MARCH QUARTERLY REPORT
30 APRIL 2008
PERTH, Western Australia, April 30 /CNW/ -
QUARTERLY HIGHLIGHTS
- New Spektra drilling rig arrived on site at the Segilola Project in
Nigeria, the most advanced gold project in the country and a 10,000m
drilling program has commenced
- Feasibility Study underway and progressing well for the Mkushi Copper
Project in Zambia
- Masbate construction is ahead of schedule by 4 weeks
- Mining Alliance Agreement with Leighton Contractors (Philippines)
Incorporated ("Leighton") executed with a 6 year term and total
contract value of US$170M
- Significant milestone of 1,000,000 manhours reached with no lost time
injury
- Construction currently 45% complete, with engineering and design 55%
complete
- All refurbishment works completed on the SAG mill and it is ready for
shipment to the Philippines
- Work commenced under the Mining Alliance Agreement on the tailings
storage facility ("TSF")
- Leighton to manage procurement and installation of 3 Sulzer power
units with a 32 mw capacity under a variation to the fixed price lump
sum contract
- Final credit approvals secured by a number of banks and signing of an
US$80.3m project finance facility expected in the June quarter
- Development expenditure on Masbate to March 31 of US$38.6M and total
cash reserves of US$47.7M
- New high grade system discovered at Libra (Masbate Project)
including:
37m @ 3.57 g Au /t
19m @ 9.39 g Au /t
27m @ 9.88 g Au /t
42m @ 10.51 g Au/t
29m @ 4.70 g Au/t
During the three months ending 31 March 2008, CGA Mining Limited's ("CGA", the "Company") activities focused on the development on the Masbate Gold Project in the Philippines and commencement of the detailed feasibility study for the Mkushi Copper Project in Zambia.
MASBATE PROJECT UPDATE
----------------------
Process Plant and Infrastructure
--------------------------------
Leighton Scope
The total construction program is currently 45% complete.
Lycopodium Engineering Pty Ltd ("Lycopodium") continued to carry out the engineering design activities to provide technical specifications and technical drawings to the Leighton construction team on site. As of March 31, the engineering/design was 55% complete.
For images please see http://files.newswire.ca/621/CGA.doc.
During the quarter the following site activities continued or were
commenced:
- earthworks for all amenities and installations at the processing
plant;
- mobilisation of the second concrete batch plant;
- construction office, laboratory and warehouse erected and fully
operational;
- completion of the contract labour accommodation;
- construction of the permanent staff accommodation and messing
facility - 87% complete;
- Carbon in Leach ("CIL") tankage erection - 63% complete;
- primary crusher foundations;
- bin and conveyor foundations; and
- reagent mixing tank, desorption column and gold room foundations.
In addition a number of offsite activities and fabrications were
commissioned by Leighton:
- steelwork to be located above CIL tanks;
- tank launders;
- disposal tanks;
- elution columns; and
- mixing tanks.
For images please see http://files.newswire.ca/621/CGA.doc.
Leighton continues to expedite the orders placed for all of the mechanical equipment. As of the 31 March all deliveries were on schedule.
SAG Mill Refurbishment
The mill as was moved from the storage facility in Spokane, Washington State to the Weir Minerals (Australia) Ltd ("Weir") workshop facility in Edmonton, Canada. As of 31 March, all refurbishment works have been completed and checked and will be prepared for sea freight to Cebu, Philippines.
All mill ancillary equipment motors, gearboxes etc. are in the process of refurbishment. Mill electrics are being designed by BEC Engineering Pty Ltd ("BEC"), a Perth based company specialising in work of this nature.
Ball Mill
The ball mills located in Cebu have been stripped of the ancillary equipment. Gearboxes are being refurbished in Perth. Motor rewinds are being carried out by ABB Electrical Asea Brown Boveri, Inc. ("ABB") in the Philippines.
As of 31 March, ball mill refurbishment is on schedule.
The design of the mills general arrangement and the associated engineering is being carried out by Metso, Metso Minerals (Australia) Ltd ("Metso") Weir and Lycopodium.
Tailings Storage Facility
GHD Engineering Pty Ltd ("GHD") completed the design of the facility to accommodate the tailings resulting from treatment of the existing announced mining reserve (37.5 million tonne). Construction of the facility forms part of the Mining Alliance Agreement and as such is the responsibility of Leighton. Work commenced in March on the clearing of the tailings pipeline route and the excavation of the keyway below the main embankment. The tailings storage facility is expected to be ready for commissioning by November 30.
For images please see http://files.newswire.ca/621/CGA.doc.
Mining
------
The Mining Alliance Agreement with Leighton was executed on 20 March. The agreement is for six years and includes the supply of all mining/earthmoving equipment, maintenance and personnel to mine the ore and associated waste material. The agreement allows for a three month pre commissioning period.
For images please see http://files.newswire.ca/621/CGA.doc.
Power
-----
During the quarter, the power arrangements have been finalised with the plan to acquire 3 Sulzer units currently utilised in China to provide a 32 mw capacity on site. This has the advantage of both lower operating costs (due to the efficiencies of the equipment) and ownership of power supply from commencement of operations (ie no reliance on third parties). The units have been inspected by our power consultants, Poyry Pic and Leighton has agreed to manage procurement, shipping, installation (with related site works) and commissioning of the units under a variation to the fixed price lump sum construction contract. The total estimated capital cost (which includes a reallocation from the operating budget) is US$25m including all related site works.
Work has also continued on the longer term power plans of construction of a coal fired power station on the project site.
Safety Milestones
-----------------
The Masbate Gold Project achieved a major safety milestone on the 8th April 2008 with 1,000,000 man hours completed without any time lost to injury.
This milestone has been achieved with the constant commitment by CGA, Phil Gold Processing and Refining Corp, Filminera Resources Corporation and its Masbate Gold Project team to ensure that safety to its employees and subcontractors is paramount.
The Masbate Gold Project management team and the head contractor to the project, Leighton have treated safety as a high priority on the project site and this cooperation has lead to this milestone being obtained.
Exploration
-----------
During the quarter both the diamond drill and a reverse circulation drill continued to test the prospectivity of some areas in the immediate vicinity of known resources at the Masbate Project. During the quarter two regions were targeted, the Libra North and Panique areas.
A location map showing these areas is shown in Figure 1 available at http://files.newswire.ca/621/CGA.doc.
The Libra North area lies immediately along strike and to the north-west of the current designed Masbate open pits and within 200 metres of the planned ROM pad; in the previous quarter high grade assay results were reported from this vicinity, follow up drilling during this reporting period has again returned significant intercepts, the results of which are reported in Table 1 below.
Table 1
Libra North Area Intercepts
-------------------------------------------------------------------------
LIBRA DRILL HOLES
-------------------------------------------------------------------------
SIGNIFICANT INTERCEPTS
-------------------------------------------------------------------------
AVERAGE
HOLE ID NORTHINGS EASTINGS AZIMUTH DIP FROM TO WIDTH ASSAY RESULT
-------------------------------------------------------------------------
MEXRC01A 25715 29565.23 30 70 0 2 2.00 2.08
-------------------------------------------------------------------------
MEXRC01A 25715 29565.23 30 70 5 11 6.00 2.60
-------------------------------------------------------------------------
MEXRC01A 25715 29565.23 30 70 16 19 3.00 1.13
-------------------------------------------------------------------------
MEXRC01A 25715 29565.23 30 70 21 58 37.00 3.56
-------------------------------------------------------------------------
MEXRC02 25746 29526.19 30 60 4 10 6.00 7.92
-------------------------------------------------------------------------
MEXRC02A 25742 29521.69 30 60 4 7 3.00 1.15
-------------------------------------------------------------------------
MEXRC02A 25742 29521.69 30 60 8 11 3.00 2.07
-------------------------------------------------------------------------
MEXRC02A 25742 29521.69 30 60 21 40 19.00 9.39
-------------------------------------------------------------------------
MEXRC04 25769 29485.29 30 60 26 53 27.00 9.87
-------------------------------------------------------------------------
MEXRC04 25769 29485.29 30 60 56 57 1.00 3.65
-------------------------------------------------------------------------
MEXRC04 25769 29485.29 30 60 64 68 4.00 2.66
-------------------------------------------------------------------------
MEXRC04 25769 29485.29 30 60 74 86 12.00 1.74
-------------------------------------------------------------------------
MEXRC04 25769 29485.29 30 60 89 91 2.00 3.26
-------------------------------------------------------------------------
MEXRC07 25709 29617.93 30 60 12 14 2.00 2.58
-------------------------------------------------------------------------
MEXRC07 25709 29617.93 30 60 112 114 2.00 2.24
-------------------------------------------------------------------------
MEXRC09 25767 29537.76 30 60 1 2 1.00 1.37
-------------------------------------------------------------------------
MEXRC09 25767 29537.76 30 60 46 48 2.00 0.92
-------------------------------------------------------------------------
MEXRC10 25792 29495.03 30 60 0 5 5.00 1.16
-------------------------------------------------------------------------
MEXRC10 25792 29495.03 30 60 67 68 1.00 1.29
-------------------------------------------------------------------------
MEXRC11 25812 29449.13 30 60 2 3 1.00 1.03
-------------------------------------------------------------------------
MEXRC11 25812 29449.13 30 60 15 22 7.00 13.43
-------------------------------------------------------------------------
MEXRC11 25812 29449.13 30 60 66 67 1.00 1.07
-------------------------------------------------------------------------
MEXRC11 25812 29449.13 30 60 117 120 3.00 0.91
-------------------------------------------------------------------------
MEXRC12 25690 29607.74 30 60 1 43 42.00 10.51
-------------------------------------------------------------------------
MEXRC12 25690 29607.74 30 60 67 68 1.00 0.95
-------------------------------------------------------------------------
MEXRC12 25690 29607.74 30 60 78 79 1.00 1.33
-------------------------------------------------------------------------
MEXRC12 25690 29607.74 30 60 113 115 2.00 1.29
-------------------------------------------------------------------------
MEXRC13 25671 29596.37 30 60 0 7 7.00 1.70
-------------------------------------------------------------------------
MEXRC13 25671 29596.37 30 60 61 90 29.00 4.70
-------------------------------------------------------------------------
MEXRC14 25645 29639.88 30 60 16 64 48.00 2.80
-------------------------------------------------------------------------
MEXRC16 25599 29677.19 30 60 25 26 1 7.94
-------------------------------------------------------------------------
MEXRC16 25599 29677.19 30 60 37 38 1 2.24
-------------------------------------------------------------------------
MEXRC16 25599 29677.19 30 60 50 52 2 2.80
-------------------------------------------------------------------------
MEXRC16 25599 29677.19 30 60 71 72 1 1.23
-------------------------------------------------------------------------
MEXRC16 25599 29677.19 30 60 76 79 3 1.30
-------------------------------------------------------------------------
MEXRC16 25599 29677.19 30 60 82 96 14 4.20
-------------------------------------------------------------------------
MEXRC18 25575 29716.34 30 60 40 41 1 1.44
-------------------------------------------------------------------------
MEXRC18 25575 29716.34 30 60 93 97 4 3.20
-------------------------------------------------------------------------
MEXRC20 25572 29767.65 30 60 8 12 4 4.22
-------------------------------------------------------------------------
MEXRC20 25572 29767.65 30 60 88 90 2 3.84
-------------------------------------------------------------------------
MSHRC41 25725 29513.94 30 60 50 55 5 1.80
-------------------------------------------------------------------------
MSHRC41 25725 29513.94 30 60 70 75 5 2.70
-------------------------------------------------------------------------
MSHRC41 25725 29513.94 30 60 107 120 13 2.31
-------------------------------------------------------------------------
During the quarter in the Libra North area, 21 reverse-circulation drillholes were completed for a total of 1706 metres. The results of this drilling are extremely encouraging and will enable the designed open pit to be expanded in this area. Geological interpretation has been completed and geological/geostatistical block model of this additional data is underway.
In the Panique region both reverse circulation and diamond drilling was carried out with the aim of converting the current inferred resource material to a reserve status. During the quarter, 42 RC holes were completed (3,653m) and 6 diamond tails were completed (473m) for a total of 4,126m.
Table 2
Panique Area Intercepts
-------------------------------------------------------------------------
PANIQUE DRILL HOLES
-------------------------------------------------------------------------
SIGNIFICANT INTERCEPTS
-------------------------------------------------------------------------
ASSAY
HOLE ID NORTHING EASTING AZIMUTH DIP TO FROM WIDTH AU PPM
-------------------------------------------------------------------------
PNQRC20 24592 30234 246 60 56 57 1 1.27
-------------------------------------------------------------------------
PNQRC27 24591 30378 246 60 11 13 2 1.11
-------------------------------------------------------------------------
PNQRC27 24591 30378 246 60 109 111 2 0.44
-------------------------------------------------------------------------
PNQRC26 24582 30358 246 60 8 10 2 0.73
-------------------------------------------------------------------------
PNQRC34 24528 30384 246 65 33 36 3 14.36
-------------------------------------------------------------------------
PNQRC46 24432 30468 246 60 87 91 4 1.00
-------------------------------------------------------------------------
PNQRC41 24482 30435 246 60 0 12 12 1.40
-------------------------------------------------------------------------
PNQRC41 24482 30435 246 60 25 26 1 0.44
-------------------------------------------------------------------------
PNQRC41 24482 30435 246 60 48 49 1 0.40
-------------------------------------------------------------------------
PNQRC41 24482 30435 246 60 62 63 1 0.56
-------------------------------------------------------------------------
PNQRC41 24482 30435 246 60 66 73 7 0.60
-------------------------------------------------------------------------
PNQRC65 24302 30619 246 60 19 21 2 1.50
-------------------------------------------------------------------------
PNQRC65 24302 30619 246 60 43 44 1 1.32
-------------------------------------------------------------------------
PNQRC65 24302 30619 246 60 62 63 1 1.45
-------------------------------------------------------------------------
PNQRC65 24302 30619 246 60 74 75 1 0.43
-------------------------------------------------------------------------
PNQRC65 24302 30619 246 60 89 91 2 2.03
-------------------------------------------------------------------------
PNQRC65 24302 30619 246 60 96 97 1 1.15
-------------------------------------------------------------------------
PNQRC60 24378 30639 246 60 12 14 2 1.15
-------------------------------------------------------------------------
PNQRC48 24482 30757 246 60 22 23 1 1.14
-------------------------------------------------------------------------
PNQRC48 24482 30757 246 60 49 55 6 4.60
-------------------------------------------------------------------------
PNQRC22 24462 30343 246 60 1 9 8 0.70
-------------------------------------------------------------------------
PNQRC22 24462 30343 246 60 15 16 1 0.40
-------------------------------------------------------------------------
PNQRC22 24462 30343 246 60 33 39 6 0.60
-------------------------------------------------------------------------
PNQRC22 24462 30343 246 60 40 41 1 0.62
-------------------------------------------------------------------------
PNQRC22 24462 30343 246 60 42 43 1 0.52
-------------------------------------------------------------------------
PNQRC22 24462 30343 246 60 60 61 1 0.60
-------------------------------------------------------------------------
PNQRC3 24642 30270 246 65 6 8 2 0.38
-------------------------------------------------------------------------
PNQRC3 24642 30270 246 65 56 57 1 1.02
-------------------------------------------------------------------------
PNQRC3 24642 30270 246 65 58 61 3 0.80
-------------------------------------------------------------------------
PNQRC3 24642 30270 246 65 66 68 2 2.00
-------------------------------------------------------------------------
PNQRC3 24642 30270 246 65 74 77 3 0.60
-------------------------------------------------------------------------
PNQRC3 24642 30270 246 65 80 81 1 0.35
-------------------------------------------------------------------------
PNQRC3 24642 30270 246 65 82 83 1 0.69
-------------------------------------------------------------------------
PNQRC4 24891 30305 246 65 1 3 2 6.50
-------------------------------------------------------------------------
PNQRC4 24891 30305 246 65 15 20 5 3.10
-------------------------------------------------------------------------
PNQRC4 24891 30305 246 65 40 43 3 2.70
-------------------------------------------------------------------------
PNQRC7A 24808 30256 246 60 0 3 3 1.00
-------------------------------------------------------------------------
PNQRC7A 24808 30256 246 60 7 10 3 1.50
-------------------------------------------------------------------------
PNQRC7A 24808 30256 246 60 13 14 1 2.01
-------------------------------------------------------------------------
PNQRC7A 24808 30256 246 60 44 45 1 0.50
-------------------------------------------------------------------------
PNQRC7A 24808 30256 246 60 46 47 1 0.30
-------------------------------------------------------------------------
PNQRC7A 24808 30256 246 60 48 50 2 1.20
-------------------------------------------------------------------------
PNQRC7A 24808 30256 246 60 52 53 1 0.97
-------------------------------------------------------------------------
PNQRC7A 24808 30256 246 60 60 65 5 0.50
-------------------------------------------------------------------------
PNQRC5 24699 30037 66 60 1 9 8 0.70
-------------------------------------------------------------------------
PNQRC5 24699 30037 66 60 11 13 2 0.89
-------------------------------------------------------------------------
PNQRC5 24699 30037 66 60 111 117 6 0.60
-------------------------------------------------------------------------
PNQRC9 24829 30328 66 60 19 21 2 1.09
-------------------------------------------------------------------------
PNQRC9 24829 30328 66 60 58 61 3 1.50
-------------------------------------------------------------------------
PNQRC9 24829 30328 66 60 97 106 9 1.10
-------------------------------------------------------------------------
PNQRC9 24829 30328 66 60 107 108 1 0.40
-------------------------------------------------------------------------
PNQRC9 24829 30328 66 60 115 117 2 1.70
-------------------------------------------------------------------------
PNQRC8 24829 30328 246 75 0 4 4 0.60
-------------------------------------------------------------------------
PNQRC8 24829 30328 246 75 6 8 2 1.00
-------------------------------------------------------------------------
PNQRC8 24829 30328 246 75 12 14 2 0.31
-------------------------------------------------------------------------
PNQRC8 24829 30328 246 75 24 26 2 0.60
-------------------------------------------------------------------------
PNQRC8 24829 30328 246 75 40 42 2 0.60
-------------------------------------------------------------------------
PNQRC8 24829 30328 246 75 46 50 4 3.40
-------------------------------------------------------------------------
PNQRC8 24829 30328 246 75 52 53 1 0.39
-------------------------------------------------------------------------
PNQRC8 24829 30328 246 75 56 58 2 1.50
-------------------------------------------------------------------------
PNQRC8 24829 30328 246 75 61 63 2 0.60
-------------------------------------------------------------------------
PNQRC8 24829 30328 246 75 67 71 4 0.80
-------------------------------------------------------------------------
PNQRC8 24829 30328 246 75 75 80 5 0.63
-------------------------------------------------------------------------
PNQRC6 24754 30157 246 60 2 4 2 0.48
-------------------------------------------------------------------------
PNQRC6 24754 30157 246 60 10 12 2 0.32
-------------------------------------------------------------------------
PNQRC6 24754 30157 246 60 20 24 4 0.36
-------------------------------------------------------------------------
PNQRC6 24754 30157 246 60 28 30 2 0.32
-------------------------------------------------------------------------
PNQRC12 24739 30261 246 60 15 16 1 0.40
-------------------------------------------------------------------------
PNQRC12 24739 30261 246 60 28 30 2 1.40
-------------------------------------------------------------------------
PNQRC12 24739 30261 246 60 40 41 1 0.37
-------------------------------------------------------------------------
PNQRC18A 24694 30326 246 60 9 13 4 1.23
-------------------------------------------------------------------------
PNQRC19 24724 30378 246 60 2 13 11 0.46
-------------------------------------------------------------------------
PNQRC19 24724 30378 246 60 17 25 8 0.41
-------------------------------------------------------------------------
PNQRC19 24724 30378 246 60 30 33 3 0.95
-------------------------------------------------------------------------
PNQRC40 24447 30352 66 70 0 2 2 0.31
-------------------------------------------------------------------------
PNQRCD5 24699 30037 65 60 124 125 1 0.92
-------------------------------------------------------------------------
PNQRCD5 24699 30037 65 60 126 127 1 0.56
-------------------------------------------------------------------------
PNQRCD5 24699 30037 65 60 129 131 2 0.50
-------------------------------------------------------------------------
PNQRCD5 24699 30037 65 60 142.1 144.1 2 0.40
-------------------------------------------------------------------------
PNQRCD5 24699 30037 65 60 145.1 150.1 5 1.92
-------------------------------------------------------------------------
PNQRCD5 24699 30037 65 60 151.1 153.1 2 1.50
-------------------------------------------------------------------------
PNQRCD5 24699 30037 65 60 167.1 170.1 3 0.63
-------------------------------------------------------------------------
PNQRCD5 24699 30037 65 60 171.7 172.4 0.7 0.71
-------------------------------------------------------------------------
PNQRCD5 24699 30037 65 60 175.4 176.4 1 0.37
-------------------------------------------------------------------------
PNQRC35 24546 30434 246 65 25 26 1 1.42
-------------------------------------------------------------------------
PNQRC35 24546 30434 246 65 31 32 1 0.49
-------------------------------------------------------------------------
PNQRC35 24546 30434 246 65 42 43 1 0.44
-------------------------------------------------------------------------
PNQRC35 24546 30434 246 65 48 49 1 0.80
-------------------------------------------------------------------------
PNQRC35 24546 30434 246 65 58 59 1 0.88
-------------------------------------------------------------------------
PNQRC35 24546 30434 246 65 70 71 1 0.32
-------------------------------------------------------------------------
PNQRC35 24546 30434 246 65 85 87 2 0.60
-------------------------------------------------------------------------
PNQRC35 24546 30434 246 65 88 90 2 1.30
-------------------------------------------------------------------------
PNQRC35 24546 30434 246 65 96 101 5 1.23
-------------------------------------------------------------------------
PNQRC35 24546 30434 246 65 29 31 2 0.40
-------------------------------------------------------------------------
PNQRC57 24290 30444 246 75 46 47 1 0.98
-------------------------------------------------------------------------
PNQRC57 24290 30444 246 75 93 97 4 4.60
-------------------------------------------------------------------------
PNQRC57 24290 30444 246 75 98 99 1 1.25
-------------------------------------------------------------------------
PNQRC57 24290 30444 246 75 100 101 1 0.34
-------------------------------------------------------------------------
PNQRC57 24290 30444 246 75 108 110 2 0.50
-------------------------------------------------------------------------
PNQRC57 24290 30444 246 75 116 118 2 0.60
-------------------------------------------------------------------------
PNQRC53 24386 30512 246 75 64 65 1 0.39
-------------------------------------------------------------------------
PNQRC53 24386 30512 246 75 66 67 1 1.77
-------------------------------------------------------------------------
PNQRC53 24386 30512 246 75 74 76 2 0.32
-------------------------------------------------------------------------
PNQRC53 24386 30512 246 75 92 96 4 0.70
-------------------------------------------------------------------------
PNQRC53 24386 30512 246 75 108 110 2 0.54
-------------------------------------------------------------------------
PNQRC53 24386 30512 246 75 112 117 5 0.50
-------------------------------------------------------------------------
PNQRC53 24386 30512 246 75 119 120 1 0.35
-------------------------------------------------------------------------
For Figures 2 and 3 please see http://files.newswire.ca/621/CGA.doc.
Expenditure
As of 31 March 2007, the group had spent approximately US$38.6M on development of the project, with total cash reserves at the same date of US$47.7M (including the cash reserves of Filminera Resources Corporation).
Project Finance Facility
Significant progress has been made on the project debt finance facility during the quarter. A number of banks have now secured their final credit approval for participation in the financing and final documentation is expected to be signed shortly. The project finance facility has been increased from US$65M to US$80.3M to consolidate the funding for the project power arrangements with the banking facility. As with all project finance facilities it will be subject to normal conditions precedent, which are presently on track to be satisfied for a drawdown in the second quarter of 2008.
MKUSHI PROJECT UPDATE
---------------------
Good progress has been made on the various components of the detailed feasibility study, which is on track for completion in the last quarter of 2008. An application for a Mining Licence over the Mkushi deposit and adjacent prospects with resource potential was submitted during February.
Drill results received during the quarter indicate potential for additional resources in the old Munshiwemba Pit and support our geological interpretations of H, L, and G Zones. An independent resource estimate to JORC and 43-101 guidelines is due for completion in the September quarter and will include all data that was not available at the time of the preliminary study.
Exploration work by our partner African Eagle Resources pic ("AFE") has intersected significant mineralisation at the Munda prospect and identified several new soil geochemical copper anomalies within the wider 476 sq km prospecting licence.
Detailed Feasibility Study - Summary
The feasibility study ("FS") is currently underway with Bateman Engineering Pty Ltd/Metplant, Metplant Engineering Services Pty Ltd (Metplant) being the principal consulting group carrying out the feasibility study for the process plant area. The geotechnical drilling has been completed and the report, being prepared by African Mining Consultants Ltd Zambia ("AMC"), is expected in the next month. The Environmental Impact Assessment has also been completed by AMC and has been presented to the authorities for review.
Snowden Mining Industry Consultants Pty Ltd ("Snowden"), Perth, has been engaged to prepare the NI 43-101 for the reserves and resources.
Discussions are advanced with the two main power suppliers in Zambia to provide a secure supply of power to the operation. In addition, discussions have commenced with smelter operations in Zambia concerning possible off-take agreements.
Completion of the FS is on track for the last quarter of 2008.
Resource Drilling & Estimation
The resource evaluation drilling programme at Munshiwemba H Zone has been completed and drill rigs transferred to our joint venture partner, Katanga Resources Ltd, for drilling programmes on additional exploration targets within the joint venture licence areas. Success on these targets could result in an increase in the resource base at the Mkushi Project. It is anticipated that further resource drilling at Munshiwemba H Zone and other core area prospects will recommence after the completion of the FS.
Results received during the quarter indicate potential for additional resources in the old Munshiwemba Pit (north east of G Zone) and have confirmed geological interpretations at H, L, and G Zones.
A close spaced vertical reverse circulation programme on a 10m x 10m grid at G Zone has also confirmed the continuity of copper mineralisation, based on visual observations as few laboratory results for this programme are yet available.
Significant new drill intersection results can be found in Table 3.
Table 3
Mkushi Area Intercepts
-------------------------------------------------------------------------
MKUSHI PROJECT
-------------------------------------------------------------------------
SIGNIFICANT INTERSECTIONS (greater than)1% CU
-------------------------------------------------------------------------
CU
GRADE
HOLE NO PROSPECT EAST NORTH AZIMUTH DIP FROM TO WIDTH % TYPE
-------------------------------------------------------------------------
MH029 H ZONE 731208 8456791 142 -50 142 147 5 1.008 DD
-------------------------------------------------------------------------
MH029 H ZONE 731208 8456791 142 -50 150 153 3 1.89 DD
-------------------------------------------------------------------------
MH084 LZONE 731050 8456855 142 -50 137 144 7 1.26 DD
-------------------------------------------------------------------------
MH084 LZONE 731050 8456855 142 -50 206 207 1 3.95 DD
-------------------------------------------------------------------------
MH085 H ZONE 731216 8456882 142 -50 25 30 5 1.03 DD
-------------------------------------------------------------------------
MH094 H ZONE 730761 8456299 142 -50 48 49 1 1.53 RC
-------------------------------------------------------------------------
MH098 H ZONE 730818 8456396 142 -50 28 31 3 1.69 RC
-------------------------------------------------------------------------
MH098 H ZONE 730818 8456396 142 -50 37 39 2 1.09 RC
-------------------------------------------------------------------------
MH099 H ZONE 730788 8456435 142 -50 83 84 1 1.88 RC
-------------------------------------------------------------------------
MH100 H ZONE 730788 8456435 142 -50 174.5 179 4.5 1.87 DD
-------------------------------------------------------------------------
MH100 H ZONE 730788 8456435 142 -50 182 185 3 1.64 DD
-------------------------------------------------------------------------
MMU050 MUNSHIWEMBA 731623 8457676 142 -50 17 20 3 1.99 DD
-------------------------------------------------------------------------
MMU050 MUNSHIWEMBA 731623 8457676 142 -50 31 57 26 1.75 DD
-------------------------------------------------------------------------
MMU051 MUNSHIWEMBA 731596 8457631 142 -50 48 57 9 2.71 DD
-------------------------------------------------------------------------
MMU052A MUNSHIWEMBA 731595 8457632 142 -50 50 53 3 1.19 DD
-------------------------------------------------------------------------
MMU053 MUNSHIWEMBA 731552 8457381 322 -50 57 65 8 4.65 RC
-------------------------------------------------------------------------
MMU053 MUNSHIWEMBA 731552 8457381 322 -50 70 74 4 2.63 RC
-------------------------------------------------------------------------
MMU053 MUNSHIWEMBA 731552 8457381 322 -50 93 96 3 1.1 RC
-------------------------------------------------------------------------
MMU055 MUNSHIWEMBA 731668 8457616 142 -50 8 13 5 1.17 RC
-------------------------------------------------------------------------
MMU057 MUNSHIWEMBA 731723 8457703 142 -50 11 16 5 2.068 RC
-------------------------------------------------------------------------
MMU060 MUNSHIWEMBA 731633 8457586 142 -50 20 29 9 1.74 RC
-------------------------------------------------------------------------
MMUP038 G ZONE 731547 8457288 0 -90 11 16 5 2.67 VertRC
-------------------------------------------------------------------------
MMUP039 G ZONE 731542 8457301 0 -90 0 11 11 1.27 VertRC
-------------------------------------------------------------------------
MMUP045 G ZONE 731564 8457345 0 -90 9 19 10 1.15 VertRC
-------------------------------------------------------------------------
Geotechnical Study
The geotechnical diamond drilling programme has been completed and a report is being prepared by AMC for inclusion in the FS.
Sterilisation Drilling
A 4,100m reverse circulation programme has been completed on proposed sites for plant, waste and tailings facilities. No mineralisation of significance was located and sites are now adequately sterilised for infrastructure.
Licences
An application for a Mining Licence over the Mkushi deposit and adjacent prospects with resource potential was submitted to the Zambian Ministry of Mines on 12 February 2008. The Environmental Impact Assessment ("EIA") prepared by AMC has been completed and submitted for review and approval by the Environmental Council of Zambia. The EIA is also a key requirement of the Mining Licence application.
Regional Exploration
Our joint venture partner AFE, which is exploring the wider 478 sq km licence around the known deposits, has now received most of the laboratory analyses from its soil geochemical programme. These have revealed several promising copper anomalies, which AFE will follow up.
AFE's diamond and reverse circulation drilling of the Munda Prospect, 5km south of Munshiwemba, yielded several intersections of copper sulphide, with grades up to 2% indicated by visual inspection and in-field XRF X-Ray Fluorescence Spectroscopy analysis.
General
As part of our ongoing commitment of community improvements work was completed on rewiring of the local medical facility in the nearby Mkushi Copper Mine village during the quarter.
SEGILOLA GOLD PROJECT UPDATE
----------------------------
The two containers that arrived at the Appapa wharf, Lagos, Turkish drill rig and the accessories and consumables, were cleared by customs in the first week of April. Arrangements were made to transport the two containers to site where the Turkish drilling crew and supervisors offloaded them. The main drilling programme has now commenced.
For an image of the Spektra Drill Rig see http://files.newswire.ca/621/CGA.doc
Drill pad construction and access track clearing in preparation for the Spektra Drill Rig continued during the quarter, a total of 18 drill pads were constructed of which 3 have been drilled by Tanylag, the Nigerian drilling company on site.
The core recovery from Tanylag Nigeria Ltd ("Tanylag"), the current local Nigerian driller on site, was not good due to only a single tube core barrel being available to them at the time. This indicates that there is a potential for an upside on the grade due to a potential loss of mineralisation from the core retrieved and also that the extent of mineralisation may be increased. The assay results (from SGS Laboratory Services Ghana Ltd ("SGS") in Ghana) can be found in Table 4.
The hole as drilled on an average angle of minus 60 degrees and the widths referred to in the table are apparent widths. Importantly, the results do confirm expected zones of mineralisation identified during previous drilling campaigns by others.
Table 4
Segilola Area Intercepts
-------------------------------------------------------------------------
SEGILOLA PROJECT
-------------------------------------------------------------------------
ASSAY RESULTS FOR HOLE SGD002
-------------------------------------------------------------------------
HOLE ID FROM TO INTERVAL SAMPLE ID WEIGHT AUG/T
-------------------------------------------------------------------------
SGD002 20.00 22.00 2.00 SX070001 3.05 1.49
-------------------------------------------------------------------------
SGD002 30.00 32.00 2.00 SX070006 2.20 1.03
-------------------------------------------------------------------------
SGD002 34.00 36.00 2.00 SX070008 3.70 2.23
-------------------------------------------------------------------------
SGD002 42.00 44.00 2.00 SX070012 1.65 0.97
-------------------------------------------------------------------------
SGD002 46.00 48.00 2.00 SX070014 3.80 1.69
-------------------------------------------------------------------------
Fugro Environmental Consultants, a Nigerian based company, has been approached to provide a proposal to establish an environmental baseline study. It is planned for this to commence during the next quarter.
A total of 282m of new trenches were dug during the quarter with some 525 samples being collected from them, together with some sampling from old existing trenches, bringing the total samples collected to date to 570. A shipment was made to SGS in Accra, Ghana comprising of 360 trench samples during the end of this quarter and results are expected to be received in the next quarter.
CORPORATE
---------
During the quarter 1,070,000 options were exercised for total cash proceeds of AUD$718,000. At 31 March 2008, the Company had 8,950,000 options and 6,250,000 outstanding warrants on issue. The total issued capital of the Company as at 31 March 2008 was 211,624,976 fully paid ordinary shares.
National Instrument 43-101 and JORC Compliance
Mr Geoff.G.Jones, F.Aus.l.M.M.CP Mng, CGA's Consulting Engineer, is acting as the Qualified Person in compliance with NI 43-101 and JORC reporting requirements with respect to this announcement. He has prepared and or supervised the preparation of the scientific or technical information in this announcement.
Cautionary Note Regarding Forward Looking Statements
This announcement includes certain "forward-looking statements" within the meaning of Canadian securities legislation. All statements, other than statements of historical fact, included herein including, without limitation, statements regarding anticipated dates for construction and production, and other milestones related to the Masbate Gold Project and other projects; estimates of capital and operating costs, recovery rates, production estimates and estimated economic return; and CGA's future operating or financial performance, are forward-looking statements. Information concerning mineral reserve and resource estimates including statements regarding the conversion of inferred resources to reserves also may be deemed to be forward-looking statements in that it reflects a prediction of the mineralization that would be encountered if a mineral deposit were developed and mined. Forward-looking statements involve various risks and uncertainties and are based on certain factors and assumptions. There can be no assurance that such statements will prove to be accurate, and actual results and future events could differ materially from those anticipated in such statements. Important factors that could cause actual results to differ materially from CGA's expectations include uncertainties related to fluctuations in gold and other commodity prices and currency exchange rates; uncertainties relating to interpretation of drill results and the geology, continuity and grade of mineral deposits; uncertainty of estimates of capital and operating costs, recovery rates, production estimates and estimated economic return; the need for cooperation of government agencies in the development of the Masbate Gold Project; the need to obtain additional financing to develop the Masbate Gold Project; the possibility of delay in development programs or in construction projects and uncertainty of meeting anticipated program milestones for the Masbate Gold Project; and other risks and uncertainties disclosed under the heading "Caution Regarding Forward-Looking Statements" in CGA's Annual Information Form for the year ended 30 June 2007 filed with the Canadian securities regulatory authorities on the SEDAR website at www.sedar.com.
Appendix 5B
Mining exploration entity monthly report
Introduced 1/7/96. Origin: Appendix 8. Amended 1/7/97, 1/7/98, 30/9/2001.
Name of entity
-------------------------------------------------------------------------
CGA Mining Limited
-------------------------------------------------------------------------
ABN Month ended ("current month")
----------------------- -----------------------------
88 009153128 March 2008
----------------------- -----------------------------
Consolidated statement of cash flows
----------------------
Year
to date
Current (nine
Cash flows related to quarter months)
operating activities US$'000 US$'000
----------------------
1.1 Receipts from product sales and
related debtors - -
1.2 Payments for (a) exploration and evaluation (1,837) (5,805)
(b) development (9,525) (36,355)
(c) production - -
(d) administration (650) (3,421)
1.3 Dividends received - -
1.4 Interest and other items of a similar
nature received 338 1,214
1.5 Interest and other costs of finance paid (115) (3,722)
1.6 Income taxes paid - -
1.7 Other -Business development (346) (346)
----------------------
(12,135) (48,435)
Net Operating Cash Flows
-------------------------------------------------------------------------
-------------------------------------------------------------------------
Cash flows related to investing activities
1.8 Payment for purchases of: (a)prospects
(b)equity investments
(c) other fixed assets (150) (150)
1.9 Proceeds from sale of: (a)prospects - -
(b)equity investments - -
(c)other fixed assets - -
1.10 Loans to other entities
1.11 Loans repaid by other entities
1.12 Other (provide details if material)
----------------------
(150) (150)
Net investing cash flows ----------------------
1.13 Total operating and investing cash flows
(carried forward) (12,285) (48,585)
-------------------------------------------------------------------------
-------------------------------------------------------------------------
1.13 Total operating and investing cash flows
(brought forward)
-------------------------------------------------------------------------
Cash flows related to financing activities
1.14 Proceeds from issues of shares, options, etc. 656 40,541
1.15 Proceeds from sale of forfeited shares
1.16 Proceeds from borrowings - 25,000
1.17 Repayment of borrowings
1.18 Dividends paid
1.19 Other (provide details if material)
----------------------
Net financing cash flows 656 65,541
-------------------------------------------------------------------------
Net increase (decrease) in cash held (11,629) 16,956
1.20 Cash at beginning of quarter/year to date 56,370 25,399
1.21 Exchange rate adjustments to item 1.20 64 2,450
----------------------
1.22 Cash at end of quarter 44,805 44,805
-------------------------------------------------------------------------
(x) Filminera Resources Corp. has an additional $2.9m in cash.
Payments to directors of the entity and associates of the directors
Payments to related entities of the entity and associates of the related
entities
----------------------
Current quarter
US$'000
----------------------
1.23 Aggregate amount of payments to the parties
included in item 1.2 287
----------------------
1.24 Aggregate amount of loans to the parties
included in item 1.10 -
-------------------------------------------------------------------------
1.25 Explanation necessary for an understanding of the transactions
-------------------------------------------------------------------------
Payment of salaries, directors fees, taxes, and superannuation.
-------------------------------------------------------------------------
Non-cash financing and investing activities
2.1 Details of financing and investing transactions which have had a
material effect on consolidated assets and liabilities but did not
involve cash flows
-------------------------------------------------------------------------
In accordance with accounting standards the Company is required to
recognise the fair value of the Warrants issued in November 2007 as a
current liability. The Warrants are required to be revalued at each
balance date, with the movement recognised as either a gain or loss in
the Income Statement. The Company does not have any current or future
cash payment liabilities in relation to the Warrants, however, accounting
standards require that a theoretical fair value be placed on them and
that this be recognised as a current liability in the Company's Financial
Statements. At 31 March 2008, the fair value of the Warrants recognised
as a current liability on the balance sheet is $6.528m and the fair value
of the movement for the quarter ended March 31, 2008 recognised in the
profit and loss statement is ($2.764m). These amounts do not reflect
either a current or future cash flow to the entity.
-------------------------------------------------------------------------
2.2 Details of outlays made by other entities to establish or increase
their share in projects in which the reporting entity has an
interest
-------------------------------------------------------------------------
-------------------------------------------------------------------------
Financing facilities available
Add notes as necessary for an understanding of the position.
-------------------------
Amount
available Amount used
US$'000 US$'000
-------------------------
3.1 Loan facilities - -
-------------------------
3.2 Credit standby arrangements - -
-------------------------------------------------------------------------
Estimated cash outflows for next quarter
-------------------------
US$'000
-------------------------
4.1 Exploration and evaluation 2,433
-------------------------
4.2 Development 38,330
-------------------------------------------------------------------------
Total 40,763
-------------------------------------------------------------------------
Reconciliation of cash
-------------------------
Reconciliation of cash at the end of the
quarter (as shown in the consolidated Current Previous
statement of cash flows) to the related quarter quarter
items in the accounts is as follows. US$'000 US$'000
-------------------------------------------------------------------------
5.1 Cash on hand and at bank 34,200 53,397
-------------------------
5.2 Deposits at call 9,030 -
-------------------------
5.3 Bank overdraft - -
-------------------------
5.4 Other (provide details)
AUD Account 1,376 2,781
AUD Deposit 199 192
-------------------------------------------------------------------------
Total: cash at end of quarter (item 1.22) 44,805 56,370
-------------------------------------------------------------------------
Changes in interests in mining tenements
----------------------------------------------------
Nature of Interest at Interest at
Tenement interest beginning of end of
reference (note (2)) quarter quarter
----------------------------------------------------
6.1 Interests in
mining
tenements
relinquished,
reduced or
lapsed - - - -
----------------------------------------------------
6.2 Interests in
mining
tenements
acquired or
increased - - - -
----------------------------------------------------
Issued and quoted securities at end of current quarter
Description includes rate of interest and any redemption or conversion
rights together with prices and dates.
----------------------------------------------------
Amount paid
Issue price up per
per security security
Total Number (see note 3) (see note 3)
number quoted (cents) (cents)
-------------------------------------------------------------------------
7.1 Preference
+Securities
(description)
----------------------------------------------------
7.2 Changes during
quarter
(a) Increases
through issues
(b) Decreases
through returns
of capital,
buy-backs,
redemptions
-------------------------------------------------------------------------
7.3 +Ordinary
securities 211,624,976 211,624,976
----------------------------------------------------
7.4 Changes during
quarter
(a) Increases
through issues
(b) Decreases
through returns
of capital,
buy-backs
-------------------------------------------------------------------------
7.5 +Convertible debt
securities
(description)
----------------------------------------------------
7.6 Changes during
quarter
(a) Increases
through issues
(b) Decreases
through securities
matured,
converted
-------------------------------------------------------------------------
7.7 Options
(description and
conversion factor)
----------------------------------------------------
7.8 Issued during
quarter
----------------------------------------------------
7.9 Exercised during
quarter 1,070,000 1,070,000 0.67 0.67
----------------------------------------------------
7.10 Expired during
quarter
-------------------------------------------------------------------------
7.11 Debentures
(totals only)
7.12 Unsecured notes
(totals only) 25,000 0
---------------------------
Compliance statement
1 This statement has been prepared under accounting policies which
comply with accounting standards as defined in the Corporations Act
or other standards acceptable to ASX (see note 4).
2 This statement does give a true and fair view of the matters
disclosed.
Sign here: (signed) Date: 30 April 2008
(Company secretary)
Print name: Hannah Hudson..............................
Notes
1 The quarterly report provides a basis for informing the market how
the entity's activities have been financed for the past quarter and
the effect on its cash position. An entity wanting to disclose
additional information is encouraged to do so, in a note or notes
attached to this report.
2 The "Nature of interest" (items 6.1 and 6.2) includes options in
respect of interests in mining tenements acquired, exercised or
lapsed during the reporting period. If the entity is involved in a
joint venture agreement and there are conditions precedent which will
change its percentage interest in a mining tenement, it should
disclose the change of percentage interest and conditions precedent
in the list required for items 6.1 and 6.2.
3 Issued and quoted securities
The issue price and amount paid up is not required in items 7.1 and
7.3 for fully paid securities.
4 The definitions in, and provisions of, MSB 1022: Accounting for
Extractive Industries and MSB 1026: Statement of Cash Flows apply to
this report.
5 Accounting Standards
ASX will accept, for example, the use of International Accounting
Standards for foreign entities. If the standards used do not address
a topic, the Australian standard on that topic (if any) must be
complied with.