Akobo Minerals AbOSL: AKOBO

Akobo Minerals Expects Mining Operations To Restart Toward End Of May 2026

· Issued by Akobo Minerals Ab

Akobo Minerals AB (publ) OSL:AKOBO:

  • OPERATIONAL UPDATE FOR APRIL 2026

  • TEMPORARILY REDUCED OPERATIONS IN APRIL DUE TO FUEL SUPPLY DISRUPTIONS

  • GOLD PRODUCTION IN APRIL FROM STOCKPILE PROCESSING: APPROX. 27 KG AT 45 G/T

  • APRIL CUMULATIVE DORÉ PRODUCTION TO DATE: APPROX. 124 KG

  • SECURED A DIESEL DELIVERY TO SITE AND EXPECTS AN ADDITIONAL DELIVERY DURING MAY

  • BASED ON CURRENT INVENTORY AND UPCOMING DELIVERY, CO EXPECTS TO HAVE SUFFICIENT DIESEL AVAILABILITY TO RESUME OPERATIONS

  • SUBJECT TO A STABLE SUPPLY OF FUEL, COMPANY EXPECTS MINING OPERATIONS TO RESTART TOWARD END OF MAY 2026

Earlier from Akobo Minerals Ab

All Akobo Minerals Ab news releases