant in Ecuador continues advancing towards our targeted Q4-2026 restart. With ongoing strong core operations and both new plants on schedule, we are poised for a strong second-half of the year."

Figure 1 – Introduction of Mill Feed at Galam Pilot Plant in Senegal

Advancing Ecuador Plant Upgrade to Plan

Rehabilitation work on the Svetlana processing plant continues to advance across the following key operational areas:

  • Overall rehabilitation of the plant has reached about 40% completion.

  • Crushing circuit - Rehabilitation of the primary raw material feed and crushing circuit is 50% complete. Remaining work includes upgrade of the cone crusher and hydraulic feeder, in addition to replacement of conveyor belts, chute lining and pulley systems.

  • Milling area – Rehabilitation of the ball mill and supporting infrastructure is over 60% complete. Work includes upgrade of the release motor and pinion bearings, and alignment of the girth gear and pinions.

  • Electrical / power systems – Installation of electrical substation transformers and rehabilitation of cabling for key equipment is progressing.

  • Leaching area – Rehabilitation of the leaching tanks including baffle replacement and air-slurry redesign is almost halfway complete.

  • Purchasing – Most replacement pieces of equipment have been secured.

  • Tailings – A geotechnical review and laboratory testing of the working tailings pond is ongoing.

  • Laboratory – Assessment of the laboratory is ongoing with a view to its rehabilitation and installation of Atomic Absorption Spectroscopy (AAS) equipment.

  • Permitting – Dynacor has submitted its application for an Investment Protection Agreement to the government of Ecuador and is advancing its commercialisation permit. All permits are on track for Q4-2026.

About Dynacor

Dynacor Group is an ore processing company dedicated to producing gold sourced from artisanal miners. Since its establishment in 1996, Dynacor has pioneered a responsible mineral supply chain with stringent traceability and audit standards for the fast-growing artisanal mining industry. By focusing on formalized miners, the Canadian company offers a win-win approach for governments and miners globally. Dynacor operates the Veta Dorada plant and owns a gold exploration property in Peru. The company is expanding to West Africa and within Latin America.

The premium paid by luxury jewellers for Dynacor's PX Impact® gold goes to Fidamar Foundation, an NGO that mainly invests in health and education projects for artisanal mining communities in Peru. Visit www.dynacor.com for more information.

Forward-Looking Information

Certain statements in the preceding may constitute forward-looking statements, which involve known and unknown risks, uncertainties and other factors that may cause the actual results, performance or achievements of Dynacor, or industry results, to be materially different from any future result, performance or achievement expressed or implied by such forward-looking statements. These statements reflect management's current expectations regarding future events and operating performance as of the date of this news release.

Contact:

For more information, please contact:

Ruth Hanna
Director, Investor Relations
T: 514-393-9000 #236
E: investors@dynacor.com
Website: https://dynacor.com

Renmark Financial Communications Inc.
Bettina Filippone
T: (416) 644-2020 or (212) 812-7680
E: bfilippone@renmarkfinancial.com  
Website: www.renmarkfinancial.com

A photo accompanying this announcement is available at https://www.globenewswire.com/NewsRoom/AttachmentNg/047ed635-81f8-4736-ae53-6d7673bc214b