  1. Slide 1: Master Plan Presentation: NCSP Group Development Strategy until 2020

    Master Plan Presentation NCSP Group Development Strategy until 2020 March 2012 Moscow 2012

  2. Slide 2: Disclaimer

    Disclaimer All statements in this presentation, other than historical facts, that address company’s business are forward looking statements. Although, NCSP believes that expectations expressed in such forward looking statements are based on reasonable assumptions, such statements should not in any w

  3. Slide 3: Contents

    Contents 1. Introduction 2. Strategy Highlights 3. Investment Projects 3

  4. Slide 4: NCSP Group Today

    NCSP Group Today Key Highlights  Largest port operator in Russia and third largest in Europe in terms of cargo turnover o 29.75% of total cargo turnover through Russian sea ports in 2011 Primorsk  Unique geographic location – all west- and south- bound routes of Russian foreign trade Baltysk  Com

  5. Slide 5: History of NCSP Group

    History of NCSP Group 2006 – 2007 2007 – 2010 2011 - Credit ratings, Eurobonds, IPO - First wave of consolidation - Acquisition of PTP - Completion of NGT - Abolition of internal - New team - new strategy competition in the port - Completion of first stage of BSC development - Implementation of Mast

  6. Slide 6: Shareholder Structure of NCSP Group and the Golden Share

    Shareholder Structure of NCSP Group and the Golden Share Shareholder structure “Golden Share” – is a paragraph in the Charter that enables: 5.3% 20.0% o Russian Government represented by Federal State Property Management Agency to nominate one candidate to the Board of Directors with a veto right 50

  7. Slide 7: New Management Team

    New Management Team Marat M. Shaydayev Rado Antolovic First Deputy CEO Deputy CEO for marketing and sales • Appointed in February 2011 • Appointed in March 2011 • 2004 - 2006 – General director of “SUMMA” Ltd. • Has been working in various ports since 1976, in such companies as MOL, • 2005 - 2009 –

  8. Slide 8: New Management Team

    New Management Team Alexey A. Medvedev Mikhail V. Sidorov IT Director Deputy CEO for Public Relations • Graduated with honors from Izhevsk State Technical University with a degree in • 2006-2009 - different positions in “IMA Group”. More than 15 years of engineering professional experience. Has succ

  9. Slide 9: Contents

    Contents 1. Introduction 2. Strategy Highlights 3. Investment Projects 9

  10. Slide 10: Objectives, Tasks and Elements of NCSP Group Strategy

    Objectives, Tasks and Elements of NCSP Group Strategy Objectives Tasks  To become the most effective port operator in  To ensure equal access to the Port infrastructure Russia for all freight forwarders  To strengthen the Group’s position as the largest  To achieve maximum efficiency of current

  11. Slide 11: Current Areas of Efficiency Improvement of NCSP Group

    Current Areas of Efficiency Improvement of NCSP Group STRATEGY  Master Plan developed for the period of 2012-2020 providing clear roadmap for long term sustainable business growth.  Senior executives replaced with highly professional and experienced management team;  Moscow Representative Office

  12. Slide 12: Current Areas of Efficiency Improvement of NCSP Group

    Current Areas of Efficiency Improvement of NCSP Group  Creation of unified motivation system for the Group of companies on the basis of KPIs and their relation to strategic development directions ;  Setting up KPI system for top managers based on their goals achievement and considering the Shareho

  13. Slide 13: NCSP Group Strategy for 2011-2020

    NCSP Group Strategy for 2011-2020 Short-term strategy Medium-term strategy Long-term strategy (2011-2012) (2012-2015) (2015-2020) Organization  New organizational structure  Pilot projects for consolidation  Capitalizing on pilot projects’ approval of certain functions experience to consolidate G

  14. Slide 14: Containers Market Model

    Containers Market Model Mln TEU per year In 2011 NCSP Group Container turnover increased by 27% (in TEU) including 44% growth in Novorossiysk versus average Russian market growth rate of 20% Key regions of container transshipment growth Transit through ports Percent 100% = 9 mln TEU of Finland North

  15. Slide 15: Grain Market Model

    Grain Market Model Mln tons per year In 2011, the Group achieved growth in grain handling (+0,3%), despite the fact that the export ban in 2011 lasted for six months versus 4.5 months in 2010, demonstrating record monthly average grain handling volumes Transshipment, fact Rail and other Transshipmen

  16. Slide 16: Iron Ore & Ore Concentrate Market Model

    Iron Ore & Ore Concentrate Market Model Mln tons per year Transshipment, fact Transshipment, forecast In 2011, the Group achieved growth in Iron Ore & Ore Concentrate handling of 25% Iron ore production and export balance in Russia 29 Capacity widening projects 24 22 107 112 ▪ Kimkanskoe The Far 85

  17. Slide 17: Oil Market Model

    Oil Market Model Mln tons per year Oil exports and main pipelines capacity, 2020 mln tons Capacity reserve In 2011 NCSP Group was 450-5051 Transshipment, fact able to maintain stable 420 volumes of crude oil 220-240 Transshipment, forecast 250-290 transshipment (-0,9%) despite decrease of exports fr

  18. Slide 18: Oil Products Market Model

    Oil Products Market Model Mln tons per year Exports and domestic oil processing, 2020 In 2011 NCSP Group Transshipment, fact increased oil products 400-500 Transshipment, forecast transshipment by 30% following the rent of two Russian Baltic ports 220-240 160-280 berths in Primorsk. Further growth p

  19. Slide 19: Coal Market Model

    Coal Market Model Mln tons per year Transshipment, fact Transshipment forecast, Rail and other types negative scenario Transshipment of transport Transshipment Transshipment forecast, through Baltic 17-17 positive scenario through Russian 12 States ports 3 Baltic ports 14 8-11 26-39 8 2010 2020 8 3

  20. Slide 20: NCSP Group Objectives

    NCSP Group Objectives Containers Oil  To ensure appropriate growth of transshipment  To monitor oil production outlook, including East capacities Siberian oil fields  To create a schedule of capacity growth, starting from  To ensure NCSP competitive advantage in Russian oil the least costly proj

  21. Slide 21: Railway infrastructure development in the direction of Primorsk

    The problem of development of railway infrastructure in the direction of Primorsk port is being resolved in cooperation with Roszheldor and RZD • Modernization of • Construction of a new railway line Ruchyi – Losevo Railway Kamennogorsk – Losevo connection under • Construction and • The project is i

  22. Slide 22: Construction of Yard B at Novorossiysk station

    Construction of the Yard B at Novorossiysk station will solve the problem of capacity shortage in the direction of the port Tikhoretsk Southern region Timashevsk Temryuk 2Н Kavkaz 4Н Yurovsky 3Н 9th km Krasnodar Krymskaya Anapa Novorossiysk Grushevaya  It is not the main raiway line and railway acc

  23. Slide 23: Contents

    Contents 1. Introduction 2. Strategy Highlights 3. Investment Projects 23

  24. Slide 24: NCSP Group Investment Projects – Summary

    NCSP Group Investment Projects – Summary NCSP Group continues to implement its investment program, which was approved by the previous team. The main emphasis of the program was made on new terminals construction (Sheskharis, NMT, BSC). Out of $538 mln1, $416 mln had been invested as of the end of 20

  25. Slide 25: Current Projects in Accordance with Existing Investment Program

    Current Projects in Accordance with Existing Investment Program IPP - Implementation Seskharis - Implementation Replacing old tanks, Completion of the the oil terminal’s construction of new tanks for oil reconstruction is planned for 2013. The products and liquid fertilizers terminal’s throughput ca

  26. Slide 26: Existing Investment Projects

    Existing Investment Projects Bunkerage complex PTP BSC Construction of bunkerage complex with the capacily of 410 Completion of construction of the first phase of container thousand tons per annum has been completed (potential to terminal with capacity of 200 thousand TEU for Kaliningrad handle fuel

  27. Slide 27: Existing Investment Projects

    Existing Investment Projects Construction period Investments Invested to date Additional Project Start End ($ mln) ($ mln) Capacity 1. Approved and existing projects Novorossiysk 1▪ Reconstruction of 2006 2013 145.7 113.8 + 0-15 mln tons Sheskharis Oil Terminal 2 ▪ Construction of Fuel Oil April 201

  28. Slide 28: Sheskharis Oil Terminal reconstruction

    Overview of Key investment Projects Sheskharis Oil Terminal reconstruction Objective ▪ Construction of the terminal А with capacity of 50 mln tons to ensure capital repairs at the terminal B ▪ Possibility to admit vessels with 150 thousand tons DWT, Old Berth (B) which are currently served at the be

  29. Slide 29: Construction of Fuel Oil Terminal, Pier 4 reconstruction

    Overview of Key Investment Projects Construction of Fuel Oil Terminal, Pier 4 reconstruction Objective ▪ Construction of a modern fuel oil terminal with capacity of 4 mln tons per annum through a 50–50 joint venture with a major international oil trader ▪ Dredging up to 13.5 m and reconstruction of

  30. Slide 30: Bunkering terminal expansion and reconstruction at IPP

    Overview of Key Investment Projects Bunkering terminal expansion and reconstruction at IPP Expansion of bunkerage complex IPP Reconstruction of IPP Objective Objective  Expansion of an existing storage park via construction of a  Increase of existing capacities of IPP by replacing old tanks new ta

  31. Slide 31: Construction of bunkerage complex at Primorsk

    Overview of Key Investment Projects Construction of bunkerage complex at Primorsk Objective Bunkerage complex ▪ Construction of bunkerage complex with the capacily of 410 thousand tons per annum has been completed ▪ Before the launch of the complex, bunkering services were offered by other operators

  32. Slide 32: Container terminal construction at Baltiysk

    Overview of Key Investment Projects Container terminal construction at Baltiysk Objective  Construction of modern container terminal with capacity of 400 thousand TEU for Kaliningrad region needs Key changes ▪ Container throughput increase is possible due to existing clients’ volumes growth, as wel

  33. Slide 33: The New Development Concept - Specialization of NCSP's Production Areas

    The New Development Concept - Specialization of NCSP’s Production Areas Profitability analysis of storage space at NLE and NCSP in 2010 Outbuildings EBITDA per m2 of storage space1. Share in aggregated EBITDA of Thousand RUB per annum # NLE + three NCSP Areas Thousand RUR per m2 p/a NLE NCSP <2 2-3

  34. Slide 34: The New Development Concept - Specialization of NCSP's Production Areas

    The New Development Concept - Specialization of NCSP’s Production Areas Projected specialization of production areas by 2020 Grain Containers ICD/Land acquisition NLE NGT – Under consideration Sugar/Perishable Iron ore/fertilizers Establishing ICD in Construction of specialized Construction of addit

  35. Slide 35: The New Development Concept - Containers

    The New Development Concept - Containers Development options There were three options considered to increase container cargo flow in Novorossiysk. Management opted for the least expensive and least risky option to achieve the result Option I – DECLINED Option II – DECLINED Option III ▪ Construction

  36. Slide 36: Construction of dedicated container terminal at NLE

    The New Development Concept - Containers Construction of dedicated container terminal at NLE with up to 500 thousand TEU capacity NLE Capacity Objective Thousand TEU 2011 2012 2013 2014 2015 2016 2017 New Project 0 0 0 86 300 400 450 ▪ Construction of a dedicated container terminal on the base of Ex

  37. Slide 37: Construction of Inland Container Depo (ICD)

    The New Development Concept - Containers Construction of Inland Container Depo (ICD) A distinctive feature of ICD is its functional dependence on the sea port operations, which determines scope of services at the inland terminal Major factors, affecting ICDs operations Major ICD advantages for sea p

  38. Slide 38: Logistics container delivery chain from door to door

    The New Development Concept - Containers Logistics container delivery chain “from door to door” ▪ Port services c.u./TEU 0.075 Exists Long-term scheme, requires development ▪ Terminal c.u./TEU 1.0 Exists End customer/ laden Road ▪ Freight forwarding and ICD c.u./TEU 0.75 Partially transpotation cont

  39. Slide 39: NGT expansion

    Overview of Investment Projects NGT expansion Objective ▪ NGT capacity expansion through ▪ New grain silos which will increase storage capacity from 120 to 188 thousand tons ▪ Instalation of a third ship loader ▪ Construction of a fourth line for unloading grain trucks ▪ Berths repair Planned result

  40. Slide 40: New Development Strategy – Iron Ore and Ore Concentrate Terminal

    New Development Strategy – Iron Ore and Ore Concentrate Terminal Marketing study of the project Financial results and investments ▪ Metalloinvest production of iron ore in 2011 was 40.1, 22.0 mln tons of ▪ 2011 results pellets, 5.2 mln tons of HBI/DRI – Throughput: 2.9 mln tons per annum ▪ There was

  41. Slide 41: Hydrotechnical infrastructure of iron ore and ore concentrate terminal

    New Development Strategy – Iron Ore and Ore Concentrate Terminal Hydrotecnical infrastructure of iron ore and ore concentrate terminal Railway Covered storage for mineral fertilizers Ship-loaders Covered storage for iron ore 41

  42. Slide 42: Potential Projects

    Potential Projects Long-term projects of construction of terminals in Primorsk for handling Containers, Ferrous Metals, Iron Ore and Ore Concentrate, Mineral Fertilizers and Oil Products Project description ▪ Objective: construction of multi-purpose deep-water port in the Russia’s North-West; creati

  43. Slide 43: Projects of The New Development Concept

    Projects of The New Development Concept Construction Period Investments Additional Project Start End ($ mln) Capacity 8 ▪ Construction of specialized container terminal 2012 2014 207.1 + 500 thousand TEU on the basis of NLE facilities (including modernization of current NLE and Port infrastructure)

  44. Slide 44: Your Contacts at NCSP

    Your Contacts at NCSP: Your Contacts at NCSP: Mikhail Grigoriev Head of Investor Relations Tel: +7 (495) 771-6060 ext. 238 e-mail: MGrigoriev@nmtp.info Kristina Senko Press-centre Tel: + 7 (8617) 60-43-93, Fax: + 7 (8617) 61-21-40 e-mail: senko@ncsp-net.com 44