Golar LNG (NASDAQ:GLNG) Q3 2020 Earnings Call
Company
Golar LNG Limited (NASDAQ:GLNG)
Period
Q3 2020 earnings call
Date
Fri, Nov 20, 2020, 10:00 AM ET
Replay
Watch the replay on this page · 1 h 13 min

On 6ix: 6ix.com/event/golar-lng-limited-glng-q3-2020-earnings-call

Replay

Transcript

Automated transcript · Written by software from the replay's audio. It can mishear names and figures; the replay is the record.

0:00 Ladies and gentlemen, thank you for standing by and welcome to the Color LNG Limited 3Q 2020 results presentation conference call. At this time, all participants are in the listen-only mode. After the speaker presentation, there will be a question-and-answer session. And to ask a question during the Q&A session, you will need to press star and 1 in your telephone. I must advise you that this conference is being recorded today, Monday, 30th of November, 2020. and I'd like to hand the conference over to the first speaker today, GOLOR CEO, Mr. Ian Ross. Thank you and please go ahead.

0:39 Thank you, operator. Good morning, good afternoon, everyone. Welcome to the GOLOR LNG 2.3 2020 results presentation. My name is Ian Ross and I'm the CEO of GOLOR LNG. Today, I'm joined on the line by CFO Karl Fredrik Staubo, replacing Karl Mitchell Thompson, who has resigned from his position due to personal reasons. We'd like to thank Callum for his contribution to GOLAR. We're also pleased to have Eduardo Maranhao, CFO of Hygo, and Thor-Olaf Proim, Chairman of both GOLAR LNG and Hygo with us today. And as usual, we also have Stuart Buchanan, Head of Investor Relations on call. I'd like to draw your attention to a forward-looking statement on slide one. And if we turn to slide four, let me give you some highlights.

1:26 Before Karl takes you through the numbers in more detail. Today we report an adjusted EBITDA of $57 million and revenue of $95 million for the quarter, which is driven by a further solid FLNG performance and a steady result from shipping. In shipping, we achieved overall time charter earnings of $39,000 per day, which is ahead of guidance. with the TFDEs earning just under 44,000 per day if you exclude dry dock days. We ended the quarter with a shipping revenue backlog of 198 million compared to 147 million at the end of Q3 2019. Our FSRU LNG Croatia conversion remains on track for handover to our customer LNG Hrvatska in December, at which time we expect to release $17 million in cash from the project and a further $30 million of cash in January next year.

2:26 Our FLNG operations maintain 100% commercial uptime through the quarter. FLNG GIMI force majeure event with BP has ended, resulting in the project schedule being extended by 11 months and with no other changes to contractual terms. and in downstream, Paul Hanrahan has been appointed as the new CEO of Hygo Energy Transition, that's the new name for Gola Power. Full capacity payments were earned from the Sergipe Power Station and FSRU Nanook and more progress has been made towards a Barkarena Terminal FID. Turning to page 5 and an update on governance, which we take very seriously. The internal review that was instigated following the allegations against the former CEO of Hygo was completed with no findings of wrongdoing.

3:14 The review has not identified any evidence establishing bribery or other corrupt conduct involving Hygo and confirms solid corporate governance and compliance. Eduardo will go through this overall timeline and provide more detail on Hygo later in the presentation. More detail on the business segments to follow. Let me now hand over to Karl to take you through the numbers and more detail on financing. Thank you.

3:42 Thank you, Ian. I'm looking forward to take on the role as CFO for Golar. My name is Karl Fredrik Staubo, and I will start by taking you through the summary results on slide six. Shipping TCE for the quarter came in at $39,100 per day, higher than our guidance of $35,000 a day, and above Q3 of last year at $35,200. However, we were seasonally down from Q2 as expected. FLNG Healey continued its solid and stable operations with 100% utilization and earnings in line with Q2. Net loss for the quarter ended at $22 million. We report a cash position for the quarter of $177 million, of which $100 million is restricted cash related to our letter of credit on the FLNG HILI and consolidated VIE cash balances related to our sale leaseback finance vessels.

4:46 The unrestricted cash position for the quarter of $77 million was negatively impacted by $17 million due to having to equity fund Gimme CapEx during the BPFM event. Following the ending of the Forsmer Share event, the draw stop under our $700 million facility available during construction has been lifted, and we have made a $75 million draw, which have replaced the $17 million of equity CapEx, increasing our liquidity post-quarter end. This realigns the drawdown ratios to the original debt equity funding ratios. And adjusting for this equity CapEx installment, our cash position for the quarter would have been $94 million.

5:39 Adjusted EBITDA for the quarter came in at $57 million, a beat against consensus at $52.4 million, driven by higher than expected shipping rates. Returning to slide 7 and adjusted EBITDA development, quarter over quarter our EBITDA was down by approximately $10 million from $67 million in Q2 to $57 million in Q3, primarily driven by seasonally lower shipping rates, which went from $45,000 a day in Q2 to $39,000 a day as mentioned. We also have a COVID-19 related closure of the shipyard where the Golar Tundra was being dry docked, which resulted in significant unscheduled off-fire during the quarter and contributed to the net reduction in our fleet utilization from 93% in Q2 to 80% in Q3.

6:39 As expected, vessel operating expenses at 28.2 million were higher than those at Q2, which came in at 24 million. The 4 million increase was mainly due to catch-up repairs and maintenance carried out following the lifting of COVID restrictions. As for our trailing last 12 months EBITDA, we're up from $283 million a year ago to $294 million last trailing month. mainly driven by an average increase in our achieved shipping rates. Turning to slide eight and our corporate financing, we have two corporate facilities maturing before year end, a $150 million corporate facility secured against our Hygo shareholding and a $30 million margin loan on our shareholding in Gola Partners.

7:35 To address these upcoming maturities, we have entered into a $100 million committed corporate debt facility secured in our Hygo shares. This will be drawable at maturity of the 150 facility that now maturing. Furthermore, we are in advanced discussion for an incremental $125 million corporate credit facility drawable upon Hygo IPO. In addition to these facilities, Other key financing events that will increase our available liquidity include contractual drawdown on the Golar Bear facility of an incremental $10 million targeted in January 2021.

8:21 As Ian explained, the acceptance and delivery of the Golar Viking project converted to an FSRU and on its way to acceptance to LNG Croatia. that will free up net liquidity of $47 million between December 2020 and January 2021. We've also received term sheets for opportunistic refinancings of the vessel Golar Frost and a potential renewal of the maturing DMLP margin loan, which combined can raise $70 million in liquidity to Golar. The net potential liquidity effect, if we draw on all of these facilities, will be an incremental $172 million in liquidity after repaying the maturing $180 million of corporate debt. So we're comfortable with the liquidity situation, assuming we draw on all these facilities.

9:17 And we think that will create significant flexibility to continue the growth of the company. Turning to slide 9, we have an update on our FLNG GIMI conversion funding sources. We have, as Ian alluded to, agreed with BP to extend the project by 11 months. That is expected to come in at an incremental construction cost of $36 million. Furthermore, we have shifted some of the capex to later in the construction period to benefit near-term liquidity. For next year, the reduction is $7 million in equity requirements before we increase in 2022 and 2023, so we've pushed the installments slightly out.

10:13 We're also happy that the increase in the construction capex is not more than the $36 million that we anticipate to be the total increase in construction costs, and we worked hard with our subcontractors to make sure that the increase in costs are not more significant given the 11-month delay. That concludes it for the financing section, and I'll now head over for Ian to run through the shipping section.

10:45 Thank you, Karl, turning to slide 11 and shipping. The quarter commenced with JKM at around $2.15 per mbtu and quoted TFDE headline spot rates of around $30,000 a day. The seasonal upswing was slower than usual due to a combination of around 120 US cargo cancellations over the summer, higher than normal European storage levels and weather related supply interruptions which continued into early September. As production resumed Late Q3, the shipping rates resumed their seasonal upswing, albeit later and lower than last year. The quarter ended with JKM at around $5.15 per MMBTU and quoted TFDE headline rates of around $59,000 a day. Subsequent to that, we have seen JKM above $7 and spot rates briefly above $100,000 for single voyages before dropping back.

11:47 Remaining true to our shipping strategy and our focus on utilisation is serving as well. Our Q3 utilisation of 80% is significantly up on Q3 2019. Our TCE of 39k for the quarter whilst above guidance was, as Karl has mentioned, also adversely affected by the tundra being in dry dock for much longer than planned due to that COVID shutdown in Singapore. And this will spill over into the early part of Q4. She's now, of course, out of Dry Dock. Additionally, we've built 123 million of shipping backlog this quarter, which you can see on slide 12. Utilisation going into 2021 is strong, with around two thirds of 2021 fleet days already backed by contract. And whilst we may sacrifice a little of the upside during the winter months, we expect to more than make up for this during the rest of the year. and we're anticipating a TCE of around $50,000 a day for Q4.

12:48 And as LNG prices cycled up and as mentioned we did see JKM at over $7 over the last few weeks, the prospect of FLNG development starts to become more interesting. So let's now have a look at FLNG in slide 14. Hilly performed well in the quarter with 100% commercial uptime as Karl noted and she has offloaded the 47th cargo The annual two week maintenance shutdown was completed without incident during the quarter, which I think deserves a mention due to the COVID constraints that the team operated under during that time. We agreed an amendment to the LTA with Perenco and SNH, which essentially does two things for us. Firstly, it removes the 500 BCF cap on the contract volume and so converts the contract to an eight year fixed duration deal.

13:37 And secondly, it allows us to invoice for any overproduction During a calendar year, which will amount to around $5 million for the overproduction to the end of last year. We expect the agreement to be formalised in due course. And our discussions with Perenco on LNG production volume increase, which is enabled with that amendment, within the remaining term of the contract, continue in the right direction. And we anticipate that Perenco will start its well campaign before the end of Q1 next year in order to prove up the additional reserves to potentially increase utilization of HILI. Should we reach agreement with Perenco, there will likely be a new risk-aligned tariff payment for that portion of additional volumes rather than on a fixed tariff.

14:25 Turning to slide 15, on FLNG GIMI, we concluded the FM issue with BP. As Karl mentioned, as a result of the delay to commercial operations of 11 months, importantly, all other aspects of the contract remain the same. and the impact on the overall budget is minimal and the financing milestones have been restructured as Karl described. On the project in Singapore, our contractors are ramped up to over 2,400 people working within COVID restrictions and getting on with the project. We expect the next dry dock, which will include attaching parts of the large sponsors to the hull to go ahead before the year end. On the FLNG business development pipeline, we've experienced a material uplift in the level of interest in FLNG with a number of new inquiries during the quarter.

15:13 The nine opportunities currently being discussed with financially strong counterparties are geographically spread and include potential deployments in West Africa, Asia, the Mediterranean and the Americas. We are in active engagement on both conversion and new build options and remain convinced of not only the commercial and schedule benefits of our design, but increasingly of the competitive carbon footprint of our offering. Clearly, we're focused on delivering GIMME right now, but these deals do take time to put together and I'd like to think that there's potential for good convergence between opportunities being ready for FID, possibly maybe in 2022, and our ability to put together a financing package for the projects. With that, can I hand over to Eduardo Maranhao to take you through the details on Hygo.

16:06 Thank you very much Ian and good morning ladies and gentlemen. So switching to slide 18, I just wanted to give a brief recap of the major events that took place over the past eight weeks. So at the end of September, our IPO efforts were put on hold as a result of allegations involving our former CEO for actions predating his work at Heigl. Immediately after that, our board of directors engaged with external legal and accounting advisors in order to conduct a detailed internal review of the company's procedures and existing compliance policies. The final outcome of this review has been delivered in the end of October and has not identified any evidence establishing improper or other corrupt conduct involving Heigl or its executives and confirms solid corporate governance and compliance.

16:57 Also in September, our existing power station in Sergipe faced issues with one of its four step-up transformers, which temporarily reduced the available generating capacity from 1.5 gigawatts to one gigawatt until the end of the second quarter of 2021, when a replacement transformer is expected to be installed. We maintain business interruption insurance cover and we do not expect material financial impact from this event. Also on September 30th, Haigo was the only qualified bidder to present a valid offer in the official tender to take over the Bahia terminal from Petrobras. Petrobras subsequently increased Haigo's perceived integrity risk, leading to a temporary disqualification of its bid.

17:47 We have then appealed from this decision and now expect a final outcome from Petrobras before the end of the year. On October, Paul Hanaren was appointed as our new Chief Executive Officer. As a former CEO of AES Corporation, Paul brings extensive experience in international business development in emerging markets and has the right skill sets to lead our growth prospects. We remain fully committed to the development of our terminal in Barca Arena. and after our mutual decision to terminate the existing MOU with Norsk Hydro, we have entered into a new agreement with the state-owned gas distribution company of the Pará state, Gás do Pará, with the goal to supply the existing regional demand for cleaner fuels.

18:36 Also in November, we have reached an important milestone in the development of the Barca Arena terminal, when the Brazilian authorities granted us with the final authorization called Outorga, to build the 605-megawatt power station and associated LNG terminal. Just as of last week, we have also been shortlisted in the Open Season Tender to supply large natural gas volumes to Copper Gas, the state-owned gas distribution company of the state of Pernambuco, which has as its shareholders the state of Pernambuco itself, Mitsui, and also Petrobras. This is a fundamental commercial initiative to accelerate the development of our terminal in Swapia. As seen above, we strongly believe that our ability to develop large-scale projects and enter into long-term partnerships in Brazil remains unchanged.

19:29 With our network of strategically located terminals and critical downstream infrastructure, we will continue our mission to deliver cheaper and cleaner energy to this huge market. If I may switch to slide number 19, The idea would be to give an update on some of the developments in our small-scale LNG business. So we continue to execute on our strategy. The first batches of equipment, including ISO containers, mobile regas units, and gas filling stations, have arrived in Brazil. And much more are expected in the coming weeks. So we have now over 100 ISO containers in the country. In order to supply our first volumes, we have partnered with Galileo, to build small liquefaction units in the states of Bahia and São Paulo.

20:17 And Haigo will be the first company to deliver bio-LNG in the country by using bio-methane from an existing landfill in São Paulo and transforming it into LNG. In the south of Brazil, we're also building our strategic distribution hub in the city of Uruguaiana, which will allow us to supply the existing demand of this important region, including the states of Rio Grande do Sul, Santa Catarina, and Paraná. If I may switch to slide 20, I also wanted to give an overview of the general update on some of the terminals that we have been developing in Brazil. So I wanted to highlight the significant milestones that we have achieved in the Barca Arena terminal. Based on those, we believe that we could be in a position to take a final investment decision in the next couple of months.

21:06 I would like to highlight, for example, the issuance of the installation license for the construction of the LNG terminal and associated facilities for the power plant. We have also been awarded the long-term port concession by CDP for the use of the existing facilities in the Vila do Conde port in the city of Barcarena. We have also received binding EPC proposals for the construction of the 605 megawatt power station from leading international suppliers. Moving over to SUAPE, We have also made significant progress over the past quarter. Subject to the receipt of final installation permits, we could also expect a final investment decision in the next couple of months. And upon the arrival of the first Avenir vessel expected for next year, SWAP is positioned to be the leading distribution center of LNG in Brazil.

22:01 Our terminal in Santa Catarina, which I also wanted to highlight, is also coming together. Preliminary environmental licenses and approvals from both UNTAC and SPU have been obtained. An FID is expected before the end of next year. Lastly, when it comes to Bahia, although we cannot guarantee the outcome of Petrobras' decision, we are confident that our proposed approach is the best solution to address all the commitments that were made towards the antitrust authorities in Brazil. It also goes in line with the government's efforts to provide cheaper and reliable gas supply to the vast local Brazilian market. So considering the development of all of our terminals, Heigl could be in a position to deliver over 25 million tons of LNG in Brazil in 2022.

22:53 Thanks, Eduardo. If we turn now to slide 21 in our ESG progress, I can highlight a couple of items. Firstly, the carrier fleet achieved best-ever fuel efficiency during the quarter, resulting in lower CO2 emissions. And the other point that's new is our recently announced partnership with Black & Veatch, under which we will be jointly exploring opportunities to marinise some of the processes and activities relating to the hydrogen economy. The initial focus will be on two areas. Firstly, CO2 management, such as capture, storage and transport, initially from the LNG supply chain, but equally could be from other industrial users. and secondly floating production of blue ammonia. So that's ammonia produced using methane for fuel but capturing the carbon from the exhaust stream. Two focus areas are clearly related but there may well be separate market opportunities evolving from the work.

23:46 Early days but it does look interesting. So summarising our priorities on slide 22. We will focus on opportunistic upside now that the majority of the shipping fleet is on term charter. In FLNG, our focus is to deliver GIMI safely, on time, on budget, and to continue to progress discussions for potential expansion of HILI, plus development of our new-build Mark III opportunities. In downstream, Haigo will focus on reaching FID on the terminal, as Eduardo has said, at Barca Arena, building out the business in Brazil and pursuing international opportunities. focus on concluding the refinancing activities that Karl discussed and of course we'll complete our budget cycle to confirm a sustainable reduction in G&A and then get back to the simplification of the GOLA group structure.

24:41 I'm pleased now to hand over to GOLA Chairman Torla Troim for some remarks prior to Q&A.

24:49 Thank you. I think I was on this call a year ago and giving a little bit of reflections from the board I want to do it again, particularly in this situation we have been through in the last couple of months. It's this year, 20 years since John Frederiksen and I went to Singapore and bought a company which at that time was called Osprey. The jewel in that company was 5 LNG carriers and a lot of knowledge about how to operate ships, which then could compress natural gas into 1,600 of the volume, freeze it down to 167 degrees Celsius, and we thought it was a pretty cool business in all possible ways. The vision we had when we bought the company was that LNG was an interesting energy going forward. At that time, nobody talked about CO2 and pollution, renewable businesses were extremely small, and the reason we liked the opportunity was that you could transport large volumes of energy from one part of the world to another part of the world. We noticed that the energy and gas prices were very different in different countries. Poor countries with high growth in population typically had Thank you very much.

26:19 LND became cheaper. Gulag was a pioneer in his business, converting the first floating re-gas terminal and also delivering the first successful FLND vessel. The FLND vessel we have working for Perenco in Cameroon today is producing gas which would otherwise have been flared or re-injected. For me, that's sustainable value creation. Greta Thunberg was probably not born when we bought Osprey. But the focus the world has today on CO2 reduction has created a new world, at least in part of the world. It's important to know that 85% of all energy in the world is still produced from hydrocarbon. For the next 20 to 30 years, hydrocarbon will produce the material part of the world's energy. But there are different kinds of hydrocarbons.

27:10 The refinery in Brazil replaced heavy fuel plants with LNG. They can save 750,000 tons of CO2 on an hourly basis. Add to the fact that it will also save significantly energy costs and it looks like a very easy decision to make. We can sit in Europe and the USA and we can drive our Teslas and think that its renewable market will take off and the world will change very, very quickly. Just remember that the amount of energy consumption in these markets hasn't gone up for 10 years. 20 years ago, China consumed approximately half of the energy consumption in the U.S. Since that time, the energy consumption in the U.S. has actually gone down, while the energy consumption in China has gone up three times, and is today approximately 50% larger than the U.S.

27:57 India has doubled its energy at the same time, and remember that the major power development in these countries is still coal. Cold. Between 65 to 70 percent of the energy consumed in these nations are cold-fired. It's cold because it's cheap. For the developing world, energy is affordability. It's their way out from poverty. When you come to Delhi, you understand that pollution isn't what the politicians are focusing on. They take what they can get for the money they have. The good news is that the new technology is making LNG cheaper. This summer we traded LNG, as Ian said, for less than $2 per mm BTU, which is $10 oil, $10-$20 oil. You're cutting 30% of the CO2 emission, you're cutting 70% of the particle emission, and you're cutting 100% of the SOx if you can convert anything from fuel to LNG.

28:51 Then we have something healthy and something cheap. Then you have a growth commodity. and it is a commodity that grows 10% a year. It's not a mining company in the world today. You don't think about switching from diesel or heavy fuel to LNG. Every day you're reading stories about shipping companies, you know, building massive container vessels, smaller boat carriers, whatever they are, they're converting it to LNG. They do it because it's cheaper? It's cleaner. They expect a carbon tax to hit them. And they're also doing it for the fact that the infrastructure for global distribution of LNG is now coming together. In China, the import in the COVID year is up more than 12%. Last month, it's up 25%. They already have 450,000 trucks working on LNG in that country.

29:40 And that's the second leg of the energy transformation, the transformation from coal to LNG. In India, they just announced last week that they're now going to build a massive infrastructure for LNG, including 1,000 petrol stations. I'm proud of what the team in Golar have delivered under Ian's stewardship. Technically, they are as good as you can get them. I'm proud when companies like Exxon and BP come to stay in our offices for several years to learn about FLND technology. I'm proud of the work done by the shipping team to reduce the risk in our shipping portfolio and to cover and to get contact with serious, solid partners. I'm proud when I come to see the owner of Perenco, a private oil company, who produced 485,000 barrels, and meet the guys who are extremely thankful for what we have pioneered together on the hilly. I'm proud of the fact that the people in Brazil over the last year have built a pipeline in the fifth largest nation in the world, a pipeline which might in three years be bigger than Petrobras LNG.

30:45 I'm proud of the fact that they know in a couple of weeks we'll produce biofuel, fueling trucks from a landfill station in Sao Paulo, and that we're working exclusively with the biggest petrol distribution in Brazil. What I'm not so proud of is the way we have financed and marketed this company. We have a lot to learn from some of our other competitors. We trade at close to 100 times book, while we are trading at 60% of book. When you're building power stations and FLNG costing more than a billion, and it takes you four years before you see any cash, you are in need of a strong liquidity buffer. And even if the board and management know that we have flexibility in our balance sheet to sort out these financings, investors shouldn't have to bother about short-term liquidity events. Their focus should be on the 20-year cash flow coming towards them, and opportunity that gives for a stable long-term dividend scheme.

31:44 As chairman of the company, I should take the main responsibility for the fact that too much time in this company has been spent on these matters. But when you have values, you can get liquidity. You can borrow on your house when you know you have rented it out for the next 25 years, and you can balance the amortization of that bank loan with your rental income and still have money left over. That's the flexibility we have. With a high cost stake based on the IPO price range, we'll have a value of 900 plus. Or a gimme vessel with a 10 times multiple is worth 2.2 billion. There are significant borrowing base. Let me finish with some words about the recent events. We're all sad that Callum Mitchell Thompson decided to leave the company.

32:31 We liked Callum both personally and professionally. He came with new views. He came from the House of Lords, and he's probably going back to the political world. He took the decision to leave after six months based on a personal life preference, which he also confirmed to some of our largest investors. And he left the company with a nice gesture that he will always remain an enthusiastic supporter of Golar and the team. I'm pleased to say that his role has been currently been taken over by Karl Staubo, who knows the company very well and who, as late as last week, confirmed its ability to deliver attractive financing to the company. Let me also touch about the Brazilian events which have hit us hard on the September 23rd when we were meant to price the Hygo IPO and the book actually was covered.

33:21 This led to the fact that the former CEO, Eduardo Antonello, who was totally instrumental in building Hygo from day one, had to leave the company. The acquisition against Antonello is linked to events that happened five years before he joined our company. The board of Hygo has from day one meant that this investigation not in any way indicated any wrongdoing was done with Hygo. However, the board started an external review of business. Close to 50 people were involved in five weeks coming through the company from A to Z. No wrongdoing was found. It was four weeks of hell. with a lot of sleepless nights for a lot of us. And I'm pleased to say that even if we're still suffering from being underserved, dragged into something which we should never have been a part of, that the business is getting back to normal.

34:11 We have subsequent to the event concluded a lot of new business in Brazil, as talked about by Maranhao, including being awarded critical installation licenses from Brazilian authorities, signed deals with state-owned companies, The ventures with VR are progressing well, and we expect to take FID on the Bacarena terminal prior to the air-end. We are in addition progressing very well on some of the international ventures. I'd like to thank our board member Paul Hannan for stepping in and taking over the CEO role. Paul used to run AAS, a Fortune 500 company for 10 years, and certainly have the skill sets and energy to help us make Hygo into that industry leader in energy transition we truly deserve to be.

35:01 Both the Hygo board and the board of Golar LND are fully committed to complete the IPO process. The SEC documents have been updated with recent events and have been reviewed by auditors and lawyers, but have so far not been filed. The timing of the IPO will be driven by market conditions, ongoing business operation and business development activities. As a result of the delay of the HIGO IPO, GULAR has been approached by industrial players which have expressed interest in different transactions involving HIGO or HIGO assets. The board of GULAR and the board of HIGO will consider these requests but the main track is to develop the company and the great potential we see in this business as an independent company through an IPO.

35:51 People have today an extreme focus on the new energy driver like hydrogen, ammonia and others. GULAR entered into this website, as Ian mentioned to you, and we have done it with a very credible engineering partner, Black & Witch. We want to be an energy transformation company. However, I've learned one thing through my experience in LNG. 20 years is what that LNG transformation took. We are today the only independent, fully integrated LNG company developing from wealth to grid. It's our vision to maximize the value of that strategic position over the next 10 to 20 years with strong focus on building LNG infrastructure in emerging markets. We don't want to wait 20 to 30 years for costs to come down on hydrogen production as it has with LNG over the last 20 years, when we really can make good business building the LNG infrastructure today.

36:50 When we can sign 25-year deals with energy majors and with PPIs on an every day basis of around five, I generally think we found a very lucrative business. Our target is now to build the size of our platform so big that the new instrument of financing becomes available for us. That should come with increased EBITDA, which is already programmed into this company by the $6 billion in EBITDA backlog we have secured. We need to convert from project financing to corporate financing, and we need to simplify the complexity of the corporate structure, which is a clear target for the board. We truly support the analyst's opinion that the value of this company is significantly higher than the current share price and rest assured that the board will do anything they can in order to materialize that differential.

37:48 That might include direct distribution of assets, sale of assets, demerger or whatever it takes in order to get the underlying value of this thing up. If we can deliver cheaper and cleaner LNG to the world and make a solid long-term return, I think we have a unique good business model. Now it's time for all of us in Godal to convert a good business model and a great integrated platform into a solid return to shareholders. You truly deserve it and we have a job to do. Thank you.

38:24 Thanks to all of them. And with that, I'd like to now hand back to the operator for questions. Thank you, ladies and gentlemen. We will now begin the question and answer session. If you wish to ask a question over the telephone lines, please press star and one in your telephone keypad. Once again, for those who wish to ask a question, please press star, one in your telephone keypad. Okay, our first question comes from the line of Dan Nolan from CTO. Please ask your question.

39:03 Yeah, good morning. First, let me say I appreciate the color that you gave on all of the various projects as it related to Hygo and all of the different various things you're doing in Brazil. I did want to ask, first of all, you'd mentioned the Sergipe power plant had a transformer issue. Could you maybe talk through a little bit, and I appreciate that it's covered by insurance, but could you maybe talk through a little bit what that might mean with respect to cash flows and earnings from Hygo or from the business until it's resolved?

39:43 Sure. Hi, Ben. This is Eduardo here. So, as I mentioned before, we expect that the transformer will be replaced by the end of the second quarter of next year. and until then, we continue to receive our capacity payments according to the PPA. So the capacity payments remain unchanged. As you may recall, we do benefit from a 60-day notice whenever the power plant is called for dispatch. And in the event of the power plant being called for dispatch, we would have to compensate for any exposure between the current spot electricity prices and the prices that were paid in the contract at the point in time. That exposure is then covered by insurance as mentioned before.

40:32 So we do not expect a material impact in the event of not being called for dispatch. And in the event of being called for dispatch, we are covered by insurance for that.

40:44 Okay, that's helpful. And then secondly for me, just as it relates to the two-thirds of the shipping book that is now contracted for next year, and I appreciate that probably some of that's on a floating rate basis, but is there any color that you might be able to give us on the type of rate that you've been able to aggregately secure for that two-thirds of the business for next year?

41:12 Hi Ben. So you're right, we do have ships on index link charters, a couple of ships that potentially could be in the spot market, but the vast majority of the fleet is on a fixed rate structure, some of it on up to a year and some of it on slightly longer. We're not guiding to longer term TCEs, but I think it's fair to say that the structure that we've put in place and our focus on through year TCE is we're moving in the right direction and I think directionally we wouldn't want to be going backwards from what we've achieved this year.

41:53 Okay, so better year over year I guess is how we should think about modeling it for that portion.

41:59 Yeah, at least as good as.

42:02 Okay, all right, perfect.

42:03 Well, that's my two questions. I'll turn it over. Thanks, guys. Thank you. Thank you. Your next question comes from the line of Mike Weber. Please ask your question.

42:19 Hey, good morning, guys. How are you?

42:21 Hey, Mike.

42:23 Hey, so there's obviously there's a ton to swing at here, but I might as well start with with Hygo and maybe maybe Tor. I know you reference as being a personal issue, a personal issue with regards to Callum, but Can you just confirm that his departure is in no way related to what happened with Hygo this fall?

42:47 Yeah.

42:48 Okay, good. And with regards to that review...

42:54 I think I specifically said that he had been in contact with some of the biggest shareholders and expressed why he's leaving. It's not related to that.

43:03 Okay, yeah, just the timing alone kind of bears the question. In terms of that review, I mean, it certainly seems like I know there was a pretty lengthy review in terms of digging into some of the details in Brazil pre-IPO and then certainly kind of post-IPO. Were you guys able to coordinate at all with Brazilian authorities? I'm trying to think about an eventual high-go IPO if you do go down that road. To what degree can you formally lift any potential overhang there? I guess maybe the right way to ask that question is, has there been an ongoing dialogue with with any of the authorities in Brazil with regard to the LNG business specifically? Are they giving any comments there to you all?

43:49 Absolutely, Michael. So, hi, this is Eduardo here. As I mentioned during the presentation, we do not have any impediment to continue to operate and to do business in Brazil. And I think that has been clearly stated by the number of different transactions that we have entered since all the events took place. So I can refer to MOUs that have been signed with the state-owned entities, licenses and authorizations that have been granted by the federal government.

44:17 Those are all signed subsequently to the initial issues to begin with, so I'm not sure if that data stream actually validates the question I'm asking. I'm really just asking whether were you able to coordinate with the authorities in Brazil with regard to that independent review in any way?

44:33 Well, when it comes to the authorities, we have not been questioned. We have not been asked to provide any further explanation to that. I mean, the events that happened with Antonello refer to him on a personal level and do not indicate the company in any way.

44:50 Sure. Yep. Okay. Just to maybe pivot, and Tor, you mentioned in your remarks that Something I think we'd all kind of suspected that you guys would have been approached probably immediately from interested parties around other strategic options for that Brazilian business. I think most people kind of view as kind of one of the crown jewels of the EM kind of frontier state energy transition. If you're in a unique position in the sense that you actually got almost completely done with an IPO, and then subsequently had to pull it. Is the right way to think about the valuation benchmark you would use to evaluate strategic interest that value you would have gotten in the IPO? And is that how you're looking at it and how we should think about it if someone can come in and kind of beat that bid? Is that the right way to think about when you'd pull the trigger on maybe some other strategic transaction?

45:46 Yeah, I would say if you think about it that way, We had an IPO range which was between 1.8 and 2.1, but neither Goulart or Stonepig were selling any shares. We were issuing primary shares. We were not selling any shares. So from that point of view, you can probably assume that we think that the value can be higher, and thereby we do not consider any kind of lower price for any of these assets. I think we know what it's worth, If anything, it's probably, I would say that with the development we now have, I think we continue to build value. It was one month of hell, but I think we are now on track again. I'm super happy with the team. I think Paul and I have also brought in some of the ex-guys that he used to work together with, and they're doing an excellent job getting this up and running. I think when it comes to things which are panicking, I think it's going to be I shouldn't say this, but I think it's going to be very hard, for instance, for Norsk Hydro to develop that thing with LNG without being in contact with AIGO. And I think they clearly see that there is no alternative.

46:58 We've spent five years on permitting this thing.

47:02 Gotcha. Let me sneak one more in here for Ian. You mentioned the GIMI and AIGO. BT and Cosmos recently downscaled TOR2 to 5 million tons, which could imply there's a second FLNG unit that could potentially be in play there. Is that your understanding? And then to where would that opportunity rank within those nine or 10 projects that you mentioned you guys are working on?

47:28 So Mike you know it's not our practice to comment on anything other than contracted work that we've announced and it's mentioned many times before and with specific reference to GIMI any dealings that we have with BP do remain under strict NDA but I do refer you as you've mentioned BP's public statements on the subject it would be no surprise for you to see that the cost structure of any future phase is important and then I'd simply repeat that our view that Golr's floating LNG solutions are cost schedule and carbon competitive and we keep pushing for opportunities to discuss our competitiveness with a large number of large and financeable counterparties. I would say that speaking specifically and hypothetically about BP, our portfolio of potential FLNG customers is very heavily weighted to large companies that we can back finance against and that can lift projects, particularly when you look at their ability to take the cargoes themselves.

48:30 So any company that has the characteristics of being able to sort out their own offtake and give us a good security package with which we can finance the project, then we're very, very interested in speaking to them.

48:45 I think Ian and the guys have done a great job selling this to the majors and I think there is probably a lot of majors who are afraid of building another Prelude. So from that point of view, they are looking at solutions which work. When you see that we have delivered 47 cargoes with Hille, and the number of cargoes from Prelude is probably less than half of it, and you see the cost differences. I think people are now searching for cheaper solutions from the majors which works, and I think our team has that credibility. So the portfolio you have today is totally different from what it was three years ago.

49:26 Yeah, it certainly seems like the opportunity set is actually kind of quietly expanding this part of the cycle. So good to hear. I'll turn it over. Thanks for the time, guys.

49:34 Cheers, Mike. Thank you. Thank you. Your next question comes from the line of Sean Morgan from Evercore. Please ask your question.

49:47 Hey, guys. I think my first question probably is best suited to Eduardo. And it was a question on the Bahia lease with Petrobras. And so I'm just wondering, with the bid acceptance from Petrobras, is that ongoing? And are there other counter bids out and outstanding that you guys are sort of competing against at this point? Are you the last sort of last man standing on that? and also maybe just help clarify what this ruling by the Brazilian Mines and Energy Administration related to Bahia is. Is Petrobras dragging their feet because they're not really anxious to lease this asset or is it more just contractual legal issues?

50:33 Hi. So let me just try to clarify here what exactly was the Bahia terminal tender. So we were the only company which was qualified to present a commercial bid, and that took place on the September 30th. We presented a commercial offer which basically had all the commercial, technical, and all the regulatory requirements posed by Petrobras. Just on the day after that, Petrobras, on the grounds of a perceived high integrity risk for Hygo, they disqualified Hygo from the process. but we have remained as the only one that have presented a commercial offer. So based on that, we have then appealed against that decision from Petrobras and we continue to discuss a final outcome for that process.

51:25 I'm not in a position to comment what were the reasons behind Petrobras' position to take that decision, but we firmly believe that there were no reasonable grounds for disqualifying Heigl from the process.

51:41 Okay. And is Petrobras obligated to find a lessor for this facility at some point by the Brazilian state?

51:49 Yes, they are. As part of the commitment that was made towards the antitrust authority, Petrobras has the obligation to lease the terminal for a minimum period of three years, and that lease should take place in the next few months.

52:05 Okay. And then one for Ian on the HILI. I'm just trying to understand the removal of the cap by SNH. What was the purpose of the cap in the first place? And was there any concession that needed to be made? I think you said it was an eight year. So it's just a continuation of the existing contract with this newer terms and increased over capacity.

52:28 That's right. So the original contract, if you recall, had an endpoint stated as the earlier of 500 BCF through the vessel or eight years. and as we've been producing a little over the annual amount each year that would have potentially brought the contract to an end a few months early. So what this has done is it's moved the contract to a firm fixed eight year duration and we've got about five and a half years left of that. But importantly, there's two things that come out of it. One is that we are allowed now to be paid for our overproduction We've made about $5 million of overproduction up to the end of 2019 and we will bill the amount for 2020 in January next year when that's calculated. So that's something that will run through the contract.

53:23 And then secondly, importantly, with that cap being lifted, it means there's no barrier to being able to come up with a deal that would allow us to put more volume through the hilly.

53:35 Okay, and that, I think you said is around $5 million of overproduction through the end of 2019, so does that revenue recognition all happen in 4Q20?

53:46 I think it will happen in 1Q, it could happen in 4Q20 if we've invoiced it by then. We can confirm that later.

53:54 Okay, thanks. That's all from me. Thank you. Your next question comes from the line of Randy Diviance from Jefferies. Please ask your question.

54:08 Howdy, gentlemen. How's it going? Hey, Randy. Hey. So looking at the liquidity events, I guess a few questions. What are the terms for the new $100 million credit facility against Tygo? And for the Frost refinancing, that's going to raise an additional maybe $40 million. And you say the margin loan. and additional 30 million. So is this your decision to push these refinancings until the first quarter and how likely is that margin loan to be upsized and completed in the next few months?

54:41 I'll be calling you to take those.

54:44 Yeah, sure. Hi, Randy. So the terms of that, sorry, the terms of the facility is LIBOR plus 500 BIPs. and it's a non-amortizing bullet facility that we have on the corporate level. When it comes to the margin loan, it's a question whether we would like to leverage the shares or not. As you know, we are repaying the margin loan now in the mid of December and we can obviously approach the same banks or a subset of those banks to renew the margin loan. As Tor said previously, not that there's any immediate plans to do so, but if you don't have leverage on certain shareholdings, you can at a later stage consider to also distribute shareholdings to shareholders.

55:35 Whether that is at the later stage, either GMOP or Hygo, it's something that we are considering. But such facility is in place today and should certainly be able to be put in place. When it comes to the $40 million net liquidity release from the potential We received two different term sheets, both of which just given the credit processes of such refinancing is more likely to occur early in the new year as opposed to now. But one of them we think is extremely attractive and we're pushing ahead in that process. But we also know that it takes two to tango on a Refinancing of a ship, and therefore we're guiding on a Q1 event on the thrust.

56:23 It could, of course, be pushed earlier, but then again, I think a lot of lenders find it easier to finance new initiatives early in a new year as opposed to late in an old year, if you want to think about it like that.

56:36 Got it. Okay. And then for that non-empathizing credit facility, the LIBOR plus 500 basis points, that's just one year term?

56:46 It's one plus one term. is what they've engaged with.

56:52 Got it. All right, and then if we can go back to the LNG shipping backlog, you know, increased by $123 million. Can you provide a little more details on those charters? Are they all fixed, all floating? And kind of what are the durations of them?

57:10 So the majority of the new backlog, in fact, I think all of the new backlog is fixed duration and the durations, I think the longest one is a couple of years. Most of them are around about a year and there's a couple that might be somewhere in between.

57:32 Got it. Good deal. Well, let's keep the train moving. Thanks so much. Thanks, Randy. Thank you. Your next question comes from the line of Craig Shear from Three Brothers. Please ask your question.

57:53 Just want to clarify, the Parenko updated agreement does not allow for reduced annual cash flow if volumes are lower, does it? And does the agreement eliminate potential to get upsized and extended terms that could support a favorable project refinancing?

58:14 There's no linkage to project financing that I'm aware of that would preclude that, and I... I can come back to you if we underproduce. I don't think we've really contemplated that with the way the vessel's going, but I don't believe... The way that the contract's structured, we're paid for availability and throughput. It's just that we've been putting more through, and so the contract's been restructured for that. But let me come back to you on that, Craig. Stuart will follow up with you on the detail. I'm sorry, I just don't know the answer.

58:49 Okay, and on the project finance question, what I meant was if you had upsized it and made it a 15-year agreement, obviously it would be a no-brainer to be able to get better financing terms on the project, whereas if it's a little more variable and flexible, even if you're going to make more EBITDA, it's harder to replace it.

59:10 We're focused right now on increasing the immediate throughput on Heli rather than thinking about extending the contract because the latent value that sits in that vessel, we want to do what we can to get more volume through that vessel and the outcome from that goes straight to our bottom line and that's our immediate focus. So we're not really considering extensions at this state in the game. Sorry, this is Karl.

59:39 Just to comment on your previous question, the revenue cannot come down on HILI under the revised schedule. So it's at E and Z that we're paid for the capacity and being there, and it cannot come down.

59:53 Thanks, Karl. Thanks, Karl. That's good to know. On Hygo, is there potential to renew the Norse Hydro Aluminum Project MOU after the Barcarina FID and a successful HiGo IPO, and could we see HiGo contract for FLNG itself as far as offtake in the next couple of years?

1:00:20 Okay, so with regards to Norsk Hydro, what I can say is that we continue on an active dialogue with them, and our decision is to take the project ahead and move on with a potential FID before the end of the year. are not connected entirely to the discussions with Norsk Hydro. So we might be in a position to move ahead with the project without their contracts. With regards to the potential FLNG supply to any Hygo project, I think this is, of course, one of the potential synergies that we believe that could be achieved. And we do contemplate it in some potential projects, especially in the north of Brazil. But this is something that is very premature and very preliminary as of today.

1:01:08 Great. And just to clarify there, I guess my thinking was if you FID Barcarena, you're the only game in town. There's just no way for these guys to convert, as they had promised the local state, to the more emission-friendly natural gas fuel without you. So I guess what I'm asking is if you do go ahead and FID in the next month or two, do you think that there's decent opportunity for Norse Hydro to return to the table in coming quarters?

1:01:44 I think what you should do is you should call Norse Hydro if they have any alternatives. I don't think enough has been said about the Hydro. If you see the location for our terminal, it's effectively outside the door of Norskeetra's plant. So I think I'm hopeful when this thing is settling down that it is possible to get that back in the fall. But of course, we don't take anything for granted.

1:02:11 Great, thank you. Nice, Craig. Thank you. The next question comes from the line of Ken Hoekstra from BPA. Please ask your question.

1:02:24 Hey, good morning, good afternoon. Ian, Karl, Eduardo, Tor, thanks for the detailed updates there before. Well, maybe Tor, just your view, you mentioned your kind of view on governance is primary, but yet you're on your fourth CFO here in two years and fourth CEO in five years. You know, I guess just going back to some of the questions before, what's the concern here just in lack of continuity given that much shuffling and to give visibility on the steady steady hand guiding, you know, continuing to guide the company.

1:02:59 I think when you're saying we are on our fourth CFO, that's not totally right because the CFO we had before Graham Robb Jones, he was with us for 20 years. So he played different roles. So I don't think that's the guy Callum took over from. So I don't think necessarily that's right. We have had two for 20 years effectively. I think he changed that a little bit. But But Ian has not been here in three years, three and a half. But of course turnover is never good. And there is no doubt that this is a kind of challenging place to work. There is hard work and there is an entrepreneurial company with a hard drive. And I can admittedly say that to have an actively involved chairman might be painful from time to time. and Ian laughing at me.

1:03:55 But I think that's what we were used to from the Frederiksen group, that we are actively as a board and it works. But the funny thing when you're saying all the alterations also, all the chief executive who was in the company, they normally came back several times, like Doug and like Gary and all the people. I take your point, but you're not correct in your facts. because we haven't changed CFO four times at least. But it's obviously a concern. It's less of a concern that the guy leaves after six months than the guy leaves after a couple of years because, of course, he was limited what he could set himself into. But we all liked Callum, and I think both Ian and I tried to convince him to stay, but kind of from personal reasons he said that he wanted a different life. Okay.

1:04:51 But, I mean, factually in that seat, it is numerically right, right? From Tienzo to Rob Johns to Callum to Carl. But, okay. So, but I get your point in terms of still at the company for a while. Now, just let me flip over, Ian, to your thoughts on the cost from the BP delay. You mentioned the $36 million. Can you maybe detail those costs if I've got that right? And is the shipyard fully operational now and what those costs are associated with?

1:05:22 So the shipyard is fully operational. It's quite amazing what they're doing in terms of their own, and it comes from the Singaporean government to start with. They have very strict rules around how they transport people. So let me give you an example. A lot of the workers live in dormitories and they sleep in the same area of the dormitory as their fellow workmates for a specific area of of the project so not only is it the specific area of the yard it's the bit of the ship that they're working on and they go from their dormitories through their canteen facility in a bus directly to their work area they stay with their workmates all day and then they come back and they can sort of rinse and repeat and the the idea behind that is if there is a COVID case they can isolate a unit very quickly and then deal with it. So we were down to less than 100 people during the four-month shutdown that we experienced in Singapore and they were really on care and maintenance activities. We're now up to 2,450 as of today working on the project which is higher than it was before we slowed down and back on track. In terms of the additional cost, the $36 million, a lot of that has gone into storage, passivation, and care of equipment that was ready to ship from vendors, plus additional time-related costs, as you might imagine.

1:06:51 You've got certain fixed costs that just continue, and they've gone out 11 months. So as a percentage of the overall budget, $36 million on $30 million is pretty good under the circumstances.

1:07:07 Great. Thank you. And then lastly, just... Maybe just on going a high go, the key risks for the FID at Barca Arena and Swap A. Eduardo, you mentioned kind of some of the things might be coming over the next few weeks. Is there a chance of delay or any other issues or of not getting the FIDs or anything else that could delay that process?

1:07:30 We are highly confident that the progress made in Barca Arena to date puts us in a very good position to take a final investment decision in the next couple of months. When it comes to SWAP, we believe that there are still some regulatory approvals that are expected in the coming weeks and could be a main driver for that decision.

1:07:53 Great. Thanks for the insight, guys. Appreciate the time.

1:07:56 Cheers, Ken.

1:07:57 Thank you. Thank you. The next question comes from the line of Gregory Lewis from BKIG. Please ask your question.

1:08:11 Thank you and good afternoon and thanks for squeezing me in here. I guess I just had a question. In kind of going through the prepared remarks, it sounds like, and I'm going to look for a little bit of color around what's been talked about over the last few quarters in terms of strategic reviews and kind of repositioning the company. Is it safe to assume that in realizing that the capital markets can be fickle and things are always in flux in the capital markets but it's the right way to think about the event path here for Golar and trying to crystallize value is it all contingent on Hygo the IPO before we think about other things like the MLP and the conventional fleet just kind of curious any color around you could give us around that well let me kind of

1:09:10 If I think about our sort of enabling strategic plan, it hasn't really changed much over the last year. And as Tor mentioned, we see the sum of the parts of the business equating more to the value recognized in the market. But to achieve that vision of creating separate investable businesses, there's a few things that we're focused on. Let me list them. There's seven or eight of them. First of all, keeping operations running safely to the satisfaction of the customers. Secondly, working hard to maximise the through-year shipping income. So that's a change of pushing quarter by quarter. We're looking at it through the course of the year. Thirdly, delivering LNG Croatia safely on time and on budget before the end of the year to deliver that $47 million in cash and take on the 10-year operations and maintenance contract. Number four, maximise throughput on FLNG Hilly whilst on contract Perenco. So maximise that volume we can get through and therefore the revenue. Fifth, we've talked about delivering Guinea safely on time and on budget to commence our 20-year contract with BP and our share of that EBITDA is around $150 million per year.

1:10:23 6. Developing the FLNG portfolio to create that realistic and investable set of project opportunities considering both Mark 1 conversion and Mark 3 new builds. We've talked a little bit about that already but we think that our FLNG portfolio backed by such high quality customers can create interesting investment opportunities for potential partners going forward. Seventh, and it's been commented on before, the future of Hygo is going to be determined by the board of Hygo and market conditions. And eighth, we'll dabble in new technology to make sure that we're right there on the fringes of things that are happening in the overall market. These are the things that I'm focusing on on a day-to-day basis, and they feed into considerations that the board may have, and Tor, I don't know if you want to add anything.

1:11:13 I think that was a good summer for the day-to-day. Obviously, the world changes every day. I think what has been a problem for us is, of course, we have tried to spin off the shipping activities several times. That has been difficult because that's not really the business we love to be in long-term. But I think by reducing the risk and by covering it up with charter, we have at least increased the downside risk in that business. When it comes to why we're preferring Hygo, no, it's because we are ready to go. So we can go effectively any day, and I think you will see us going pretty soon. And that's why we're giving priority to that first. Then when it comes to, if you want to do anything as described in some of the, looking for a partner to build the FLNG business going forward, then you really want to get Hilly Train 3 up and running, you want to do some more stuff, You want to build a bigger portfolio before you bring in a partner.

1:12:16 But I think we are pragmatic. If we can keep the upstream and downstream model together in one way or the other, I think it's great because then you have the hedge when gas prices are low and high. The midstream is not our business going forward and it shouldn't be, but there are no kind of Structuring talks to other people as well about doing something. So we'll see. But you're right. Hygo is priority one because that's on the block right now.

1:12:49 Okay, great. Thanks, everybody.

1:12:52 Thanks. And with that, I'd like to draw the call to close due to time constraints. Thank you for your participation and interest in GOLA. Please stay safe. We look forward to sharing our progress with you next quarter. With that, I'll hand back to the operator. Thank you everyone. That does conclude our conference for today.

Follow Golar LNG Limited into a list and get an email when it puts out news.

Latest news releases

Companies on this call

Speakers

Ian Ross

CEO, Golar LNG

Karl Fredrik Staubo

CFO, Golar LNG

Eduardo Maranhao

CFO, Hygo Energy Transition

Thor-Olaf Proim

Chairman, Golar LNG & Hygo Energy Transition

Dan Nolan

Analyst

Mike Weber

Analyst

Sean Morgan

Analyst, Evercore

Randy Diviance

Analyst, Jefferies

Craig Shear

Analyst, Three Brothers

Ken Hoekstra

Analyst, BPA

Gregory Lewis

Analyst, BKIG

More from Golar LNG Limited