Dakota Gold Corp. · AMEX:DC
Dakota Gold — Technical Presentation (November 2026)
38 slides from Dakota Gold's technical presentation, Nov 23, 2026

Slide 1: Richmond Hill Gold Project Pre-Feasibility Study Webcast Presentation
Richmond Hill Gold Project Pre-Feasibility Study Webcast Presentation | November 23, 2026 NYSE American: DC dakotagoldcorp.com

Slide 2: Company Overview and PFS Highlights
COMPANY OVERVIEW PFS HIGHLIGHTS JACK HENRIS CEO, PRESIDENT & DIRECTOR dakotagoldcorp.com | NYSE-A: DC 2

Slide 3: Disclaimer
Disclaimer Cautionary Note Regarding Forward-Looking Statements This presentation and the accompanying webcast contain “forward-looking statements” within the meaning of Section 27A of the Securities Act of 1933 and Section 21E of the Securities Exchange Act of 1934, which are intended to be covere

Slide 4: PFS supports simple, open pit, heap leach project
Richmond Hill – PFS supports simple, open pit, heap leach project Richmond Hill Pre-Feasibility Study outlines an efficient, three stage crush and truck stack operation to provide strong economics and leverage to the gold price GOLD PRICE AFTER-TAX NPV 5% AFTER-TAX IRR AFTER-TAX PAYBACK LOM AISC US

Slide 5: Growth potential
Richmond Hill – Growth potential Pre-Feasibility Study Outlines Strong Foundation for Future Growth and Mine Sequence Optimization 2026-2027 DEFINITION DRILL PROGRAM UNDERWAY Targeting Increase in Reserve For Feasibility Study Inferred Material Conversion in High-Recovery Breccia Zone Not Included

Slide 6: Richmond Hill recap of heap leach resource and exploration potential
RICHMOND HILL recap of HEAP LEACH RESOURCE and EXPLORATION POTENTIAL LINDSAY CHASTEN SENIOR EXPLORATION MANAGER dakotagoldcorp.com | NYSE-A: DC 6

Slide 7: Reserve and Resource review
Richmond Hill – Reserve and Resource review PFS Mineral Reserve and Resource - November 2026 • Heap Leachable Mineral Reserve: • 2.2 M oz of P&P Gold • 25.4 M oz of P&P Silver • Heap Leachable Mineral Resource: (Exclusive of Reserves) • 0.4 M oz of M&I Gold • 5.2 M oz of M&I Silver • 1.1 M oz of Inf

Slide 8: Heap leachable reserves and resources
Richmond Hill – Heap leachable reserves and resources Richmond Hill Heap Leachable Reserves Notes: NSR Gold Silver • Mineral resources reported are exclusive of reserves. Category Ktonnes Gold (koz) Silver (koz) • Based on a constrained block model using drill results up to June 17, 2026, ($/tonne)

Slide 9: Drilling filled M&I gaps between the IA and PFS
Drilling filled M&I gaps between the IA and PFS Section location Section 3760 m / 12332 ft North IA model • February 2025 W E N 100 m grid • Showing PFS M&I and MI&I shells PFS model • November 2026 W E M&I blocks • 10 m slices • 100 m grid dakotagoldcorp.com | NYSE-A: DC 9

Slide 10: Drilling filled M&I gaps between the IA and PFS
Drilling filled M&I gaps between the IA and PFS Section location Section 5000 m / 13448 ft North IA model • February 2025 W E N 100 m grid • Showing PFS M&I and MI&I shells PFS model • November 2026 W E M&I blocks • 10 m slices • 100 m grid dakotagoldcorp.com | NYSE-A: DC 10

Slide 11: Opportunities for resource growth
Opportunities for resource growth • The 2026-2027 Definition Drill Program includes approximately 11,000 meters in 123 holes and is designed to test the potential to convert Inferred Mineral Resources within and adjacent to the PFS pit to Measured and Indicated (M&I) N • The Definition Drill 500 m N

Slide 12: Richmond Hill PFS supports efficient, open pit heap leach operation
RICHMOND HILL PFS SUPPORTS EFFICIENT, OPEN PIT HEAP LEACH OPERATION MIKE EISELEIN VICE PRESIDENT PROJECT DEVELOPMENT dakotagoldcorp.com | NYSE-A: DC 12

Slide 13: PFS led by M3
Richmond Hill – PFS led by M3 Lead Study Manager Resource and Environmental & Metallurgy Heap Leach Mining Plan Water Treatment Design, Closure & Reclamation Environmental sub-contractors supporting permit engineering • LifeCycleGeo • BKS Environmental Assoc. • Vantage Point • Geosyntec • GEI Consul

Slide 14: PFS overview
Richmond Hill – PFS overview Pre-Feasibility Key Parameters (All Currencies in US$) Technically straightforward, open pit and heap leach operation Key Assumptions • Processing 120 Mt LOM, three-stage crush Base Case Gold Price $3,500/oz • Peak mining rates approximately 36mt per year starting in yea

Slide 15: PFS plan production & cost profile
Richmond Hill – PFS plan production & cost profile Gold Equiv Prod (kozs) Gold Prod (kozs) Gold Grade (g/t) YEAR 1 YEAR 2 YEAR 3 YEAR 4 YEAR 5 YEAR 6 YEAR 7 YEAR 8 YEAR 9 YEAR 10 250 PFS 171,000 oz/yr 200 AVG GOLD PRODUCTION Gold Production (1,000’s oz) 150 1.6 Moz GOLD LOM PRODUCTION (9-year mine

Slide 16: Mine schedule profile
Richmond Hill - Mine schedule profile • Eight-year mining, focusing on grade and recoveries to bring value forward • Years 1 – 2: Sub-phasing high grade smaller pits • Years 3 – 5: Higher value ultimate pits • Years 6 – 8: Final pits and mining • Conventional truck & shovel open pit operation • Loa

Slide 17: Mine production schedule
Richmond Hill - Mine production schedule • Peak Mining rates approximate 36mt per year starting in year 2 • Transition material (10.6mt) stockpiled and processed in year 9 Material and Waste (thousand tonnes) 40,000 36,288 36,261 36,314 35,776 36,288 35,000 30,000 27,216 23,665 25,000 22,956 20,000

Slide 18: Heap leach pad production profile
Richmond Hill - Heap leach pad production profile • Quick recovery – 30-to-45-day average leach cycle to achieve a projected LOM pad recovery of 72.4% • Heap leach pad with Merrill Crowe processing designed for with a capacity of 41ktpd but with potential future expansion to 54ktpd • Residual produ

Slide 19: PFS capital cost details
Richmond Hill – PFS capital cost details Capital cost estimate based on open pit mining utilizing a single heap leach pad, truck and shovel Capital Cost Items (US$M) Initial Sustaining LOM operation with Merrill Crowe processing with a Ore Preparation (Earthworks and Crushing circuit) $127.2 $0.0 $1

Slide 20: PFS proposed infrastructure
Richmond Hill – PFS proposed infrastructure • 725 acres of disturbance is anticipated with the initial permit • Large single heap leach with capacity for 154mt, with strong natural buttressing and built for the final 40mt to be “on-off” and reusable • Small overall crushing plant footprint consisten

Slide 21: Processing flow sheet
Richmond Hill - Processing flow sheet Three stage, crush, shovel and truck operation processing ~41kTPD dakotagoldcorp.com NYSE-A: DC dakotagoldcorp.com || NYSE-A: DC 21

Slide 22: PFS operating cost details
Richmond Hill – PFS operating cost details Costs based on a detailed annual mining and processing schedule, including variations in haulage profiles Operating Cost Items LOM (US$M) US$/tonne US$/oz Au leached Mining Costs Mining $787.9 $6.59 $505 • Open pit truck and shovel mining operation using in

Slide 23: Metallurgy
Richmond Hill - Metallurgy Positive Metallurgical Results PFS Assigned Gold Recovery by Lithology • 24 master-composite column tests and 110 bottle-roll tests – Oxide, 12.7 mm (1/2-inch) P80 confirmed that Richmond Hill is amenable to heap leaching, with positive gold recoveries supporting the Pre-F

Slide 24: Location and infrastructure
Richmond Hill - Location and infrastructure Legend Richmond Hill – Private Land Location: Richmond Hill M&I resource cone • Project 15-minute drive from headquarters in Lead, SD Maitland - Private Land Coeur - Wharf Land Package Labor: • South Dakota provides access to labor for exploration through

Slide 25: Richmond Hill PFS outlines profitable operation
RICHMOND HILL PFS OUTLINES PROFITABLE OPERATION SHAWN CAMPBELL CHIEF FINANCIAL AND DEVELOPMENT OFFICER dakotagoldcorp.com | NYSE-A: DC 25

Slide 26: PFS strong economics
Richmond Hill – PFS strong economics • The PFS has robust project economics, including a $2.0 billion NPV(5%), 71% IRR and a payback of only 1.4 years at a base case gold price of $3,500/oz. The financial metrics remain robust in a lower gold price environment, and at a gold price of $4,250/oz the

Slide 27: PFS after-tax free cash flow profile
Richmond Hill – PFS after-tax free cash flow profile • For years 1 through 8 the average after-tax free cash flow per year is ~$366 M at a gold price of $3,500/oz and $474 M at a gold price of $4,250/oz PRE-PROD YEAR 1 YEAR 2 YEAR 3 YEAR 4 YEAR 5 YEAR 6 YEAR 7 YEAR 8 YEAR 9 YEAR 10 YEAR 11 LOM $4,00

Slide 28: Strong project financial metrics
Richmond Hill – Strong project financial metrics $3,500/oz Au (Base Case) $4,250/oz Au Net Present Value discounted at 5% to Initial Capital Cost Ratio NPV5% @ $3,500/ oz Gold Price $2,000 M $2,744 M Initial Capital Cost $538 M $538 M Ratio of NPV5%: CAPEX 3.7 X 5.1 X Number of Times Initial CAPEX i

Slide 29: Opportunity for increased valuation
Opportunity for increased valuation • Opportunity for $EV/oz of Resources and Reserves valuation to increase as Richmond Hill advances through Feasibility Study and into Production. Developer US$EV/ RESOURCE oz Developer US$EV/ RESERVE oz Source: CIBC Weekly Mining Comps as at Nov 2, 2026 dakotagold

Slide 30: Illustrative peer production multiples
Illustrative peer production multiples Source: CIBC Weekly Mining Comps Report as of Nov 2, 2026 170 KOZPA as 1.TEV = market cap + net debt + non-controlling interest + preferred shares 2026E Prod'n EV (US$M) 2.Analyst consensus estimates. COMPANY TEV (US$M)1 % of (AuEq koz)2 per 170 KOZPA PRODUCTIO

Slide 31: Value Creation Opportunity
VALUE CREATION OPPORTUNITY JACK HENRIS CEO, PRESIDENT & DIRECTOR dakotagoldcorp.com | NYSE-A: DC 31

Slide 32: Timeline to production
Richmond Hill - Timeline to production - Targeting first gold production in 2029 through a disciplined, phased responsible development approach 2026 2027 2028 2029 2030 Pre-Feasibility Study Feasibility Study Baseline Data Collection Permitting - County Conditional Use Permit - SD DANR Large Scale M

Slide 33: Homestake District: One location. Multiple opportunities.
HOMESTAKE One location. Multiple opportunities. DISTRICT Dakota Gold’s land package creates a diversified project-development portfolio in one of America’s most prolific gold districts. ~50K MINERAL ACRES DEVELOPMENT PROJECT RICHMOND HILL Production pathway and Pre-Feasibility Feasibility Permitting

Slide 34: Questions and Answers
Richmond Hill Gold Project Pre-Feasibility Study QUESTIONS and ANSWERS NYSE American: DC dakotagoldcorp.com

Slide 35: Media and Investor Relations
MEDIA AND INVESTOR RELATIONS Jack Henris Chief Executive Officer, President and Director O +1 605 717 2540 Shawn Campbell Chief Financial and Development Officer info@dakotagoldcorp.com O +1 778 655 9638 Carling Gaze @dakotagoldcorp Director of Investor Relations O +1 605 679 7429 linkedin.com/compa

Slide 36: Appendix
APPENDIX dakotagoldcorp.com | NYSE-A: DC 36

Slide 37: Millable Resources
Richmond Hill – Millable Resources Notes: NSR Gold Silver • Based on a constrained block model using drill results up to June 17, 2026, Category Ktonnes Gold (koz) Silver (koz) ($/tonne) (g/tonne) (g/tonne) with estimation using inverse distance squared methodology. • A gold price of $2,900 per ounc

Slide 38: Combined Heap Leachable and Millable Resources Inclusive of Reserves
Richmond Hill – Combined Heap Leachable and Millable Resources Inclusive of Reserves Notes: NSR Gold Silver Gold • Based on a constrained block model using drill results up to June 17, 2026, Category Ktonnes Silver (koz) ($/tonne) (g/tonne) (g/tonne) (koz) with estimation using inverse distance squa
Source: company website
More decks from Dakota Gold Corp.
Investor Presentation (November 2026)30 slides · November 2026
LD Micro 20th Annual Main Event (October 2026)21 slides · Oct 21, 2026
Investor Presentation (October 2026)30 slides · October 2026
38th Annual Mining Forum Americas (September 2026)18 slides · Sep 29, 2026
Precious Metals Summit Beaver Creek 202614 slides · Sep 24, 2026
H.C. Wainwright & Co. 28th Annual Global Investment Conference (September 2026)22 slides · Sep 14, 2026