Since arriving at the Dorado-2 location, approximately 2.2 km from the original Dorado-1 well location, the rig has successfully concluded the ready to operate process and has drilled the surface hole and installed the surface casing. Forward Plan The rig will drill the 17 1/2” hole to the planned section depth of approximately 1,200 metres Measured Depth (“MD”) followed by setting the 13-3/8” cas