/NOT FOR DISSEMINATION IN THE UNITED STATES OR FOR RELEASE TO US NEWS
WIRE SERVICES/
28 APRIL 2009
MARCH QUARTERLY REPORT
PERTH, Western Australia, April 28 /CNW/ -
HIGHLIGHTS
- Construction of the processing plant was completed on schedule on
20 February 2009.
- Construction of the 30 MW power plant has now been completed as well.
- The following items have now been completed, tested and commissioned:
- power to start and run the complete milling circuit;
- fuel farm for the receipt and storage of both HFO & diesel fuel;
- process water delivery and storage systems;
- complete crushing circuit (Primary Crusher, Stockpile, Transfer
and Pebble Crusher);
- SAG mill;
- ball mill;
- CIL circuit;
- gold elution circuit and gold room; and
- tailings dam and disposal system ready to receive tailings.
- All mining equipment is on site, commissioned and operating.
- A complete selection of ore types by material (both high grade and
low grade for oxide, transitional and fresh) are on the ROM pad.
- The CIL tanks have been filled and consumables added.
- High grade ore from the ROM pad has now been introduced to the
circuit.
- Lycopodium Engineering Pty Ltd is on site with the final completion
testing due to commence this week.
- Operating team in place.
- Confirmatory grade control drilling results at the Masbate Gold
Project including:
19m @ 24.59 g/t
17m @ 8.05 g/t
6m @ 19.59 g/t
16m @ 6.36 g/t
40m @ 2.58 g/t
33m @ 2.99 g/t
- Significant drilling results at the Segilola Project including:
6m @ 8.07 g/t including 3m @ 13.23 g/t
11.85m @ 11.33 g/t including 1m at 17.1g/t and 2.1m @ 50.06 g/t
6m @ 13.56 g/t including 3m @ 22.71 g/t
8.1m @ 12.23 g/t including 3m @ 24.68 g/t
6.5m @ 8.77 g/t including 0.55m @ 16.35 g/t and 2m @ 11.52
g/t
4.6m @ 34.61 g/t and 2.1m @ 71.51 g/t
- Cash position of US$24.7M at 31 March 2009.
MASBATE PROJECT UPDATE
----------------------
Commissioning Update
On 20 February, under the terms of the EPC Contracts with Phil. Gold Processing Refining Corp. ("PGPRC") and Filminera Resources Corporation ("FRC"), Leighton Contractors Asia Limited ("LCAL") was awarded Practical Completion ("PC") of its scope of work in the process plant construction.
LCAL personnel under the supervision of PGPRC appointed specialist contractors Weir Services Australia Pty Ltd ("Weir") (mills) and BEC Engineering Pty Ltd ("BEC") (mill electrics) continued with the installation of the Semi Autogenous Grinding ("SAG") mill and the two ball mills. Final alignment of the SAG and No. 1 ball mill was completed mid April. This enabled the commissioning of the crushing and grinding circuit. Installation of the No. 2 ball mill is 95% complete with the installation of the trunnion bearing housing and liners remaining. Both final commissioning steps and operation of the plant is not constrained by the No. 2 ball mill as both can operate in isolation.
Consumables were introduced to the circuit on 27 April and ROM pad high grade ore has now been fed to the plant.
Final receipt and installation of the discharge spigots at the end of the tailings delivery line will complete the LCAL work in this area. These activities are not affecting the commissioning of the process plant as provision is made for direct end discharge into the Tailings Storage Facility ("TSF").
Work on the plant site drainage and surrounding roads is 95% complete.
At the time of the award of PC, an extensive 'punch list' of items requiring attention was compiled. LCAL has continued to work on this remediation work and are 98% complete. Under the terms of the EPC contract, LCAL is obliged to provide labour to assist with commissioning and performance testing of the processing facility under the direction of Lycopodium Engineering Pty Ltd ("Lycopodium"). Lycopodium engineers are on site and scheduled to commence performance testing shortly.
To view the Masbate Process and Power Plant as at 21 April 2009, please visit: http://files.newswire.ca/578/Masbateproject.doc
Mill Refurbishment & Installation
Weir completed the installation of the SAG mill with specialist assistance from BEC, German Hydraulics And Plant Service, Inc and Outotech Engineering Pty Ltd. The mill was initially started on 10 April then was shut down for minor adjustments. Low grade material was supplied to the mill on 17 April.
The No. 1 ball mill was also started on 10 April, shut down for minor remedial work and initially commissioned with low grade material on 17 April. Delivery of the No. 2 ball mill trunnion bearing liner is imminent, and we expect to commission this unit prior to the end of April as well.
CIL Circuit
Lycopodium was commissioned by LCAL to carry out wet commissioning of the complete leach and gold recovery circuit. Lycopodium completed this work by the end of the March quarter and subsequently switched to an ore commissioning role under an arrangement with PGPRC. The crushing, milling and leach feed areas commenced operations on 17 April and achieved a throughput rate of 450 tonne per hour (including recirculating load) prior to having shut down due to a failure of the mill discharge pump (new Warman unit supplied ex Australia) on 18 April. Rectification of the pump failure was completed four days later with the plant now operating again, with consumables and high grade ore from the ROM pad also introduced. The first production pour anticipated in the second week of May.
Power Station
LCAL was awarded PC under the Power EPC Contract on 3 April. The contract involved the installation of 5 engines and generators plus associated ancillary equipment and storage facilities capable of supplying 30 Mega Watt ("MW") of power to the entire project. The design of the facility has been completed by Poyry Energy Inc. ("Poyry") a specialist firm of electrical engineers and commissioning of the facility is being carried out by Wartsila Philippines Inc ("Wartsila") a subsidiary of the Finnish parent company Wartsila Finland Oy, the manufactures of the five units. Pre-inspection testing carried out by Wartsila resulted in a favourable report on all five units.
PGPRC instructed Warstila to concentrate on commissioning the three larger units (18 MW) to enable sufficient power to commission the process plant. On 17 April the initial three units were commissioned and operated effectively. Subsequently one of the units was shut down for work on the cooling system. The fourth and fifth units are planned to be commissioned within a few days.
PGPRC has finalised an Operating and Maintenance Agreement ("O&M") with Wartsila Philippines for the management and operation of the plant. To view inside the Masbate Power Plant, please visit: http://files.newswire.ca/578/Masbateproject.doc
Masbate Power Plant
Fuel Farm
The refurbishment of the delivery and storage facility to accommodate Heavy Fuel Oil ("HFO") and diesel has been completed. Improvements to the receivable and delivery systems will take place during the operational phase when actual requirements of each product become clearer.
Infrastructure
All planned infrastructure i.e. accommodation, general office, assay laboratory, water supply, security entrance, clinic etc are complete and being used.
Mining and Geology
Total mining production for the period was 644,039 bank cubic meters ("BCM"). Pioneering work was undertaken, with access being established to the first four starter pits. The remainder of the period saw the arrival of the balance of the mining fleet including drills and explosives. Mining for the period concentrated on the ramping up of production rates. By the end of the period, the starter pits were established and daily movements were on target.
A total of 247,882 t of high grade ore was delivered to the run of mine ("ROM") at an average grade of 1.44 g/t. Low grade ore mined was 244,331 t @ 0.64 g/t.
Blast hole drilling progressed well, with no issues. An emulsion plant has been included in the Orica contract and is forecast to be running by July.
Relocating farmers and other residents within the dump foot prints has now been completed. The ROM pad is currently at capacity.
Recruitment of the mine technical staff is progressing well with key personnel in place to ensure continuity of production.
Mining areas for the period included HMB West, HMB East and Libra East. Some pioneering work also occurred at Binstar, and the base of HMB East.
The majority of the infill drilling in HMB West and Libra West has been returned, geological interpretations are currently being updated.
To view a map of the Ore Stockpiles, please visit: http://files.newswire.ca/578/Masbateproject.doc
The map above shows the locations of the current operating stockpiles at the Masbate Project, at the end of March. All mining and stockpiling records were compared to the survey pick-up volume and the table below summarises the current status of the available ore and low-grade stocks. With these initial stocks and the advanced state of the mining program, the mine will be able to maintain ore for the mill.
To view Table 1, please click on: http://files.newswire.ca/578/Masbateproject.doc
Grade Control Drilling
318 holes were drilled during the March quarter posting a total meterage of 14,002 meters. Drilling was done in HMB East, Main Vein West, HMB West, Libra Main, Libra West, Main Vein West and Montana. (See Table 2 below)
Initial reconciliation between the resource block model and the grade control block model shows a positive correlation in tonnes and grade, giving a 2% increase in contained gold for mill feed ore.
Development Works
Complete assay results for the last deep hole, testing the down dip extension of the Main Vein Ore Body were received during the period.
As previously reported the deep hole below Main Vein returned an intercept of 192m @ 0.90 g/t Au from 121m to 313m down hole.
The geophysical contractor GPX has mobilised to the Philippines and preparation for the aeromagnetic survey is well underway.
To view Table 2 of the Masbate Project, please see: http://files.newswire.ca/578/Masbateproject.doc
Safety
LCAL has achieved a 3.5 million man hour safety milestone without a single lost time injury during the entire construction phase of both the process plant and the power plant.
Environment and Permitting
All the necessary sampling and measuring of discharges resulting from onsite activities are being carried out to ensure compliance with the Philippines Regulations and the specific requirements under the Environmental Compliance Certificate ("ECC"). A Multi-Partite Monitoring Team comprised of the Mines and Geosciences Bureau ("MGB"), Environmental Management Bureau, Local Government Units, the eight impacted barangays and an NGO, amongst others, maintain an active participation in monitoring the test results.
There is also, an ongoing program managing permitting and titling issues. The Philippines has an established framework that is well regulated and monitored by the MGB and other related bodies, with continual input and oversight. We continue to work with these bodies and address any requests made and have a program that monitors the progression of permits required for operation and the renewal of such permits as required.
Community Relations
With the transition into the operational phase, the community relations programmes have been further enhanced. A dedicated community relations department, supported by fourteen community facilitators from the eight impacted barangays and specialist consultants, focussed on improving communications into the local communities and implementing livelihood and information and education programs have been retained.
Key projects include:
- additional potable water supplies and identification of hazardous
water sources;
- medical assistance of medicines and ambulance services;
- fishnet supply and associated livelihood training;
- fishpond repairs and associated livelihood training;
- educational assistance support;
- on-going farm to market road maintenance and repairs; and
- capacity building of existing NGO organizations in the district.
As part of that process the project leadership is also focussed on formalising arrangements with local small scale miners to ensure the project can work collaboratively with all relevant parties, while also seeking to improve their operating techniques to reduce any impact on safety and the environment.
A series of peaceful gatherings were held during commissioning on an access road leading to the process plant. These rallies, whilst commonplace in the Philippines and peaceful resulted in the distribution of inaccurate information.
The Masbate Gold Project has a broad level of support from the senior political leadership in Masbate Province and the eight impacted local barangays (villages) together with strong political and MGB support both in Manila and Region V (which includes the Masbate province).
FRC and PGPRC adopt a co-operative and supportive approach towards small scale miners and adhere to the principles of responsible mining at its Masbate Gold Project, as attested to by the MGB and evidenced by the construction of the entire processing and power plants without even one lost time injury. That same exceptional level of care and commitment will be applied to all aspects of the operation moving forward including most importantly the environment and the community programs and support.
Expenditure
As at 31 March 2009, the group has spent US$168.7M on the development of the Masbate Gold Project. The capital development budget forecast is currently in the order of US$175M. Total cash reserves at 31 March were US$24.7M, (including the cash reserves of FRC) and all facilities have been drawn.
SEGILOLA GOLD PROJECT UPDATE ---------------------------- Summary
Drilling of the 10,000m programme continued well during quarter, with additional positive sample assays being returned. The total drilled meters up to the end March 2009 is 8435.8m to give a total of 88 completed holes. A slight improvement has been achieved in the assay turnaround times with results being received from 38 sampled holes (including one re-sampled hole following core review). Core logging and sample preparation is ongoing at the Ilesha Camp, which also includes digital data capture and data entry into the drill hole database.
A local surveying contractor has been engaged to do a topographical survey of the project site.
Ongoing drill pad clearance with an excavator is being achieved to keep ahead of the drill advance.
Environmental Consultants (Fugro Consultants Nigeria Limited) have reviewed the draft comments for the environmental baseline study report of the project site and should be releasing the final report next quarter.
Survey
The ground survey of the project area is currently underway. Sphero Grid Surveyors, an Osogbo based survey contractor was engaged to do a topographic survey of the project site. A 2.5 km NNE-SSW grid centred on the main mineralized vein have been cut. A 1km E-W grid line centred on the mineralized zone is also being done. More E-W lines are being cut at 200m intervals along the NNE-SSW baseline to form part of the grid to create a topographic contour of the main mineralised zone.
Table 3 can be viewed at: http://files.newswire.ca/578/Masbateproject.doc
Metallurgical Testing
Additional samples were sent for metallurgical testwork (bottle roll test) to provide additional and ongoing confirmation of the good gold recovery potential (95%+).
CORPORATE ---------
As at 31 March 2009, group cash was US$24.7M (including the cash reserves of FRC) and we had drawn US$79.1M under the BNP arranged project finance facility for the Masbate Gold Project and US$10m under the Meridian/Casten Facility.
At 31 March 2009, the Company had 12,725,000 options and 5,575,000 outstanding warrants on issue. The total issued capital of the Company as at 31 March 2009 was 254,286,976 fully paid ordinary shares.
ABOUT CGA MINING LIMITED ------------------------
CGA is listed on the Toronto Stock Exchange and Australian Securities Exchange. The Masbate Gold Project in the Philippines has now been constructed and we are currently commissioning the 4mtpa plant and power plant. The project has a total indicated resource base of 4.55M ounces, total inferred resource base of 3.22M ounces and a probable reserve of 3.03M ounces of gold. It is currently forecast to produce over 200,000 ounces per annum. CGA is completing a scoping study for the expansion of the plant throughput at Masbate. The mining contract for the Masbate Gold Project has been awarded to Leighton, the largest mining contractor in the world. There are currently four drilling rigs on site.
The Company is also currently undertaking a 10,000m drilling program at Segilola, regarded as Nigeria's most advanced gold property. CGA has a disciplined acquisition program focused on acquiring new gold projects with a substantial initial resource with the capacity to grow materially and where the development and operational experience of CGA can be applied to enhance shareholder value.
NATIONAL INSTRUMENT 43-101 AND JORC COMPLIANCE ----------------------------------------------
Mr Geoff.G.Jones, F.Aus.I.M.M.CP Mng, CGA's Consulting Engineer, is acting as the Qualified Person in compliance with NI 43-101 and JORC reporting requirements with respect to this announcement. He has prepared and or supervised the preparation of the scientific or technical information in this announcement and confirms compliance with NI43-101 and JORC requirements.
Further information relating to the Masbate Project is included in the technical report entitled Technical Report on the Mineral Resources of the Masbate Deposit, Masbate Province, Republic of the Philippines for CGA Mining Limited prepared by Mining Associates Pty Ltd and available on SEDAR at www.sedar.com, lodged 8 July 2008.
Andrew James Vigar of Mining Associates Pty Ltd, a qualified person, has verified the resource statement for the Masbate Project as disclosed in this announcement, including sampling, analytical and test data underlying the estimate. Verification of the data included numerous site visits, database validation of historical drill results and review of sampling and assaying protocols. The qualified person was satisfied with the verification process.
A NI 43-101 compliant report has been lodged on www.sedar.com verifying and supporting the new reserve statement made for the Masbate Project. Mr Daniel Tuffin of Lower Quartile Solution Pty Ltd, a qualified person, has verified the reserve statement for the Masbate Project as disclosed in this announcement, including sampling, analytical and test data underlying the estimate. Verification of the data included database validation of historical drill results and review of sampling and assaying protocols. The qualified person was satisfied with the verification process.
CAUTIONARY NOTE REGARDING FORWARD LOOKING STATEMENTS ----------------------------------------------------
This announcement includes certain "forward-looking statements" within the meaning of Canadian securities legislation. All statements, other than statements of historical fact, included herein including, without limitation, statements regarding anticipated dates for construction and production, and other milestones related to the Masbate Gold Project and other projects; estimates of capital and operating costs, recovery rates, production estimates and estimated economic return; and CGA's future operating or financial performance, are forward-looking statements. Information concerning mineral reserve and resource estimates including statements regarding the conversion of inferred resources to reserves also may be deemed to be forward-looking statements in that it reflects a prediction of the mineralization that would be encountered if a mineral deposit were developed and mined. Forward-looking statements involve various risks and uncertainties and are based on certain factors and assumptions. There can be no assurance that such statements will prove to be accurate, and actual results and future events could differ materially from those anticipated in such statements. Important factors that could cause actual results to differ materially from CGA's expectations include uncertainties related to fluctuations in gold and other commodity prices and currency exchange rates; uncertainties relating to interpretation of drill results and the geology, continuity and grade of mineral deposits; uncertainty of estimates of capital and operating costs, recovery rates, production estimates and estimated economic return; the need for cooperation of government agencies in the development of the Masbate Gold Project; the need to obtain additional financing to develop the Masbate Gold Project; the possibility of delay in development programs or in construction projects and uncertainty of meeting anticipated program milestones for the Masbate Gold Project; and other risks and uncertainties disclosed under the heading "Risk Factors" in CGA's Annual Information Form for the year ended 30 June 2008 filed with the Canadian securities regulatory authorities on the SEDAR website at www.sedar.com.
Appendix 5B
Mining exploration entity quarterly report
Introduced 1/7/96. Origin: Appendix 8. Amended 1/7/97, 1/7/98, 30/9/2001.
Name of entity
-------------------------------------------------------------------------
CGA Mining Limited
-------------------------------------------------------------------------
ABN Quarter ended ("current quarter")
-------------------- ---------------------------------
88 009 153 128 31 March 2009
-------------------- ---------------------------------
Consolidated statement of cash flows
---------------------------
Current quarter Year to
date
Cash flows related to operating activities (three
months)
$US'000 $US'000
---------------------------
1.1 Receipts from product sales and related
debtors
1.2 Payments for
(a) exploration and evaluation (896) (5,514)
(b) development (including working
capital expenditure) (24,841) (95,083)
(c) production
(d) administration (1,013) (3,057)
1.3 Dividends received
1.4 Interest and other items of a similar
nature received 5 341
1.5 Interest and other costs of finance paid (175) (2,136)
1.6 Income taxes paid
1.7 Other (Business development) (136) (396)
---------------------------
Net Operating Cash Flows (27,056) (105,845)
-------------------------------------------------------------------------
Cash flows related to investing
activities
1.8 Payment for purchases of:
(a) prospects
(b) equity investments
(c) other fixed assets (120) (120)
1.9 Proceeds from sale of:
(a) prospects
(b) equity investments
(c) other fixed assets
1.10 Loans to other entities (9,784) (17,196)
1.11 Loans repaid by other entities
1.12 Other (payment of deferred acquisition
cost) (4,500) (4,500)
---------------------------
Net investing cash flows (14,284) (21,816)
---------------------------
1.13 Total operating and investing cash
flows (carried forward)
-------------------------------------------------------------------------
1.13 Total operating and investing cash
flows (brought forward) (41,340) (127,661)
-------------------------------------------------------------------------
Cash flows related to financing
activities
1.14 Proceeds from issues of shares,
options, etc. 20,584 20,631
1.15 Proceeds from sale of forfeited shares
1.16 Proceeds from borrowings 15,507 87,607
1.17 Repayment of borrowings
1.18 Dividends paid
1.19 Other (capital raising costs) (1,114) (1,114)
---------------------------
Net financing cash flows 34,976 107,123
-------------------------------------------------------------------------
Net increase (decrease) in cash held (6,364) (20,538)
1.20 Cash at beginning of quarter/year to
date 30,585 44,781
1.21 Exchange rate adjustments to item 1.20 (334) (356)
---------------------------
1.22 Cash at end of quarter(x) 23,886 23,886
-------------------------------------------------------------------------
(x) an additional US$820,322 in cash is held by Filminera Resources
Corporation
Payments to directors of the entity and associates of the directors
Payments to related entities of the entity and associates of the related
entities
---------------
Current quarter
$US'000
---------------
1.23 Aggregate amount of payments to the parties included
in item 1.2 221
---------------
1.24 Aggregate amount of loans to the parties included
in item 1.10 -
-------------------------------------------------------------------------
1.25 Explanation necessary for an understanding of the
transactions
--------------------------------------------------------------------
Payment of directors' fees, salaries, taxes, and superannuation.
--------------------------------------------------------------------
Non-cash financing and investing activities
2.1 Details of financing and investing transactions which have had a
material effect on consolidated assets and liabilities but did not
involve cash flows
--------------------------------------------------------------------
n/a
--------------------------------------------------------------------
2.2 Details of outlays made by other entities to establish or increase
their share in projects in which the reporting entity has an
interest
--------------------------------------------------------------------
n/a
--------------------------------------------------------------------
Financing facilities available
Add notes as necessary for an understanding of the position.
------------------------
Amount
available Amount used
$US'000 $US'000
------------------------
3.1 Loan facilities 1,280 89,020
------------------------
3.2 Credit standby arrangements - -
-------------------------------------------------------------------------
Estimated cash outflows for next quarter
------------
$US'000
------------
4.1 Exploration and evaluation 573
------------
4.2 Development 6,100
-------------------------------------------------------------------------
Total 6,673
-------------------------------------------------------------------------
Reconciliation of cash
---------------------
Reconciliation of cash at the end of the
quarter (as shown in the consolidated Current Previous
statement of cash flows) to the related quarter quarter
items in the accounts is as follows. $US'000 $US'000
-------------------------------------------------------------------------
5.1 Cash on hand and at bank 23,494 30,121
---------------------
5.2 Deposits at call
---------------------
5.3 Bank overdraft
---------------------
5.4 Other (AUD account) 392 464
-------------------------------------------------------------------------
Total: cash at end of quarter (item 1.22)(x) 23,886 30,585
-------------------------------------------------------------------------
(x) an additional US$268,784 in cash is held by Filminera Resources
Corporation
Changes in interests in mining tenements
------------------------------------------------
Nature of Interest at Interest at
Tenement interest beginning end of
reference (note (2)) of quarter quarter
------------------------------------------------
6.1 Interests in mining
tenements relinquished,
reduced or lapsed n/a n/a n/a n/a
------------------------------------------------
6.2 Interests in mining
tenements acquired
or increased n/a n/a n/a n/a
------------------------------------------------
Issued and quoted securities at end of current quarter
Description includes rate of interest and any redemption or conversion
rights together with prices and dates.
---------------------------------------------------
Amount paid
Issue price up per
per security security
Total Number (see note 3) (see note 3)
number quoted (cents) (cents)
-------------------------------------------------------------------------
7.1 Preference +
securities
(description)
---------------------------------------------------
7.2 Changes during
quarter
(a) Increases
through issues
(b) Decreases
through returns
of capital,
buy-backs,
redemptions
-------------------------------------------------------------------------
7.3 +Ordinary
securities 254,289,976 254,289,976
---------------------------------------------------
7.4 Changes during
quarter
(a) Increases
through issues
Private placement
Option exercises
(b) Decreases
through returns
of capital, 20,000,000 20,000,000 C$1.25 C$1.25
buy-backs 410,000 410,000 A$0.90 A$0.90
-------------------------------------------------------------------------
7.5 +Convertible
debt securities
(description)
---------------------------------------------------
7.6 Changes during
quarter
(a) Increases
through issues
(b) Decreases
through securities
matured, converted
-------------------------------------------------------------------------
7.7 Options
(description and Exercise Expiry
conversion factor) price date
---------------------------------------------------
7.8 Issued during
quarter
---------------------------------------------------
7.9 Exercised during
quarter
---------------------------------------------------
7.10 Expired during
quarter
-------------------------------------------------------------------------
7.11 Debentures
(totals only) - -
-----------------------------------------------
7.12 Unsecured notes
(totals only) 25,000
-------------------------
Compliance statement
1 This statement has been prepared under accounting policies which
comply with accounting standards as defined in the Corporations Act
or other standards acceptable to ASX (see note 4).
2 This statement does give a true and fair view of the matters
disclosed.
Sign here: "signed" Date: ..28 April 2009................
(Company secretary)
Print name: .Hannah Hudson................
Notes
1 The quarterly report provides a basis for informing the market how
the entity's activities have been financed for the past quarter and
the effect on its cash position. An entity wanting to disclose
additional information is encouraged to do so, in a note or notes
attached to this report.
2 The "Nature of interest" (items 6.1 and 6.2) includes options in
respect of interests in mining tenements acquired, exercised or
lapsed during the reporting period. If the entity is involved in a
joint venture agreement and there are conditions precedent which will
change its percentage interest in a mining tenement, it should
disclose the change of percentage interest and conditions precedent
in the list required for items 6.1 and 6.2.
3 Issued and quoted securities The issue price and amount paid up is
not required in items 7.1 and 7.3 for fully paid securities.
4 The definitions in, and provisions of, AASB 1022: Accounting for
Extractive Industries and AASB 1026: Statement of Cash Flows apply to
this report.
5 Accounting Standards ASX will accept, for example, the use of
International Accounting Standards for foreign entities. If the
standards used do not address a topic, the Australian standard on
that topic (if any) must be complied with.