Feb. 7, 2011 (Canada NewsWire Group) --
NOT FOR DISSEMINATION IN THE UNITED STATES OR FOR RELEASE TO US NEWS WIRE SERVICES
ANNOUNCEMENT TO THE TORONTO STOCK EXCHANGE AND AUSTRALIAN SECURITIES EXCHANGE
PERTH, Western Australia, Feb. 7 /CNW/ - The Board of CGA Mining Limited ("CGA", "the Company") (TSX Code: CGA, ASX Code: CGX) is pleased to announce that the Net Profit from Continuing Operations for the six months to 31 December 2010 was $39.019M, up from $7.639M for the corresponding period last year. That represents a net profit increase by more than 400% from the comparable period last year to $39.019M for the six months ended 31 December 2010. At the same time, cash flow from operations (excluding taxes and capital), more than doubled to $46.952M from $19.759 for the six months ended 31 December 2009. The final audited half year financial statements and the Management Discussion & Analysis for the quarter ended 31 December 2010 will be released later in the week.
ABOUT CGA MINING LIMITED
CGA is listed on the main board of the Toronto Stock Exchange and ASX. The Masbate Gold Project in the Philippines was successfully constructed with first gold poured mid 2009. The project has a total indicated resource base of 4.55M ounces of gold, total inferred resource base of 3.22M ounces of gold and a probable reserve of 3.03M ounces of gold. It is currently forecast to produce over 200,000 ounces per annum.
The plant was constructed by Leighton Contractors Asia Limited ("Leighton") without one lost time injury. The mining contract for the project has also been awarded to Leighton, the largest mining contractor in the world. CGA is currently undertaking an expansion of the plant to achieve a throughput level of 6.5Mtpa.
CGA has a disciplined acquisition program focused on acquiring new gold projects with a substantial initial resource with the capacity to grow materially and where the development and operational experience of CGA can be applied to enhance shareholder value.
NATIONAL INSTRUMENT 43-101 AND JORC COMPLIANCE
Mr Geoff.G.Jones, F.Aus.I.M.M.CP Mng, CGA's Consulting Engineer, is acting as the Qualified Person in compliance with NI 43-101 and JORC reporting requirements with respect to this announcement. He has prepared and or supervised the preparation of the scientific or technical information in this announcement and confirms compliance with NI43-101 and JORC requirements.
Further information relating to the Masbate Project is included in the technical report entitled Technical Report on the Mineral Resources of the Masbate Deposit, Masbate Province, Republic of the Philippines for CGA Mining Limited prepared by Mining Associates Pty Ltd and available on SEDAR at sedar.com, lodged 8 July 2008.
Andrew James Vigar of Mining Associates Pty Ltd, a qualified person, has verified the resource statement for the Masbate Project as disclosed in this announcement, including sampling, analytical and test data underlying the estimate. Verification of the data included numerous site visits, database validation of historical drill results and review of sampling and assaying protocols. The qualified person was satisfied with the verification process.
A NI 43-101 compliant report has been lodged on sedar.com verifying and supporting the new reserve statement made for the Masbate Project. Mr Daniel Tuffin, previously of Lower Quartile Solution Pty Ltd, a qualified person, has verified the reserve statement for the Masbate Project as disclosed in this announcement, including sampling, analytical and test data underlying the estimate. Verification of the data included database validation of historical drill results and review of sampling and assaying protocols. The qualified person was satisfied with the verification process.
CAUTIONARY NOTE REGARDING FORWARD LOOKING STATEMENTS
This announcement includes certain "forward-looking statements" within the meaning of Canadian securities legislation. All statements, other than statements of historical fact, included herein including, without limitation, statements regarding milestones related to the Masbate Gold Project, production estimates and CGA's future operating or financial performance, are forward-looking statements. Forward-looking statements involve various risks and uncertainties and are based on certain factors and assumptions. There can be no assurance that such statements will prove to be accurate, and actual results and future events could differ materially from those anticipated in such statements. Important factors that could cause actual results to differ materially from CGA's expectations include uncertainties related to fluctuations in gold and other commodity prices and currency exchange rates; uncertainties relating to interpretation of drill results and the geology, continuity and grade of mineral deposits; uncertainty of estimates of capital and operating costs, recovery rates, production estimates and estimated economic return; the need for cooperation of government agencies in the development of CGA's mineral projects; the need to obtain additional financing to develop CGA's mineral projects; the possibility of delay in development programs or in construction projects and uncertainty of meeting anticipated program milestones for CGA's mineral projects; and other risks and uncertainties disclosed under the heading "Risk Factors" in CGA's Annual Information Form for the year ended 30 June 2010 filed with the Canadian securities regulatory authorities on the SEDAR website at sedar.com.
| Australian Contact | US Contact | ||
| President & CEO - Michael Carrick | Independent Chairman - Mark Savage | ||
| Tel: +61 8 9263 4000 | Tel: +1 505 344 2822 | ||
| Fax: +61 8 9263 4020 | Fax: +1 505 344 2922 | ||
| Email: mcarrick@cgamining.com | Email: marksavage@comcast.net |