CEZ as: Temelín Nuclear Power Plant's Unit 1 is set to undergo a scheduled outage. The plant's staff have 70 investment projects planned.

· Issued by CEZ AS

Summary by 6ix AI

ČEZ plans to disconnect generating Unit 1 of its Temelín Nuclear Power Plant in South Bohemia from the power grid on the evening of Friday, October 16, starting a scheduled outage. Planned work includes inspecting safety systems and the turbine and replacing some fuel assemblies.

Key details

  • ČEZ plans more than 19,000 tasks during the outage, including replacing 66 fuel assemblies, and has tentatively reserved two months for the work. Plant staff have 70 investment projects planned.
  • Planned work includes inspecting the reactor pressure vessel, one reactor coolant pump, one of four steam generators, and the turbine and generator, including pulling out the generator rotor. Four storage casks will be moved into the spent fuel storage facility.
  • Projects include replacing the fire water tank and continuing the move to a new control system. At the end of the outage, the integrity of the containment building around the reactor will be checked.
  • Approximately 1,000 people will work on the outage, half of them employees of contractor firms. It is one of two shutdowns scheduled at Temelín this year.
  • Unit 1 will move to a longer 18-month fuel cycle at the end of November, meaning about sixteen months of operation followed by approximately two months of outage. Unit 2 already runs on this schedule. ČEZ says the goal is to increase total electricity generation and reduce strain on equipment.

What’s still pending

  • The grid disconnection is planned for the evening of Friday, October 16, with the reactor operating at approximately one-third of its capacity.
  • The two-month duration of the outage is a tentative reservation.
  • Unit 1's switch to the 18-month fuel cycle is planned for the end of November.

6ix AI wrote this summary from the release below and checked it against the release.

Publication date16/10/2026
Category:Nuclear power plants
Temelín Nuclear Power Plant's Unit 1 is set to undergo a scheduled outage. The plant's staff have 70 investment projects planned.

On the evening of Friday, October 16, the Temelín Nuclear Power Plant will disconnect its generating Unit 1 from the power grid. This will mark the start of a scheduled outage, during which, e.g. safety systems and the turbine will be inspected, and some fuel assemblies will be replaced. In total, ČEZ plans to carry out more than 19,000 tasks, for which it has tentatively reserved two months.

Temelín NPP has two outages in plan this year

Operators plan to disconnect the Unit's 1 generator from the transmission grid on Friday evening while the reactor operating at approximately one-third of its capacity. The South Bohemian nuclear power plant is scheduled for two shutdowns this year. "All of our nuclear units have transitioned, or are currently transitioning, to longer fuel cycles. At Temelín, we can therefore expect alternating years with two and one outage, which will naturally affect the annual production. However, nothing changes regarding our long-term goal of supplying an average of 32 terawatt-hours per year," says Bohdan Zronek, a member of the ČEZ Board of Directors and Director of the Nuclear Energy Division.

Inspections of the reactor, turbine, or leak tests of the buildings surrounding the reactor

In addition to the replacement of 66 fuel assemblies, hundreds of other inspections, checks, and upgrades will take place at Unit 1. The plant staff will, for example, will inspect the reactor pressure vessel and move four storage casks into the spent fuel storage facility. One of the reactor coolant pumps and one of the four steam generators will undergo inspections.

In the secondary circuit, technicians will perform rigorous inspections of the turbine and generator, including the pulling out of its rotor. "We have a number of construction and modernization projects planned, such as replacing the fire water tank and continuing the transition to a new control system. At the end of the outage, we will verify the integrity of the containment building surrounding the reactor," Petr Měšťan explained.

In total, approximately 1,000 people will be involved in the outage work, half of whom are employees of contractor firms.

In recent years, the ČEZ Group's nuclear power plants have been gradually transitioning to extended fuel cycles. At Dukovany, a 16-month fuel cycle has been the standard since 2024, with units operating for 15 months between outages, followed by an outage lasting more than a month. Temelín will also complete the transition to a longer, specifically 18-month fuel cycle this year. In its case, this means sixteen months of operation and approximately two months of outage. Unit 2 at the Temelín Nuclear Power Plant is already operating under this schedule, and Unit 1 will transition to the extended fuel cycle at the end of November.. The goal of these changes is to increase total electricity generation and reduce the strain on the equipment thanks to the stability of operating parameters.

Marek Sviták, mluvčí ČEZ, Jaderná elektrárna Temelín

Photogallery
News on the topic
  • 4/9/2026
    Dukovany Heading Towards 80 Years of Operation. CEZ Strengthens Its Role as a Pillar of the Czech Energy Sector
  • 2/12/2026
    Temelín prepares for a planned outage of Unit 2. During this shutdown, it will complete the transition to longer operation between shutdowns.
  • 1/15/2026
    ČEZ to Invest CZK 3.8 billion in Modernisation of Temelín This Year
  • 9/10/2025
    The largest contract in the history of operating Czech NPP´s since their commissioning heads to Plzeň