CGA Mining LimitedTSX: CGA

Announcement to the Australian Securities Exchange and Toronto Stock Exchange

· Issued by CGA Mining Limited via CNW

Masbate Gold Project

Mobilisation of Primary Construction Contractor

PERTH, Western Australia, Oct. 26 /CNW/ - The Board of CGA Mining Limited ("CGA", "the Company") and Phil. Gold Processing and Refining Corp. ("PGPRC") are pleased to announce the commencement of on site work at the Masbate Gold Project in the Philippines.

Principal Contractor

--------------------

Leighton Contractors Philippines ("LCP") have mobilised an extensive earthmoving equipment fleet, concrete batch plant and ancillary equipment including portable office accommodation to the project site on the island of Masbate. The equipment was transported using the LCP owned barge from a nearby site where LCP had previously completed a similar project.

All equipment was unloaded via the Company owned jetty (existing from previous operations and owned by Filminera Resources Corporation) and immediately put to work clearing the designated process plant site.

To date the following activities have commenced:

-   process plant earthworks;

-   contractors office erection;

-   contractors Philippine Nationals accommodation and utilities; and

-   concrete batch plant erection.

A selection of photographs illustrating the progress to date have been posted on the CGA website www.cgamining.com under Projects/Masbate Gold Project.

Drilling Activities

-------------------

A diamond drill and a reserve circulation drill were mobilised at site during September to carry out respectively, a detailed geotechnical drill program at the process plant site and a sterilisation program at the process plant site, waste dump areas and the proposed tailings storage facility.

The geotechnical drill program and analysis is complete, and the report compiled by an independent Philippine consultant is presently being assessed. Lycopodium will incorporate the findings of the report in the design of the foundations for the high load bearing installations in the process plant.

The sterilisation program continues over the areas set aside for waste storage and tailings deposition. The drilling within the process plant site has confirmed the suitability of location for the plant site.