Ahluwalia Contracts (India) (NSE:AHLUCONT) Q2 2026 Earnings Call

Ahluwalia Contracts (India) (NSE:AHLUCONT) Q2 2026 earnings call, held 2026-11-17. Watch the replay and read the transcript on 6ix.

Mon, November 16, 2026 at 11:56 PMendedReplay
Ahluwalia Contracts (India) (NSE:AHLUCONT) Q2 2026 Earnings Call
Company
Ahluwalia Contracts (India) Limited (NSE:AHLUCONT)
Period
Q2 2026 earnings call
Date
Mon, Nov 16, 2026, 11:56 PM ET
Replay
Watch the replay on this page · 1 h 4 min

On 6ix: 6ix.com/event/ahluwalia-contracts-india-limited-ahlucont-q2-2026-earnings-call

Replay

Transcript

Automated transcript · Written by software from the replay's audio. It can mishear names and figures; the replay is the record.

0:00 Ladies and gentlemen, good day, and welcome to Ahluwalia Contracts (India Limited Q2 H1 FY 'twenty seven Earnings Conference Call. As a reminder, all participant lines will be in a listen only mode, and there will be an opportunity for you to ask questions after the presentation concludes.

0:29 Please note that this conference is being recorded. I now hand the conference over to Ms. Deepashree Joshi from Ambit Capital. Thank you, and over to you, ma'am. Good afternoon, everyone. On behalf of Ambit Capital, I thank the management of Ahluwalia Contracts (India) Limited for the opportunity to host their two q FY twenty seven earnings conference call. To discuss the results, I am pleased to welcome mister Shubhed Upal, Deputy Managing Director Mr. Ahluwalia,

1:01 Director and Mr. Sadhvi Singh, Chief Financial Officer. Now I invite the management to take us through the key highlights of the quarter, post which we open up for Q and A. Thank you and over to you, sir. Thank you. Good afternoon, everybody. The Ahluwalia Contracts (India Limited) has announced its financial results for Q2 FY 'twenty seven. During Q2 FY 'twenty seven, the company has achieved a turnover of INR 1,463.67 crore and a PAT of INR 55.86 crores in comparison to a turnover of INR 1,125.81 crores and a PAT of INR 11.48 crores during Q1 FY 'twenty seven and a turnover of INR 1,177.30 crores and a PAT of INR 79.05 crores during Q2 FY 'twenty six.

1:54 The company has registered a growth of 30.01% in turnover and a growth of 389.2% in PAT during Q2 FY 'twenty seven in comparison to Q1 FY 'twenty seven, whereas a growth of 24.32% in turnover and a degrowth of 29.33% in PAT during Q2 FY 'twenty seven in comparison to Q2 FY 'twenty six. EPS of the company for Q2 FY 'twenty seven is INR 8.34 as compared to an EPS of INR 1.70 in Q1 FY 'twenty seven and INR 11.80 in Q2 FY 'twenty six. During Q2 FY 'twenty seven, the company's EBITDA margin is 7.58% as compared to an EBITDA margin of 4.29% in Q1 FY 'twenty seven and ten point nine two percent in Q2 FY 'twenty six.

2:55 And the PAT margin is 3.78% as compared to a PAT margin of 1.0% in Q1 FY 'twenty seven and six point six three percent in Q2 FY 'twenty six. During H1 FY 'twenty seven, the company has achieved a turnover of 2,589.48 crores and a PAT of INR 67.28 crores in comparison to a turnover of INR 2,182.18 crores and a PAT of INR 130.16 crores in H1 FY 'twenty six.

3:30 EPS of the company for H1 FY 'twenty seven is INR 10.04 as compared to INR 19.43 in H1 FY 'twenty six. During H1 FY or FY 'twenty seven, the company's EBITDA margin is 6.15% as compared to 9.85% and a PAT margin of 2.57 as compared to 5.88% in the corresponding period of the last financial year. Net order book of the company as on 09/30/2026 is INR 19,627.92 crores to be executed over the next three to three point five years. Total order inflow during FY 'twenty seven till 09/30/2026 is INR 558.07 crores. At present, we are L1 in-one project amounting to INR 379.00 crores.

4:27 We are ready to take questions now. Thank you very much. We will now begin the question and answer session. If you wish to remove yourself from the question queue, you may press star and two. Participants are requested to use handsets while asking a question. Ladies and gentlemen, let's wait for a moment while the question queue attendant. I repeat, anyone who wishes to ask a question may press star and one on their touch tone telephone. The first question is from the line of Parviz Kasi from Nuvama Group. Please proceed.

5:20 Hi. Good afternoon, and thanks for taking my question. Good afternoon, Parvez. Hi. So our execution has been pretty decent in H1, but there obviously have been hits on the EBITDA margin front. So one, if you could give your views on this performance? And second, how do we see the rest of FY 'twenty seven and FY 'twenty eight panning out both in terms of revenues and margins?

5:51 That's the first question. So I'll answer that. Or you have any other questions? It's Ahluwalia, who can answer that. Sure. Yes. Please go ahead, sir. So I had enumerated in the last phone call after Q1 the reasons for the slowdown. So Q2, as you can see, the numbers are significantly better from Q1 due to the concentration of our projects in North India, primarily in NCR. Q1 numbers have been hit because some of our bigger projects, they started off slowly for reasons beyond our control, as also due to the labor costs having been revised upward significantly by the various governments in NCR.

6:46 So the slow moving projects have since started yielding revenue. So that's why there is a significant increase, as I told you, in Q2. So hence, because of Q1 only, the H1 numbers of this financial year sort of pale in comparison to the last financial year. But I think the worst is behind us. Going forward,

7:14 we expect to maintain similar margins in this financial year, wherein we are also factoring in the impact of NGT shutdowns. As you know, construction in NCR is shut at the moment on account of draft guidelines. And it is expected at least one to one point five months is expected to be lost. The silver lining for us is that our largest project in NCR is in Delhi. That is exempt from the graph guidelines, which is the Sensi Vista project. Their work is going on full speed. But still, there is going to be an impact in the turnover in Q3.

8:01 We're factoring all that in, and our guidance for the rest of the year is that we're going to our EBITDA margins are going to be similar to what we've achieved in this quarter. Yes, sir. And in terms of revenue growth for FY 'twenty seven and FY 'twenty eight, how do we see that?

8:24 So a 15% guidance was given last time by me. I'm sticking to that as far as the revenue is concerned. And it will be in FY 'twenty eight, it will be between 15% to 20%. Sure. The second question is, last year also, our Q2 revenues were higher than Q1 and then we see we saw a decline in Q3 again because of these draft guidelines. Traditionally, I mean, for most EPC companies, Q1 used to be better than we used to see a slowdown in Q2, and then Q3 used to be better than Q2. Now with these set of challenges that we see in NCR every year, do you think our quarterly numbers have now kind of got inverted that maybe Q2 is going to be better than Q3 every year?

9:20 Yes. Actually, traditionally, Q3 and Q4 in the glory days always used to the run rate used to be significantly higher. But Q3 now, if you see last year, there was a 10% dip in our turnover, and that impacted our margins also. So this year also this year also, we are expecting a similar dip, but some of it may be made up by other Central Vista project, where we expect to log a turnover of close to INR 150 crores in this quarter to Q3. So but yes, Q2 and Q4 going forward, if the pollution levels continue, I think Q2, Q4 are going to be the best quarters going forward in a calendar year.

10:12 Last question, I mean, any guidance for the order intake front would be helpful. You said further intakes order intake is what you're asking, sorry? Yes. So yes, I've given a guidance of about INR 4,000 crores. We have close to about post September also, we won an order, which is our existing client, Times of India, Bennett University, about INR $3.50 odd crores. So we are close to about INR 1,000 crores till date. And my guidance last time was INR 4,000 crores. We are sticking to that.

10:49 Sure, sir. Thanks and all the best. Thank you. Thank you. The next question is from the line of Shivan Shah from Dollar Capital. Please proceed. Sir,

11:06 just to get a clarity, so we are saying that third and fourth quarter would be better than the Q2? What we are saying is that Q3, as far as top line is concerned, there is likely to be a dip of up to 10% on account of graph. Q4, of course, will be the best quarter, but our margins would be similar to what we have achieved in Q2.

11:41 Okay. So 10% dip, that is on a Y o Y basis and not on Q o Q? No, actually, it's 10% dip on Q on so we are expecting a turnover of about 1,300 crores in Q3. If you see in Q3 of last financial year, it was about INR 1,100 crores. So from that, the turnover will grow up. Yes.

12:11 Yes. So that was and then the Q4 definitely should be better versus the third quarter. Yes. So so in so Yes. In that case, then we should be then doing the even higher than the 15% that we are looking at because INR 2,600 crore we have already done. So maybe close to 18% plus kind of a number should be there. We could achieve that, but my guidance is for 15%. It will be definitely 15% plus.

12:55 Okay. Okay. Got it. And second, sir, so this quarter, what we have achieved 7.6%, that number will be there for the second half and for FY 2028, then how we one can look at even the we are looking at 15%, 20% kind of a growth? Yes. As I said, we are looking at a 15% to 20% top line growth. And maybe there will be, as I said last time, there are a number of headwinds, a number of unpredictable factors which come into play. But yes, we are looking to grow

13:31 our EBITDA margins by at least one percentage point in FY 'twenty eight. Okay. So maybe 8.5% is doable? Yes, 8.5% to 9% is doable. Okay. Okay. Got it. Got it. But is there any positivity that you are seeing, but that this 8.5%, 9%, what could be the possibility that we can reach to a 10% kind of a close to a double digit? Or it is very, very difficult to say right now? It's difficult to say right now. Okay. Okay. Got it.

14:17 Second, sir, on on on the central, quarter, you said $1.50 odd crore kind of our revenue that we are looking at. So for full year, last time we were saying of INR 700 crores and next year INR 1,000 odd crore. So that number will remain intact? Yes. In October, we achieved a turnover about INR 43 crores in Central Vista, which is likely to go up to about INR 60 crores this month and another INR 60 crores or 70 crores next month. So and going forward, it would be about INR 200 crores plus in the last quarter for that particular project.

15:05 Okay. Okay. Got it. And for Mumbai, Jallari Park, what kind of revenue we look at for this year and next year? Vikas, will you answer that? Yes. I'll answer that. Yeah. Sharma, come again, please, regarding what we are asking. For Mumbai, Jensen jewelry, in one is how much revenue we have done? And in the second half, how much we are looking at? And for next year, how much we can look at?

15:39 The jewelry part theoretically has not started, Shava. Though has been a client, but there has sort of things. Sir, can you please come closer to the device? What I'm saying, someone, is that we we have still not got the notice to proceed from the client. The client is still sorting out some internal issues regarding their permissions and some matters. So we are not expecting any turnover this quarter also.

16:26 Okay. So in fourth quarter, can we can we look at some revenue or still January January January, I don't I don't want to put in a number. Even after we get notice to proceed, there would be an active... No. No. Actual work to start is going to take about three months because there is still a lot of land that has to be cleaned up on the top, which the client has to do.

16:56 So there... If you if you know that in Mumbai, there was a recent ban on some earthwork and dumping and all that across. So that has still been sorted out. Okay. Got it. And sir, what about the CSTM registration? So there, previously, we were looking at close to for more than INR 500 crore for this year and 700 crore in next year. So So CST has now picked up, Shubhrant. So CST now is picked up. Last month, we did about 80 crore rupees from 50.

17:37 Actually, just to let everybody, you know, the the the gathering here on call just to let them know that CSPP billing is actually a little different because railway processes work differently. So where our actual work done is close to 100 or 110. But if conversion into billing is lower even in other, like, normal UTC, CPW contract, their payment systems are a little different. So... But, yes, last... But last month, we have we have done about an 80 crore turnover there, which is registered or built. Okay. So so for full year, this year at 2728, how we look at revenue in terms of for us as as a p and l booking?

18:33 So, Shrivan, we are going to be doing a billing of about INR 150 crores in Q3 as far as CSMT is concerned, and we're going to be doing a billing of close to about INR 200 crores in Q4. Okay. Okay. Got it. Then as Vikashi said, the number the progress there has picked up. All the designs most of the designs have been approved now. And the numbers that we projected in the last call, we are on track to achieve them. Got it. Lastly, sir, balance sheet item mobilization advance, retention money and unbilled revenue?

19:21 Mobilization advance is 939 crore, and retention money is 437 crore. $3.87, sir. And unbilled revenue, 925 crore. Sir, retention, you said, three eighty seven? Retention retention is four thirty seven. Four thirty seven. Okay. Got it. And mobilization, how much is the interest bearing out of nine thirty nine? 32%. 32? 32. Okay. Got it. And the CapEx for full year now how we can look at given that the first half we have already done $1.42 crore?

20:11 Yes. But top 142 crore and this quarter, 66 crores. And we are expecting around... Maybe around 225 crores would be there for the whole year. Okay. Okay. Got it. And all the best, sir. Thank you. Thank you. Thank you. The next question is from the line of from Counter Cyclical Investments. Please proceed. Sir, thank you for the opportunity. So, actually, I just had a suggestion. So, you know, our stock is trading at a three year low almost, and, you know, we have a strong treasury balance of close to a thousand crores. So, you know, why don't we consider a share buyback? This would be a great time to do that. And it is a tax efficient way for the company now to reward shareholders and also perpetually increases EPS.

21:06 Why don't we please consider a share buyback? Okay. That's a suggestion that we'll take into account. But the rationale behind not really focusing on this is that going forward, supply chain being impacted and time lines getting constricted. Our focus is how to increase efficiencies. And we want a war chest, which we can which we have ready access to, to ensure that we better we have better control on the supply chain so that our time lines we can squeeze and increase our margins. That is our single-minded goal to improve our top line as well as bottom line.

21:55 I understand, sir, but just please take this into consideration whenever possible. Thank you. Thank you so much. Hello? Yes. Hello? Yes. No, no. We'll take that into consideration. Thank you. Thank you for the question. Yes, thank you for the suggestion. Sorry. Yes. Thank you. The next question is from the line of Keshav Garg from Counter Cyclical PMS. Please proceed. Sir, congratulations for good recovery quarter on quarter. Sir... But I'm comparing our number with our smaller listed peer, which is. So so there are... Apart from a good revenue growth, sir, their EBITDA has also doubled y on y. And, sir, now our EBITDA margins have converged with their margin or other their margins have converged with our margins, whereas before we had a superior margin profile.

22:58 So so basically, exactly... I mean, if some factors are hitting, then they would be the same for all the players of the industry. So is there any specific hit that we are getting due to any factor and whereas... Which is not applying to them? So first of all, thank you for your words, your compliment. Look, B. L. Kashyap is a very respected peer. And at one point in time, both companies were very similar. So DNA remains similar, and their way of executing is very similar to us. But there today, they have a much smaller base.

23:43 We having a larger base, obviously, as you would know, the costs are higher. In this quarter, if you do a deep dive on our numbers, we've registered a higher EBITDA in spite of our staff costs going by up by an absolute number of about INR 12.5 crores, right? Our staff numbers are more. Peer outlays have also gone up. In September, I think close to 3 crores of more we have paid from the corresponding quarter or the preceding quarter also as far as due to change in laws is concerned, right? Minimum wage exempt has gone up from 15,000 to 25,000. Now virtually 85% of our labor force and staff are coming under the So all these statutory issues, plus the extra costs on account of our scale, so to say, our IDCs, I think if we were to do a comparison, if you were to do a deep dive of IDC costs between BLK and us, ours would be higher. But that doesn't necessarily mean that we are more inefficient than him. We are just factoring in, we are building up costs, we are building up capacities to because we are at an inflection point.

24:58 We are close we would be by the end of this year close to about INR 5,500 crores. So we're building up to make that quantum jump. That is why to do a fair comparison, while I could sort of say the same thing if we compare our EBITDA to Larsen and Tubro. Now Larsen and Tubro is at 5.5%. We are at 7.5%. Again, the same logic applies that applies whether we me and BLK, I'm on the lower end of the totem pole as far as L and T is concerned. Understood, sir. So now also in our annual report, I could see that we have an investment property of around 85 crores, 90 crores and on which we made a loss of INR 10 crores in FY 'twenty six and INR 5.3 crore in FY 'twenty five. So why don't we just monetize this investment property and use the proceeds in our business?

25:56 Notion loss. INR 34 crore. No. Sir, during the 03/31/2026, that was INR 34 crores. I think so. There is no INR 88 crores, 89 crores. And until we are in the office, I guess INR 34 crores. I think some... Sir, actually, what I'm referring to is the investment property worth INR 84 crores as on 03/31/2026. On this investment property, we earned a rental income of INR 6.25 crore. So explain, this is on a cost? This is a quota project that we are basically have built up commercial mark here. And we are earning revenue from there and this is around $11.80 crore lakh this quarter also. So this year, we are expecting the revenue of around might be there with seven and a half code this year from the project.

27:19 Understood. Hope you got your answer? Yes, sir. I got it, sir. Now lastly, I wanted to understand, you sir, I think you had alluded to the fact that our contracts where the the pass through or the price hike is dependent upon the WPI, which in the first quarter had hardly moved, whereas the cost on the ground had actually gone up far more than the WPI. So there is a lag effect, sir, but now I believe that WPI is going up quite significantly. So can we expect progressively better, at least better compensation from the clients and consequently better margins on a quarter on quarter basis? Yes, that has played its part in Q2 also, as I said during the last investor call.

28:07 And what generally happens is that the lag is there in the beginning. And during by the end of the project cycle, it's sort of the two graphs match. So it started picking up. And we have two kinds of built in escalation in our floor in our contracts. In government contracts, it's based on WTI, as you just said. In private contracts, it's there are basic rates of these volatile materials, be it cement, RMC or steel, right? And post the last major increase on account of labor, we have even we have reached out to all our clients. Some clients have already agreed to labor escalation as per the minimum wage index and talks are going on with the others also.

29:00 This was the new order that we are bidding for, are we providing for these things? Because state government, before every election, they are... They compulsively increase the the the minimum wages regardless of the economic logic. So so that being the case, these freebies, etcetera, are not going to stop. So have we made some changes in the mean, in the kind of agreements we are signing with us? Yes, have. A, as I mentioned last time around, we in order to consolidate, that is why I had revised in the last phone call my order inflow to about INR 4,000 crores because we wanted to pick and choose going forward, our order book being healthy enough.

29:48 And we are now whenever we are bidding, we are making sure we don't bid without the escalation clause, be it factoring this escalation, be it labor escalation or material escalation. Great, sir. Thank you very much and best of luck. Thank you. Thank you. The next question is from the line of Mahesh Patel from ICICI Securities. Yes. Hi, sir. Thanks for the opportunity. So my first question is what we mentioned in the last call, right, that labor cost had gone up in Haryana and UP for... By about 35%, 40%, right? So just wanted to state a subject, although you did mention that some of the clients have agreed for absorption.

30:36 So wherever they have agreed, is it full absorption of this cost? And approves how much percentage of our order book can we say that this escalation absorption has been agreed upon? And secondly, sir, the material cost, this quarter, I think, if I consider Y o Y, the material cost has gone up significantly compared to the labor cost. So just some color on that, what is happening in this quarter? So first escalation, as I said, almost if I was to put a number in the proper context to this, almost 50% of our clients where the labor escalation clause did not exist have agreed for this going forward, right, from today escalation as per the minimum wage index.

31:34 As regards our higher yes, our material costs are higher by about four to five percentage points. That is primarily due to the mix of the projects that we are executing at the moment. Some are bigger projects like Centrum Vista and CSMT, as Mr. Vikas Ahluwalia mentioned in an answer to an earlier question that these are EPC contracts, these are not item rate contracts. Sometimes the materials when they come in, the way the billing is done, it's just about the billing covers the cost of the materials coming in, right? In an item rate contract, the item is billed fully. By that, I mean, it's not only the material cost, it's also the fixed cost and it's also the profit.

32:25 In a life cycle, kind of balances out as a project, I'm saying, Central Vista or PSMT. As the structure would be nearing completion, our items, structural items would be fully built, right? So then when the full build will be there on the value of an executed item, the material percentage would automatically come down. So what you would see going forward in the next six, eight, nine months, some of these larger projects, the material percentage would come down as a percentage of total revenue. Okay, sir. Got it. And sir, secondly... Yes, absolutely clear. My second question is regarding our order book, right? So we have around half of the order book in NCR region.

33:13 So in terms of just to understand from Q1 to Q2, what has led to this margin improvement, Can we also get a breakup a rough breakup of in terms of revenue breakup in NCR versus the non NCR revenue? Around breakup percentage range would be fine from Q1 to Q2, what has changed? Around the is good. The INR would be part You that said INR $5.25 crores. INR $5.25 Yes. These are approximate figures you can mail to us, but approximately we can tell you, out of the total revenue was INR $14.63 crores, about INR $5.20 crores would be NCR. And sir, what would be the roughly the percentage in Q1?

34:07 Q1, I think our total turnover was about INR $11.25 crores. And 50 crores. Would be about INR $3.50 crores. But these are approximate figures. Don't have that number in front of our guidance. Got it, sir. Okay. And sir, you have highlighted that there would be around, I think, that Q3, there will be one to one point five months of band you are expecting, right, in NCR and still you are expecting INR 1,300 crores of revenue. So which are the key projects that you see this high moment coming from?

34:57 As I said, if we were to take a similar run rate, I'm taking a 10% degrowth in our top line. But Central Vista is exempt, right? So we are expecting a turnover of about INR 150 crores from this one project alone. Then we have a hospital project, a MAT in Gurgaon, which is also exempt. So we are expecting about INR 50 crores from this particular project. And we are hoping that at least maybe half of December in Gurgaon, at least the blanket ban is in Delhi. But as far as NCR is concerned, the rest of NCR is concerned, as things stand today, the blanket ban is till November 20.

35:50 Post that, the position of AQI will decide when the work will start. So that's why and we are also basing our guidance on last corresponding quarter of the last financial year, where there was a bit of a degrowth there was a degrowth of about 10 percentage point, and we stuck to that. Okay, Got it. Thank you. Thank you and all the best. Thank you. Thank you. The next question is from the line of from JM Financial. Please go ahead. So then you mentioned that the blended money is only in Delhi. So from 2011, even that can change to 85 megahertz?

36:37 I don't think the bank because Delhi government, it's a little confusing. Delhi government had come out with a blanket bank till end of January, right? Then the central government had come out and given a statement that in NCR, the projects will remain closed from November 5 to November 20. So as things stand today, in the rest of NCR other than Delhi, till today, what we have in writing from the government is the projects are closed till November 20. As I said, we are expecting if AQI does not improve, we are expecting this will go up or this will be extended. But hospital project is exempt. Work is going on full speed as these two projects are.

37:27 But in Gurgaon, all projects are exempted or only central and Max Hospital? No. No. All projects are closed as things stand today.. Since twentieth since November 20, all projects are closed other than the Max Hospital. Okay. Oh, sir. Secondly, on on margins. So you mentioned that q two was 77.6%, and we expect a similar number in the second half as well. And next year, you mentioned that we are looking for eight and a half to 9%. So earlier, are targeting a higher number. So apart from this issuing bank for the second half, for next year, what is the key reason for we not going closer to double digit or even nine, nine and a half percent?

38:16 Are there any projects where we see that the margins which you are earlier factoring are not expected to come or some other reason? No, we are just conservative in our guidance. And as I said, Q3, which traditionally has always been a higher run rate quarter, now we expect that every year, it's going to be impacted. So that and then as I said, there are lots of headwinds, lots of unpredictable we've seen over the last two years, one thing or the other crops up every quarter, which tends to impact. That's why I think it would be foolhardy to talk about double digit margins.

39:07 But I that's why I'm giving a guidance of 8.5% to 9%, which should be done considering our strong order book. And we've also factored in increased costs, which we incurred now in the last two quarters because we are planning to ramp up our top line. So what I'm trying to say is the inefficiencies on account of factoring in for growth, those would be reduced in the next financial year. Okay. But there is no project specific issue as such? No. Sir, on employee costs, so we saw a sharp increase in Q2, so INR 133 crores. So do we expect it to come down in second half? Was it because of some bonus and salary hikes?

40:00 No, it won't come down, but yes, it's majorly on account of increments, which we have announced. It's not going to come down, but as a percentage, as our turnover goes up, it will come down. This is what I was alluding to when I was talking about preparing for the next phase of growth. Okay. Got it. Sir, on other income, we have seen a sizable number in the first half. So we expect it to further improve given our improved cash balance. That would be similar number around approximate. Okay. Is possibility there that project may get canceled or we don't see that as a possibility?

40:53 No. No. That's not a possibility. And is it a fixed price contract or a variable price? Vikash, will you answer that?. I I... It's. Vikram, are you there? Wait. Can you check your figures? Yeah. I know. Vikash, sir, can you please answer? We'll we'll... There is an escalation clause in there. Okay. So despite the significant delay that we have seen post the bidding, post bidding the order, we don't see any impact on margin given the escalation?

41:42 Yes. Okay. Okay. Oh, thank you, sir. Those are my questions. Thank you. The next question is from the line of from Tunga Investments. Please proceed. You. A few things. CapEx, which we are doing, may I know which are the areas where we are actually adding CapEx? And my second question is that I think there will be UP elections that will be that are scheduled maybe in Q4 or maybe in Q1 of next year. So is our guidance taking into account any disruptions whatsoever of the UP elections?

42:28 That's my second question. And the third question is that what is the mix of fixed price projects and variable projects as in general for us? And what is the mix of item rate projects in terms of the unexecuted book? And finally, the unexecuted book, how long do you think what is the minimum and the maximum? I think Sorry? No, no, I think there is some background noise from somewhere. You please go ahead. We heard your question. The last one, yes, please go ahead. The last one is that the total unexecuted order book, what is the time line minimum and maximum during which this would be executed? It is four Okay.

43:26 So that is all. There are four questions here and all. Anything Yes. No, no, that's Okay. First of all, CapEx. So the CapEx is primarily on equipment such as cranes, matching plants and loader and shuttering materials, right, which is basically now specialized shuttering materials, aluminum shuttering is required for high rise buildings or system shuttering is required for large table farms are required for commercial buildings. So the CapEx is on that. To further clarify this, when at the beginning of this year, we said the CapEx would be in excess of INR 300 crores.

44:13 Last quarter, we pruned it down to about INR $2.20 odd crores. So we are sticking to that number. As far as UP elections is concerned, we have one major project outside of NCR in UP. Noida is technically also in UP, but we consider that as a part of MCR. We don't expect any major disruptions. As far as Varanasi is concerned, though our stipulated date of completion is June 27, but the client at the behest of the central government is looking to complete it, get it completed earlier because they want to inaugurate it before the elections. In all probabilities, we will complete it before February or by January end. So no disruption there also.

45:04 As far as fixed price and what is variable is concerned, Sadhguru. Fixed price 9.19%, fixed price contracts are there. The EPC is around 46%. Coming to time lines, the unexecuted order book is about INR 20,000 crores, which, as I mentioned earlier, is to be executed about three to three point five years. The earlier, like, say, if we look at the Central Vista project, the time line is about two years, right? We can say about six months have elapsed. So another eighteen months to twenty months, we'll be completing this job. So that's the earliest earlier bit.

45:55 Have I answered all your questions? Yes. Yes. Just one question regarding the UP election. See, while the project is one, but I'm just talking from the resources point of view, do you see that there will be disruptions in terms of the resources ending up traveling back and forth to this? That something... Can you just repeat that question, please? Sorry. No. For the UP election, there will be resources of people who are stopped in the projects may also have to travel. So one is the projects getting completed, but do you see any disruptions in people traveling? Actually, most of our workforce comes from Bihar, Bengal, Yarkhand.

46:40 There is very little workforce which comes from UP. I believe you're talking about that, that whether some what we experienced for Bihar and Bengal the last financial year. Yes, no, we don't expect a major disruption because UP does not contribute much as far as our workforce. Got it. And one question structurally is that our depreciation keeps going up and our margins are also on the operating margins are also remaining stagnant or I think you mentioned that there is little room for that to go up. So therefore, usually companies do more CapEx and depreciation so that I mean, not more CapEx so that the business gets better margin.

47:30 But do you think it is a structurally, this is where we are headed, we need to do a lot of CapEx to really push ourselves in the bigger league and therefore but the margins also would be in the similar range. How do you think about not one year, two year, but over a much longer period? So our thinking is slightly counterintuitive on this. While we did plan and we did a large CapEx last financial year and planned similar numbers this year. But we what our gut is telling us that this business is cyclical business. If and we've gone through a downturn late two thousand around 2008, two thousand and nine, twenty ten.

48:18 So and considering that whatever disruptions are happening in the supply chain on an account of what is happening in The West or in The Middle East, we are being slightly conservative. We feel that in case there is a slowdown, which is not impending, say, four, five years down the line, if there's a slowdown, there would be a lot of PMI costs or other costs that we would incur if there is a slowdown. So we've sort of counterintuitively decided that we'll reduce our CapEx. And that sort of fits in because our order book is at an all time high. To feed this order book, I think we have the necessary equipment and the shuttering materials.

49:06 That's why we are waiting and watching. Got it. Got it. This is very helpful. Thank you. I'll come back in queue. Thank you. Thank you. The next question is from the line of Nirmam from Unique PMS. Please proceed. Yes. Thank you, sir, for the opportunity. I have a slightly broader question. As you mentioned, some of the other challenges kept popping up in the past two years. So how do we navigate the supply chain challenges or the skilled labor issues? And this is from a medium to long term perspective. What should change from the present circumstances, you know, to earn double digit margins on a sustainable basis? So let me start with the last point first.

49:57 To get back to the days of double digit margins, the entire has to up its efficiency. Keeping that in mind, the constituents of the ecosystem, which is the developer, clients, contractors, designers, everybody has realized that we are all badly hit on account of skill shortage, both number in terms of numbers and actual skills. So everybody started working on standardization. And to do that, for that to actually mature into actual work on the ground, standardized work on the ground, any newer trend, it takes about three, four, five years. But work has started, right? As it happens in the West, a lot of things get made off-site in factories, and they are assembled.

50:52 One aspect of that which we see is the use of pre engineered buildings or prefabricated building, say, if we take into account the Central Vista project. It's a INR 3,000 crore project. The time line is about two years. It's a 33.5 lakh, 3,300,000 or 3,400,000 square feet building. Nowhere in the world such a building of client aspires to complete in two years. In India, it's being thought of, and we are actually more or less on track there. So these are this is on account of things being or the structure being fabricated outside and getting to site and like a Lego site being erected there. So these double digit margins can be achieved, will be achieved once more standardization is there. This will take, to my mind, at least two to three years to happen, one. Second is training.

51:51 As we know, the skill levels have gone down, numbers have gone down. We are in touch with our various industry bodies are in touch with government, the skills ministry, how to use the vocational institutes that the government has, wherein the labor can be trained. The true challenge here is that any time that a major change or paradigm shift has to be there, it costs money, where the government needs to step in. Government is, I think, now alive to the challenge. Again, the action and its results will take at least a year to two years. But this skill shortage will have to be sort of made up, primarily driven by the government. And we are all sort of pushing the government towards that. And we are hopeful things action on the ground will be visible, as I said, in the next year or two years.

52:45 What else was did you ask? You repeat your question? On the supply chain challenges, so, you know, something or other that keeps on popping up. So how do you then see... Because these would be... You know, you couldn't predict these challenges. Then how do I agree you as a with you. It calls for better planning. Our planning resources, we've upped our planning resources. We've upped the IT bandwidth that we have or expenditure that we have. We factored in based on our experience over the last two years, more so over the last one year, where supply chain has been very, very badly affected, primarily on account of the war in the Middle East.

53:30 So we now we plan better, we factor in the time lines that are required for getting a particular material to site. Say, for instance, if we could get reinforcement steel or structural steel or cement in about two to three weeks on-site from the time it was indented. We now factor in time lines of about five to six weeks, in some cases, even eight weeks, especially for electromechanical materials like chillers and panels and transformers and so on and so forth. So our experience is what is coming into play to help us plan better. Got it, sir. Thank you. Very helpful. So my next question is just, so North Region is a major part of the unexecuted order book. Are we looking to increase business in other regions going forward now given all these NBT challenges and other issues?

54:24 Even the skilled labor issue you mentioned was largely in the Northern Region. So do you plan to Yes, move into other yes, it's already happening. If you were to see our order book, we are in, I think, memory serves me right, in 19 states at the moment. From being a purely North centric company, we now have a significant presence in Mumbai. I think our total... 24%. Yes, 24 of our order book comes from there. East is 15%.

54:55 And even in East, for that matter, when we saw we've seen a slowdown in BR and Bengal, we further moved on to Northeast, a significant amount of contribution comes from Assam as far as our total order book is concerned. South is something that we are growing our business. As things stand today, we have an order book of about INR 2,000 crores coming in only from Bangalore. We are actively our order pipeline consists of some projects that we are bidding for in Hyderabad. So yes, and we have regional offices in all these locations. So we are pretty much looking to grow, but we are also looking at picking and choosing. Bihar, Bengal, which continue to be cash strapped are not we're just maintaining our presence there. We're not we're picking and choosing. We're not very aggressive because we feel the state government is stretched financially.

55:48 Assam is something which we are looking to grow. Mumbai, we're looking to grow. Bangalore and Hyderabad, we're looking to grow. Understood, sir. Thank you and all the best. Thank you. Thank you. The next question is from the line of from Swan Investments. Please Hi, sir. Thank you for the opportunity. My question is, yeah, my question is with respect to the DLF city center downtown project. There is an increase of, by 200 crores in the order value. Is this purely like commodity price inflation that is passed on or there is some increase in the scope of work?

56:34 So this is an increase in scope of work. Ishita, did you get my answer? Yes. Thank you. Yeah. As there is no response, I'm taking the next question from the line of Ankit, an individual investor. Please proceed. Yeah. Hi. Good evening. Thanks for taking my So, sir, I wanted to check on... So I think material cost question has been answered, which was one of the point I had. But at the same time, in quarter three and quarter four, we are seeing that we'll be maintaining a quarter two margin. However, last year, the last year quarter three was also impacted by MG2 severely.

57:23 Last year, we maintained almost 9% of margin. So and we did not have Central Vista as a base, which we discussed in quarter four and quarter one concourse in that. In quarter three, we will have Central Vista as a cushion against the last quarter three base. So why would we still maintain the quarter two margin for quarter three and quarter four is the first question I have. Okay. So as I said, my guidance is conservative. But to be slightly more specific, yes, central infrastructure is there. But at the same time, what we are seeing is that the price continues there, especially on our electromechanical work.

58:20 The impact of price increase vis a vis the actual compensation through the escalation clauses, we are still not sure whether that will be fully compensated in these quarters. As I said during the life cycle of a project, it tends to match towards the second latter half of the life cycle of a project. Secondly, there is going to be a bit of an impact on account of increase. As per our calculation, it is going to impact our margin by about zero five percentage point. Having said that, we are reaching out. We have already reached out to all our clients that this needs to be compensated to us because this is a change in government policy.

59:09 So we are whether we will be able to convince our clients and they would agree within the next two quarters, that remains to be seen. So these are some of the and then we are still not very clear about the supply chain. Will it continue to be impacted? One day, we feel that the war is over. The second day, we hear that Iran has hit some U. S. Assets of basis in Bahrain. So this uncertainty continues to be there, and we feel that it's better to factor them in while giving a guidance. But as I said, my guidance is conservative. It will definitely be around what we've achieved in Q2, we can better it also. Sure. And just extension to that, sir, is that the private residential projects, which we discussed earlier, are normally margin accretive.

1:00:01 As the execution will pick up, may not be in the quarter three because of MGTO or some part of quarter four. But eventually, will that have an accretive effect on our margins despite of the labor increase and then subsequently, I think the prestigious clients are considering that henceforth? I think so. Okay. One more, sir, is about the Varanasi project. So I think I just missed that point, but I understood that the Varanasi project will be hopefully completed before the UP election as it is due for the inauguration or client wants once it's that way. Is that the right amount? Yes, you're right. That is what the government is wanting for it to be inaugurated prior to the elections.

1:00:54 And that is what we are all towards. The next question is from the line of Shrivansha from Doylott Capital. Hi, sir. Sir, on the bidding pipeline, so two things. One is how much value of projects that we have bid and bid is yet to open, and what's the bid pipeline currently? Okay. The first part of your question, I think the projects that we bid for open on private sector, it's not really a public opening.

1:01:40 So I think projects which have been bid for between private and public sector was INR 1,500 crores. Our total pipeline as it stands today is about INR 5,000 crores. Got it, sir. Thank you and all the best. Thank you. Thank you. The next question is from the line of from GM Financial. Please proceed. On depreciation, we have seen a sharp rise in Q1 and Q2 to 32 crores and 35 crores. So incrementally, what are we expecting in terms of quarterly rate? This quarter, if you see, has increased around INR 2.5 crores.

1:02:26 And you may expect that for the whole year around 35 course average. Okay. And next year? Next it would be around, I think, 37 to 38 crores. Okay. And the CapEx for next year, FY 'twenty eight? It would be similar about, as I said, about 220 crores. Between 220,250 crores. Okay. Okay. Thank you, sir. Those are my questions. Thanks. Thank you. Ladies and gentlemen, that was the last question for today. I now hand the conference over to the management for closing comments.

1:03:16 Thank you, everybody, for joining in, and see you soon. Thank you very much. On behalf of Ambit Capital, that concludes this conference. Thank you for joining us, and you may now disconnect your lines. Thank you.

Follow Ahluwalia Contracts (India) Limited into a list and get an email when it puts out news.

Latest news releases

Companies on this call

Speakers

Deepashree Joshi

at Ambit Capital

Shubhed Upal

Deputy Managing Director at Ahluwalia Contracts (India) Limited

Sadhvi Singh

Chief Financial Officer at Ahluwalia Contracts (India) Limited