Replay available

Tutor Perini (NYSE:TPC) Q2 2020 Earnings Call

Tutor Perini (NYSE:TPC) Q2 2020 earnings call, held 2020-07-29. Watch the replay and read the transcript on 6ix.

Wed, July 29, 2020 at 5:00 PMendedReplay
Tutor Perini (NYSE:TPC) Q2 2020 Earnings Call
Company
Tutor Perini Corporation (NYSE:TPC)
Period
Q2 2020 earnings call
Date
Wed, Jul 29, 2020, 5:00 PM ET
Replay
Watch the replay on this page · 49 min

On 6ix: 6ix.com/event/tutor-perini-corporation-tpc-q2-2020-earnings-call

Replay

Transcript

Automated transcript · Written by software from the replay's audio. It can mishear names and figures; the replay is the record.

0:01 Good day ladies and gentlemen and welcome to the Tutor Perini Corporation second quarter 2020 earnings conference call. My name is Victor and I will be your coordinator for today. At this time all participants are in a listen-only mode. Following management's prepared remarks, we will be opening the call for a question and answer session. As a reminder, this conference call is being recorded for replay purposes. If anyone should require operator or technical assistance during the conference call, please press star zero on your telephone keypad. I will now turn the conference over to your host for today, Mr. Jorge Casado, Vice President of Investor Relations. Please proceed, sir.

0:42 Hello, everyone, and thank you for your participation. With us on the call today are Ronald Tutor, Chairman and CEO, and Gary Smalley, Executive Vice President and CFO. Before discussing our results, I will remind everyone that during today's call, we will be making forward-looking statements which are based on management's current assessment of existing trends and information. There is an inherent risk that our actual results could differ materially. You can find our disclosures about risk factors that could potentially contribute to such differences in our most recent Form 10-K, which was filed on February 26, 2020, and in the Form 10-Q that we are filing today. The company assumes no obligation to update forward-looking statements whether as a result of new information, future events, or otherwise other than as required by law.

1:27 In addition, during today's call, we will be discussing certain non-GAAP financial measures. The appropriate GAAP financial reconciliations are incorporated in our earnings release which we issued earlier today and filed with the SEC and which is also posted in the investor relations section of our website. With that said, I will turn the call over to Ronald Tutor.

1:47 Thank you, Jorge. Good afternoon and thank you all for joining us. We experienced a very solid momentum following our strong first quarter results, which enabled us to deliver very good results for the second quarter as well. This was despite a full quarter of adverse COVID-19 impacts, which, though not inconsequential, did not prevent us from achieving budget expectations so far this year. Gary later on will talk about that impact and the impact of a poor ruling on a litigation that hurt us in the quarter, but in spite of it, we were able to maintain almost the full budget and be ahead of budget for the first two quarters.

2:35 Our revenue grew 13% year over year in the second quarter, driven by strong growth in both our civil and building segments as we continue to advance several large projects. including the three Purple Line projects in Los Angeles, the California High Speed Rail, and the Minneapolis Southwest Light Rail, amongst others. On a year-to-date basis, we have delivered strong double-digit revenue growth across the entire business. Extraordinary operating cash of $92 million was the most noteworthy aspect of our second quarter results. An outstanding accomplishment that was the second highest quarter result since our merger in 2008 and the fifth best quarter of operating cash across all quarters since that time.

3:31 Our performance was largely driven by strong collections on major civil projects but also by projects, excuse me, by progress made on settlements which brought in approximately $40 million of cash. Our excellent cash generation in the second quarter puts us well ahead of budget expectations for operating cash through the first half of 2020. Importantly, we anticipate even stronger operating cash generation in the second half of the year, specific both to earnings and other settlements teed up and in the process. Our operating income for the second quarter was up an impressive 51%, but compared to our adjusted operating income for the same quarter last year, which excludes the impact of the goodwill impairment charge that we took that quarter.

4:31 The significant increase in operating income was the result of continued progress on several higher margin civil projects that I mentioned earlier. I will point out here that none of our major civil projects have been thus far materially impacted by the COVID-19 pandemic. And the impact on certain projects and other segments appears to be largely behind us at this point. Our operating income this quarter would have been significantly higher had it not been for a $13 million charge we were required to take in the specialty contractor segment. due to that adverse arbitration result I spoke about earlier on an electrical project in New York in our specialty group, which will still result in the collection of $3 million of cash despite that same ruling.

5:31 Despite operating in a COVID-19 environment, our civil and building segments delivered profits ahead of budget for the quarter. which helped to overcome the shortfall we once again experienced in the specialty contractor segment. Mostly a result of the charge I mentioned on that appropriate arbitration. Gary will provide you with all of the financial details of the quarter in a moment, including specifics around the COVID-19 impacts, but I will reiterate that our results for the second quarter were very good. and particularly outstanding for operating cash. I remain confident that we will produce even stronger results over the remainder of this year and into next year as our major projects continue to advance.

6:25 I mentioned last quarter that the vast majority of our projects have been deemed essential services, which has allowed project activities to continue despite all the issues of COVID-19. Because of this, and particularly since our higher margin projects have not been significantly affected by the pandemic, we still expect that it will not prevent us from achieving our planned results for 2020. However, I will caution, as I did last year, that there is still considerable uncertainty about the duration of the pandemic and how it could eventually impact our business. Our backlog was still $10 billion at the end of the second quarter, still at a high level that will continue to provide for revenue growth and strong profits.

7:19 As expected, our backlog is lower this year compared to the same period last year due to our strong revenue burn in 2020 and a relatively lower volume of new awards in the first half of this year compared to last year. The second quarter of 2020 included $717 million of new awards and adjustments. The most significant of these included more than $300 million of additional funding from recently approved change orders in our civil group, over $235 million at Rudolph and Slatton for various building projects in California, the largest of which was a $69 million education building and another $67 million at Lunda Construction in the Midwest for various civil infrastructure projects.

8:18 Several major bid opportunities over the next year have been temporarily deferred while public agencies await federal supplemental funding. However, we continue to be extremely busy working on our other bids that have not been affected. Last week we submitted our bid for the Honolulu Rail Transit P3 project and we anticipate a team selection award of that project in the fourth quarter of this year. Recall that only one other team is competing for this project. In August we will be submitting our proposal to the LAMTA for the initial planning and design services of what will eventually be the $8 billion Sepulveda Transit Corridor P3 project.

9:11 As a reminder, this project will be executed under a design support general contractor framework through which design support and preliminary design can ultimately lead to a negotiated general contract at the end of the quarter excuse me, at the end of the design period with approval process. In August, London Construction will be bidding on the $850 million I-69 project in Indiana with an award expected later this year or early next. In addition, our bid for the LAMTA's $400 million LAX Airport Metro Connector is expected to be submitted and awarded in the fourth quarter of this year.

10:03 Other major upcoming bids include the $2 billion Newark Airport Air Train with selection award expected in the second quarter of 2021, the $2 billion JFK Airport Landside Roadway Development Project, which we believe will be awarded later next year the $1.4 billion Porter Bridge replacement in New Jersey which has recently been funded and we expect to bid early next year and the $1.2 billion Metro North Penn Station access project in New York for which we are one of only three teams shortlisted. We expect to bid that project early next year.

10:51 In Northern California, we continue to talk to the owners about the $2 billion Bay Area Rapid Transit, or BART, Silicon Valley Phase II extension, which is anticipated to bid in the third quarter of next year with an award in the fourth quarter of 2021. Black Construction, our subsidiary in Guam, already has a substantial $500 million backlog, which as we've spoken, Two at great length with the Marines moving from Okinawa and that $10 billion program now finally in place and accelerating. We will be bidding on over $2 billion of opportunities on the island of Guam over the next 18 months, substantial portion of which is for the U.S. Navy and that Marine transfer.

11:49 Other sizable Sybil opportunities that we are tracking for bids further down the road include the $4 billion West Santa Ana Transit Corridor and the $1.5 billion East San Fernando Valley Corridor, both for Los Angeles MTA. The $3.5 billion Port Authority New York City Bus Terminal, the $2.5 billion Dunbarton Bridge Rail Corridor in Northern California, and the $2 billion LaGuardia Air Train project. As we have been pointing out for some time, the volume of prospective civil opportunities of significant size remains unprecedented. However, while COVID-19 has impacted the funding and timing of these prospective projects, there are still a significant number of opportunities considered critical that are likely to be funded in prior to work. Prioritized for completion.

12:51 It is widely expected that the federal government will approve a substantial supplemental funding package aimed at supporting state and local transportation agencies' critical infrastructure needs, which we hope should help backfill any funding gaps for the more complex projects we are pursuing. Our building segments larger prospective opportunities include an $800 million new hospital in Northern California, the $500 million Burbank Airport Terminal replacement, the $350 million Harbor UCLA Lawrence outpatient facility, a $350 million hospitality and gaming project in New Orleans, the $300 million Hudson County Courthouse in New Jersey upon which we've already proposed in our waiting results and a $265 million veterans home facility in Northern California.

13:55 Our specialty contractors group remains focused on supporting our large civil projects and also continues to experience solid demand for the electrical and mechanical services from our customers, particularly in New York and Texas. The specialty contractors' workload is accelerating alongside the progress of our major civil projects, and I expect that while we will see improved and sustained and better operating results from the specialty group this year and beyond, as new work in this segment is more profitable and more consistent. without the disputes that have plagued them from the past.

14:40 As mentioned earlier, we have made some notable progress this quarter on certain settlements which helped contribute to our strong operating cash. We continue to be persistent and determined in our efforts to collect the monies owed to us. Through the COVID-19 pandemic has caused delays with our owners where many of them have gone home and still not come back to work. These delays have started to ease as certain of those COVID restrictions have been lifted and we have numerous mediations and dates in place over the next 60 to 90 days that should allow significant progress for the balance of the year and concluding several of these claims and collecting the cash that's appropriate.

15:34 We remain confident in the cash flow going beyond the second quarter all the way till the end of the year. Finally, our year-to-date earnings per share results are ahead of budget expectations for the first two quarters. And we have thus far been able to offset the adverse impacts of COVID-19 with strong continuing contributions from our large higher margin civil projects, being mindful of the uncertainties around COVID-19 and its potential to affect our business. However, based on our current assessment of market conditions and our forecast for the remainder of the year, we are maintaining our 2020 earnings per share guidance in the range of $1.80 to $2.10.

16:25 With that, I turn the call over to Gary Smalley to present the details of our financial results.

16:33 Thank you, Ron. Good afternoon, everyone. I will begin with the discussion of our results for the second quarter, followed by some commentary on our balance sheet, cash flow, and then our 2020 guidance assumptions. In my discussions today, comparisons to last year's results will be on a pre-goodwill impairment basis, to better compare the normal operating results of each segment between the two periods. As Jorge mentioned earlier, a reconciliation of these non-GAAP financial measures to the most nearly comparable GAAP measures is provided in the press release we issued earlier. Revenue for the second quarter was $1.3 billion, up approximately $150 million, or 13%, compared to revenue of $1.1 billion for the same quarter of last year. The growth was driven by increased activities on the large infrastructure projects that Ron mentioned earlier, as well as on certain building projects in California and Oklahoma.

17:33 Our revenue grew in spite of the COVID-19 pandemic, which impacted our revenue by an estimated $130 million in the second quarter, mostly due to some project suspensions or delays that lasted through the middle to latter part of the quarter. Note that very few of our projects are currently delayed by COVID. The COVID revenue impacts by segment for the second quarter were as follows. $15 million for civil, $80 million for building, and $35 million for specialty. Civil segment revenue for the quarter was $569 million, up a strong 20% compared to the second quarter of last year, driven by contributions from the projects I just referred to. Revenue for the building segment was $473 million, up 10% compared to the same quarter of 2019, predominantly due to increased activities on various newer projects in California.

18:29 Specialty contractor segment revenue for the quarter was $234 million, up 5% year over year. Income from construction operations for the second quarter was $58 million, an increase of 51% compared to adjusted income from construction operations of $38 million for the same quarter of last year. The significant increase was mostly due to contributions associated with the significant volume growth we experienced this quarter in civil and building segments. Income from construction operations was negatively affected by $9 million for the quarter due to COVID, with the segment breakdown as follows. $2 million for civil, $2 million for building, and $5 million for specialty contractors.

19:17 As Ron mentioned earlier, we took a charge of $13 million in the specialty contractor segment due to an adverse arbitration ruling on an electrical project in New York, but we'll still collect $3 million from the decision. So our income this quarter would have been $22 million higher had it not been for the project charge and the COVID-19 impacts. Civil segment income from construction operations was $65 million compared to adjusted income from construction operations of $46 million for the same quarter of last year. The segment's income grew 43% year over year, primarily because of strong contributions from our large mass transit projects in California. In addition to the $2 million COVID impact in the quarter, the civil segment's income was also reduced by nearly $8 million of incremental non-cash amortization expense this quarter related to an increased equity interest and a joint venture that we acquired in the fourth quarter of 2019.

20:18 Even with the additional amortization expense, the civil segments operating margin was strong at 11.5% for the second quarter of 2020 compared to an adjusted operating margin of 9.7% for the same quarter of last year. Civil segment operating margin was at the high end of the 10 to 12% margin range we typically see for the segment. We expect to remain at the upper end of this range or even higher for 2020. Building segment income from construction operations was $18 million, up an outstanding 84% compared to adjusted income from construction operations of $10 million for the second quarter of last year. The strong increase was mostly driven by contributions from certain projects in California, Oklahoma, and the Northeast.

21:08 The building segment second quarter operating margin was 3.8%, compared to an adjusted operating margin of 2.3% for the second quarter of 2019. The elevated margin for this year's second quarter reflects contributions from certain higher margin projects. Building segment operating margin for the full year of 2020 is expected to be in the 2 to 3% range. Specialty contractors' loss from construction operations for the second quarter was $11 million compared to an adjusted loss from construction operations of $4 million for the same quarter of last year. The larger loss in this year's second quarter was principally due to the $13 million charge related to the unfavorable arbitration ruling that Ron and I mentioned earlier.

21:55 We are optimistic that as the segment's newer, higher margin projects continue to accelerate, the group's operating results will improve substantially. Interest expense for the second quarter of 2020 was $6 and many more. Thank you. Net income attributable to Tutor Perini for the second quarter of 2020 was $18.7 million or 37 cents per diluted share compared to adjusted net income attributable to Tutor Perini of $9 million or 18 cents per diluted share for the same quarter of last year. The doubling of net income in EPS in this year's second quarter was due to the factors I mentioned that drove the increases in revenue and income from construction operations.

23:05 As Ron indicated earlier, On a year-to-date basis, our EPS of 71 cents is ahead of budget, and this is even after a 17-cent year-to-date EPS impact from COVID-19 and a 19-cent impact from the adverse arbitration ruling in the second quarter. Though we cannot be certain as to how and to what extent COVID-19 might affect our business in the future, we believe that barring any significant worsening of the pandemic, the largest impacts could hopefully be behind us at this point. Next, let's discuss operating cash, clearly a bright spot in the quarter. Our second quarter cash generation of $92 million was simply outstanding. It was the highest second quarter operating cash result since our merger in 2008, with the next best second quarter result being $73 million 10 years ago.

23:58 The $92 million of operating cash is a significant improvement over the $13 million that we generated in the second quarter of last year. In this year's second quarter, strong cash contributions associated with increased project execution activities on certain higher margin projects driven by our near record backlog at the end of last year were enhanced by progress made on the resolution collection of disputed balances and a modest decrease in working capital. As Ron noted, progress on certain settlements for the quarter resulted in the collection of approximately $40 million that contributed to our second quarter cash flow. Our excellent second quarter cash flow combined with better than expected operating cash result in the first quarter of this year resulted in positive year-to-date operating cash flow of $58 million, which is well ahead of our budgeted expectations and nearly $170 million better than the operating cash performance through the first six months of last year.

25:02 For the first half of this year, the $58 million of operating cash resulted from The strong cash contributions associated with the same increased project execution activities that we mentioned, as well as the progress made on the resolution and collection of disputed balances, which more than offset a working capital increase of $69 million. In other words, the quality of our cash generation this quarter and in the first half of this year is very high, driven mostly by collections on improved project performance and to a lesser extent on the settlements. It is evident that what we are now seeing is the fruition of our concerted efforts to significantly improve cash generation. Although we've had strong operating cash generation so far this year, we expect that it will be even better over the remainder of the year.

25:49 We're tracking favorably to achieve our goal of generating operating cash that exceeds net income for 2020, which would mark the fourth time in the last five years that we have done this. As a reminder, last quarter I mentioned that our operating Cash generation for the remainder of 2020 will also be positively impacted by the CARES Act, which allows for the acceleration of the refund for our 2019 net operating loss and the deferral of the employer portion of FICA payments for the last three quarters of 2020, with half of this amount payable at the end of 2021 and the other half payable at the end of 2022. We estimate that operating cash for the last two quarters of 2020 will be enhanced by approximately $35 million by the CARES Act $15 million for the NOL and approximately $20 million for the FICA payment deferrals.

26:41 Our total debt as of June 30th, 2020 was $836 million level with the balance at the end of 2019 and down 13% compared to $956 million at the end of the second quarter of last year. During the second quarter of this year, we paid down a revolver by $75 million So it was down to $100 million as of June 30th. As many of you know, our credit facility includes a spring forward maturity provision whereby it will mature on December 17th of 2020 if our convertible notes are still outstanding at that time. We continue to explore available options to address the spring forward provision and the outstanding convertible notes. Once we have firmed up a path forward, which we expect will occur in the current third quarter, we will make an announcement.

27:31 We remain well within the limits of and in compliance with our debt covenants at the end of the second quarter and in fact have the lowest bank covenant leverage ratio that we have had in nearly nine years. We anticipate that we will continue to be comfortably within our covenant limits going forward. Ron mentioned earlier that we are maintaining our EPS guidance range for 2020 at $1.80 to $2.10 per share given our strong results through the first half of the year. We still believe that our guidance factors in the inherent uncertainties that are common in our business, such as unanticipated delays in project awards and project execution and unfavorable adjustments to our estimates to complete projects that may occur from time to time. Our decision to maintain our guidance also assumes that the vast majority of our projects will continue to operate during the balance of the COVID-19 pandemic and our hope that the worst of COVID-19's impacts are behind us.

28:27 Now let me provide an update on a couple of the assumptions in our guidance. G&A expense for 2020 is now expected to be approximately $260 to $270 million. Capital expenditures for this year are expected to be approximately $50 million, of which about $35 million will still be for owner-funded project-specific equipment. Apart from these, all of our assumptions remain unchanged from what I indicated last quarter. With that, Ron, I'll turn the call back over to you.

28:58 Thanks, Gary. To recap, despite the impacts of COVID-19, we delivered a very good second quarter result highlighted by the extraordinary cash generation as well as solid earnings and margins that are tracking favorably against our budget on a year-to-date basis. For the most part, things continue to be business as usual on our project except for new enhanced health and safety measures that have been implemented on most of our major projects, particularly in New York and New Jersey due to the pandemic. I'm still confident in our ability to achieve our guidance for 2020 and look forward to reporting even stronger results in the second half of the year as we usually do. And that second half of the year, we fully expect to have significantly stronger cash flows.

29:59 I will conclude by commenting that it's an exciting time to be at Tutor Perini, whether as an employee, an executive, or otherwise invested in our future. Fortunately, amid the havoc being wreaked by COVID-19 across the various industries, we continue performing well and are well positioned as an industry leader and fortunately an industry that has not been severely impacted by COVID-19. Our backlog is as robust as ever and our market opportunities have never been better. Excelling best where project complexity is greatest and the size is significant, we favor working on the largest, most complex infrastructure projects in the country, which offers significant long-term career opportunities and an intellectually challenging We believe we're in a multi-year period of solid growth and increasing profits with extremely limited competition for the largest opportunities ahead.

31:09 And we are now also beginning a period of strong and significantly improved cash generation, something that we have been waiting too long for and working hard to accomplish. That said, thank you. And with that, I'll turn the call over back to the operator for questions. Thank you. Ladies and gentlemen, we will now have our question and answer session. If you would like to ask a question, please press star 1 on your telephone keypad. A confirmation tone will indicate that your line is in the question queue. For any of those with speaker equipment, it may be necessary for you to pick up your headset before pressing the star keys. One moment, please, while we now poll for questions. Our first question comes from Stephen Fisher with UBS.

32:03 Please proceed with your question.

32:06 Thanks. Good afternoon, guys. Hi, Stephen. Hi, Steve. Hi. Very nice to see the cash flow coming through. We'll get to that in a minute. I just want to ask you maybe, Gary, can you just bridge the first half versus the second half implied from an earnings perspective since you're implying about 53 cents of higher earnings in the second half versus the first half. I think you'd get maybe 15 to 20 cents from the absence of that $13 million write-off. And then I'm not sure if you're, I guess you'd add back the 17 cents of COVID impact. If that's all correct, what's the rest of the other 20 cents to get you the second half to the midpoint of the guidance?

32:53 Yeah, we continue to see in the second half progress being picked up in the larger higher margin civil projects, infrastructure projects that Ron noted. Keep in mind that we're always out of the gate slow with weather and we pick up momentum as the year progresses. So we just expect more and more volume as the year progresses.

33:17 That's just a matter of fact, Steve, and it's always been that way. If you look back over the years, First quarter's the worst, the second quarter is usually mediocre, and the third and fourth quarters are always the biggest, revenue and profit.

33:31 Okay, and are you anticipating getting that $190 million and 17 cents fully back in the second half of the year?

33:41 What are you talking about? You're talking revenue at $190 million?

33:46 Yeah, wasn't that what you said the impact was in the first half of the year?

33:51 Yeah, the impact of COVID in the first half of the year, that's what you're referring to, was 190 million. Keep in mind that our budget is what we measure ourselves against and also how we project where we're going to be with respect to the end up for the year. And through the first six months, revenue is nearly on track, even with the impacts. It's almost dead on, even with the 190 million impact reflecting some of the conservatism, I guess, that we factored in. and we are comfortably ahead of EPS where we were in the budget for the first six months. Okay.

34:29 And to be very direct, all of this large civil work design build of $3.5 billion at Purple Line 2 and 3 in Los Angeles, the Newark Terminal, the California High Speed Rail, there are six major projects all of which are accelerating in revenue that are high profit. They're all maintaining their margins and that's where the increases are coming from that are able to frankly pick up any glitches or settlements or anything that affects the short term because the revenue and costs from those major works are what's driving everything. And I focus more on the profitability of those jobs and the higher margins as we evolve from much of the lower margin work into the higher margin work given the same revenue. So long and short of it, barring anything unforeseen, we're still supportive and believe in our projections.

35:30 Got it. That's helpful. And then on the cash flow, so it sounds like the second half will also be stronger than the first half. You've got $35 million. You mentioned, Gary, of NOL and FICA benefits. What other specific settlement payments do you have in the expectations there versus just sort of collection of regular receivables, and are there any specific project advance payments that you have embedded in there?

35:57 We have a number of them, and I'm not sure I want to get into the specifics, but we have a particularly large job where we have a milestone we hit where we get paid $58 million. That occurs in September. We have a mediation. In next week on a large claim we have where the owners essentially admitted entitlements and we're now haggling over how much they pay, which has a value of $30 million. We have another mediation on $60 million worth of entitlements admitted. It's a matter of whether we can agree on costs. There is a whole slew of specifics. including a final release of retention that has been delayed two years.

36:45 That's all our money and exceeds $30 million. That's why both Gary and I remain confident that our cash flow for the balance of the year will even be more significant.

36:59 Okay. And then maybe in terms of the actual DOT process, I guess how – and some state-level budgets. And I'm curious what you're seeing and how that may be affecting or not affecting the bidding timeframes, the nature of the projects, or how they're choosing whether they need to prioritize things differently. So how are budgets and any constraints affecting sort of project timing and planning for the DOTs?

37:35 Well, there's no question. I talk to all our major owners regularly about these All of these significant jobs that I mentioned earlier specifically in the budgets for, we're talking to them all the time. They're calling us for information. We're guiding their budgets. And things have been pushed back without a question until we see action from Washington, until the government puts together another bill that takes the pain away from the New York transits, the port authorities, LAMTAs, all of these major agencies that affect the world's transport or the U.S.'s transportation. They're simply putting them back 90 in 20 days.

38:25 We just bid a $2 billion plus job in Hawaii. We're about to turn in that large MTA job. Many of these that were ticketed to bid the latter part of this year, first year, have been put back six months in anticipation of another bill providing that support to all the cities and states. On top of that, there's the infrastructure bill that both the Republicans continue to talk about, but the Democrats have been very specific in their support of a $2 billion infrastructure bill. So there's just a lot in place to try to fight through the issues of the pandemic Okay. Thanks, Ron. Appreciate it. Sure. Thank you.

39:33 Our next question comes from Alec Reigel with E. Reilly SBR. Please proceed with your question.

39:41 Thanks, and nice quarter, gentlemen. Thanks, Alex.

39:47 Ron, can you touch upon the state of the market from a competitive standpoint right now? Are any peers getting concerned about the future, and does it appear as if they're getting more aggressive on bids? Possibly driving down the margin opportunities in advance of maybe some uncertainty?

40:11 No, I think it's quite the opposite. There are so few what I would call peers. Let me be charitable and say we bid against one other company on the Honolulu Rail Project. It's over $2 billion, and that company consisted of a Spanish company and two Japanese companies. We have one other proposer on the $8 billion LAMTA job, which we are very confident in, and that is a U.S. firm owned by an Italian company. Everywhere we are bidding, there is one other bidder, maybe on occasion two other bidders. And the one thing that's universal is that our peers have not done well on the large, complicated work.

41:03 As a result, you saw Granite withdraw from all major work. You saw Fluor withdraw from all major work. You saw Skanska with their U.S. operations some two and a half years ago withdraw from all major work. Although with the lack of competition, I fully expect them to come back in at some point after their reorganization is complete. Either Bechtel or Fluor have ever been a factor and it's no surprise. No, if anything it's quite the contrary. I think most of us who see how we operate have raised our prices and the attitude is most of the results on these very large jobs have been very poor.

41:49 So with our exception, and I won't get into why, we've done extremely well and we continue to raise our margins. and the way I read the marketplace, nobody's dropping margins. They're more afraid of losses than they are of procuring backlog. Margins are up everywhere. Nobody's cutting fees.

42:12 And Gary, maybe can you remind us what your options are to settle your converts by year end and what the timing looks like?

42:21 Yeah, we've... One thing we've got... A lot of cash that has come in and we continue to expect more cash to come in. That is certainly an option. We are looking at just everything you can imagine, Alex. Looking at doing different types of refinancing as well. But really, I'd just rather not comment further on what we're doing other than we're looking at options. We're zeroing in on what we think is the best option We'll move on something, or we expect to anyway, during the third quarter. And as soon as we decide on something, then we'll make an announcement.

43:06 I would also add that what I said earlier, I remain confident with the knowledge of the issues we're dealing with and the cash we're collecting. I believe irrespective of any third-party transaction, we will have the money in-house to pay off the converts without a doubt.

43:27 Excellent. And then, Gary, one last question. From a modeling standpoint, how should we think about depreciation and amortization for the full year of 2020?

43:35 Yeah, there's no change there. We're still looking at $109 million for the two together. Perfect.

43:42 Thank you very much. You're welcome. Thank you. Our next question comes from Brent Thielman with DA Davidson. Please proceed with your question.

43:55 Great. Thank you. Ron, I appreciate the color on sort of the bidding environment and sticking to local budgets. I was just curious, you know, as you've gotten deeper into this sort of COVID environment, you look at your own, you know, backlog of business and civil, anything in there that causes you concern just from a funding perspective or do you feel like that's pretty solidified?

44:18 No, I talk to all our owners. All the existing contracts are fully funded. Whether it's the Port Authority in New York on Newark, the New York Transit, or LAMTA, they're fully funded at the inception of the contract award. And there has been no sense of any issues, even with extra work and funding extra work. It's really the Newark that is just being deferred until they get stabilized.

44:49 Okay. I was a little surprised. I would have thought with traffic down, it might have been a net benefit to the civil group, but it sounds like COVID overall has been a bit of a headwind. Has that just been confined to a few projects overall?

45:03 Well, it's affected us dramatically in New York, to be candid. Now that New York appears to be out from under it, we had jobs that basically lost half their crews and efficiencies in the tunnels at New York Transit. We lost a Number of people and revenue associated on the Newark Terminal, even though we were maintained a large field force, we lost probably 100 people on the job due to COVID. So we've had impact. It's just that the owners have been supportive. The jobs have continued. We've literally monitored fevers in New Jersey. We've monitored individuals. We've taken whatever steps it took to keep the jobs going. and it appears everywhere but Los Angeles the worst is behind us.

45:51 Now Los Angeles is reared its head but all our work is going in Los Angeles and candidly if we have three to 350 people in the field driving tunnels and stations maybe we've had eight or ten instances of COVID and COVID related quarantines. So it's always there and it always has some level of impact but not demonstrably in the big picture, but you wake up and you lose a hundred million of revenue and eight or nine million of deferred margin. And it affects you when you're looking at earnings per share and that sort of thing. But overall, we continue to work.

46:32 Yeah, Ron, I just interject this. Brent, keep in mind that the COVID impact for Civil for the quarter was only 15, you know, one five, $15 million. of revenue, and $2 million of pre-tax income. So all the things Ron said are correct, but we worked around it so that the financial impact has been very minimal.

46:59 Okay. Okay. Maybe just one for the buildings group. Ron, just thinking about some of the sectors there, convention centers, lodging, it might be a tougher spot to be in in the years ahead. I'm just curious. Your thoughts and outlook for that business group and how you think about moving those resources over the next few years, just given that backdrop.

47:24 As you know, the building group is not a large contributor to our income. They are a large revenue generator, but not large income. And a significant part of their income is in our fixed price building work, which we continue to do. I don't see too many hotels and casinos. Going to be built in the next few years. We have the one that was shut down in South Carolina and mothballed for the time being. That was a $190 million project that was well underway but stopped. I see the building business having a difficult time sustaining the revenue and profitability, let's say, after next year for the next few years.

48:11 and until the country decides what it's going to build and what it isn't, obviously everything to do with airlines as well as hotels is virtually frozen. So I don't have a crystal ball to tell you when it can get back to normal. I assume at some point it will. When that point is, I can't tell you.

48:34 Okay. Well, thank you. Congrats on that.

48:36 And Brent, one thing. In the meantime, it's a blessing to have the the $10 billion of backlog that we have so that as things settle down with COVID-19 and the impacts are fully known, we'll continue to work off that fully funded backlog. Yep.

48:56 Yep. Thanks, Gary. Thank you. There are no further questions at this time. I'd like to turn the floor back over to management for any closing remarks.

49:07 Nothing further to add. Thank you, everybody, and we'll catch you next quarter. Ladies and gentlemen, this concludes today's web conference. You may now disconnect your lines at this time. Thank you for your participation, and have a great day.

Follow Tutor Perini Corporation into a list and get an email when it puts out news.

Latest news releases

Companies on this call

Speakers

Jorge Casado

Vice President of Investor Relations

Alec Reigel

Analyst, E. Reilly SBR

Brent Thielman

Analyst, DA Davidson

Stephen Fisher

Analyst, UBS

Gary Smalley

Executive Vice President and CFO

Ronald Tutor

Chairman and CEO

More from Tutor Perini Corporation