Belo Sun Mining Corp. · TSX:BSX

Belo Sun Mining — Investor Presentation (November 2013)

53 slides from Belo Sun Mining's investor presentation, November 2013

  1. Slide 1: The Largest Developing Gold Project in Brazil

    TSX: BSX The LARGEST developing GOLD PROJECT in BRAZIL CORPORATE PRESENTATION November 2013

  2. Slide 2: Cautionary Notes

    Cautionary Notes All statements, other than statements of historical fact, contained or incorporated by reference in this presentation, but not limited to, any information as to the future financial or operating performance of Belo Sun, constitute ‘‘forward-looking information’’ or ‘‘forward-looking

  3. Slide 3: BSX Opens TSX April 30th, 2012

    BSX Opens TSX April 30th, 2012 TSX: BSX 3

  4. Slide 4: Key Projects

    Key Projects Volta Grande (5.1 Moz M&I) (2.5 Moz Inf) TSX: BSX 4

  5. Slide 5: Resource Expansion (2009 to 2013)

    Resource Expansion (2009 to 2013) Under Present Management Under Present Management Verena (Pre • 42 Additional • 137 • 112 • 273 Additional • 126 Additional • 94 Additional BSX) Drill Holes Additional Additional Drill Holes Drill Holes Drill Holes • 170 Drill Included Drill Holes Drill Holes Includ

  6. Slide 6: Experienced Board & Management

    Experienced Board & Management BOARD OF DIRECTORS MANAGEMENT Peter Tagliamonte (Chairman) BRAZIL OPERATIONS TORONTO OFFICE Engineer Stan Bharti Carlos Costa Ian Pritchard Engineer Geologist (30 years experience) Chief Operating Officer Jay Hodgson Ricardo Lopes Ryan Ptolemy Geologist Geologist (27 y

  7. Slide 7: Capital Structure

    Capital Structure Shares Outstanding No. 265.9 million Fully Diluted No. 285.9 million Share Price C$ $0.40 * Market Capitalization C$ $106 million 52 Week High & Low C$ $1.83 - $0.34 Average Daily Volume No. 1,000,000 (3 month average) Cash & Cash Equivalents C$ $25 million ** *As at Nov 4th , 2013

  8. Slide 8: Volta Grande Infrastructure

    Volta Grande Infrastructure TSX: BSX 8

  9. Slide 9: Belo Monte Dam Construction

    Belo Monte Dam Construction 9

  10. Slide 10: Volta Grande Main Deposits (October 2013)

    Volta Grande Main Deposits (October 2013) Ouro Verde Measured & Indicated: 44.2 Mt (2.4M oz) @ 1.70 g/t Au Inferred: 23.4 Mt (1.2M oz) @ 1.48 g/t Au Grota Seca Measured & Indicated: 47.1 Mt (2.4M oz) @ 1.59 g/t Au Inferred: 18.9 Mt (1M oz) @ 1.59 g/t Au Volta Grande Total Measured & Indicated: 93.8

  11. Slide 11: Volta Grande

    Volta Grande Topography View from Ouro Verde • Deposit located well above water line • Upstream damming of river will further reduce river level TSX: BSX 11

  12. Slide 12: Brownfields Exploration

    Brownfields Exploration Ouro Verde Grota Seca Target Areas for future resource expansion *South Block Inferred Resource Estimate -Indicated Pit Constrained – 2.5M tonnes Exploration Camp @ 3.06 g/t Au containing 246k oz Au -Inferred Pit Constrained – 2.9M tonnes @ 3.94 g/t Au containing 370k oz Au -

  13. Slide 13: Grande Artisanal Mine

    Grande Artisanal Mine Quartz veins – N60E/45SE TSX: BSX 13

  14. Slide 14: South Block Garimpo Operations - 1980

    South Block Garimpo Operations - 1980 TSX: BSX 14

  15. Slide 15: Volta Grande

    4 Wi Volta Grande BELO enn , MINING TSX: BSX

  16. Slide 16: Ouro Verde - Central portion of Domain-2

    OURO VERDE - Central portion of Domain-2 270 m HG zone inside of D2 Sec 975NW Sec 475NW

  17. Slide 17: Grota Seca - Central portion of Domain-1

    GROTA SECA - Central portion of Domain-1 - HG zone related to the general trend presented in slide 15 Sec 2050W Sec 1725W 190m Notes - Cut-off: aprox. 1.50 ppm HG zone inside of D1 - Num. drill holes: 41 - Num. samples: 487 - Thickness: max=16m, min=2m, aver=8m - HG zone near surface 325m

  18. Slide 18: Grota Seca - Portion along Galo area

    GROTA SECA - Portion along “Galo” area - HG zone related to the “galo” trend presented in the slide 15 Sec 800W Sec 525W Main structural controls Notes - Cut-off: aprox. 1.50 ppm - Num. drill holes: 42 - Num. samples: 377 - Thickness: need to be modeled TSX: BSX - HG zones near surface

  19. Slide 19: Galo - Garimpo U/G Operations

    Galo – Garimpo U/G Operations TSX: BSX 19

  20. Slide 20: Artisanal Mining

    Artisanal Mining TSX: BSX 20

  21. Slide 21: Artisanal Mining

    Artisanal Mining Garimpo TSX: BSX 21

  22. Slide 22: Garimpo Mine - Galo

    Garimpo Mine - Galo TSX: BSX 22

  23. Slide 23: Project Performance (After Tax)

    Project Performance (After Tax) Project Data Prefeasibility Results Production Data Life of mine 10 Years Annual Mine Throughput 7 million tpy Metallurgical Recovery Au 94% Average Annual Gold Production 313,100 oz Average Waste to Ore Strip Ratio 6.88:1 Average Grade of M&I Resource 1.72 g/t Averag

  24. Slide 24: Operating Cost Breakdown

    Operating Cost Breakdown Cost per tonne Ore in Cost per Ounce Produced Category US$ in US$ Mining Cost per Tonne material moved 2.26 Mining 17.36 389.60 Processing 10.50 235.70 General and Administrative 2.52 56.60 Total US$30.38 US$681.90 Strip Ratio 6.88:1 TSX: BSX 24

  25. Slide 25: Brazilian Reais

    Brazilian Reais Sept 2012 – Sept 2013 2.6 2.5 2.4 BRAZILIAN REAIS 2.3 2.2 2.1 2 1.9 Source: Bloomberg September 17th, 2013 TSX: BSX 25

  26. Slide 26: Sensitivities

    Sensitivities After Tax Discount at 5% CAPEX US$ OPEX US$ R$ to US$ IRR % NPV US$ Payback Millions Millions Years Base Case 749.1 711.5 2.08 15.2 474 4.5 CAPEX Reduced by 5% 711.7 711.5 16.3 507 4.3 CAPEX Reduced by 10% 674 711.5 17.4 535 4.1 CAPEX Reduced by 15% 636 711.5 18.6 565 3.9 OPEX Reduced

  27. Slide 27: Volta Grande - Preliminary Project Layout

    Volta Grande – Preliminary Project Layout TSX: BSX 27

  28. Slide 28: Proposed Location of Plant Facility

    Proposed Location of Plant Facility TSX: BSX 28

  29. Slide 29: Regional Geology & BSX Sampling/Geophysics

    Regional Geology & BSX Sampling/Geophysics Jatoba BSX airborne survey limit  11 DDH = 2,389m + auger drilling 11m @ 0.3 % Cu (up to 1.38% Cu)  Geotem-mag airborne survey 28 km road access from Itata to BUMA  grid soil sampling: up to 189 ppb Au (1km line spacing) Garimpinho 79.5 g/t Au in diorite

  30. Slide 30: Artisanal Workings

    Artisanal Workings TSX: BSX 30

  31. Slide 31: Patrocinio Tapajos District

    Patrocinio Tapajos District More than one million ounces of historical gold production at Patrocinio 3.0 km by 1.5 km soil geochemical anomaly defined Grab samples have returned gold values up to 37 g/t in granite and up to 67 g/t in veins IP geophysical survey completed 1,500 meter drill program co

  32. Slide 32: Patrocinio Project Garimpeiro Mining

    Patrocinio Project Garimpeiro Mining TSX: BSX 32

  33. Slide 33: LTM Share Performance

    LTM Share Performance September 4, 2012 – September 4, 2013 60% Return Over Period 40% 20% – Spot Au: (18%) (20%) S&P/TSX Global Gold: (36%) (40%) Belo Sun: (38%) Emerging Gold Peers: (47%) Producing Gold Peers: (49%) (60%) (80%) Sep-12 Nov-12 Jan-13 Mar-13 May-13 Jul-13 Sep-13 1 Source: TD Securiti

  34. Slide 34: Independent Research Coverage

    Independent Research Coverage Independent Research – Full Coverage Firm Analyst TD Securities Dan Earle CIBC Jeff Kileen BMO Capital Markets John P. Hayes National Bank Financial Shane Nagle Cormark Securities Richard Gray Canaccord Genuity Rahul Paul Dundee Capital Markets Joseph Fazzini Macquarie

  35. Slide 35: Camp Site

    Camp Site Acampamento da Bel TSX: BSX 35

  36. Slide 36: Aerial View

    Aerial View Four Aérea Si Regiao TSX: BSX

  37. Slide 37: Ouro Verde - Block Model Cross Section 900 NW

    Ouro Verde – Block Model Cross Section 900 NW SW NE 0m MR Open Pit 70m Mining - Saprolite US$/t 1.06 Mining - Fresh rock Open Pit US$/t 1.41 g/t Au Processing US$/t 11.98 G&A US$/t 2.89 50m -200m 190m Au recovery - Saprolite % 94 Au recovery - Fresh Rock % 94 Selling cost US$ / Oz 13.82 Au Price US$

  38. Slide 38: Ouro Verde - Block Model Cross Section 525 NW

    Ouro Verde – Block Model Cross Section 525 NW SW NE 120m 0m 60m MR Open Pit g/t Au 150m Mining - Saprolite US$/t 1.06 Mining - Fresh rock Open Pit US$/t 1.41 Processing US$/t 11.98 G&A US$/t 2.89 -200m Au recovery - Saprolite % 94 Au recovery - Fresh Rock % 94 Selling cost US$ / Oz 13.82 Au Price US

  39. Slide 39: Ouro Verde - Block Model Cross Section 300 NW

    Ouro Verde – Block Model Cross Section 300 NW SW NE 0m 25m 120m MR Open Pit g/t Au Mining - Saprolite US$/t 1.06 70m Mining - Fresh rock Open Pit US$/t 1.41 Processing US$/t 11.98 G&A US$/t 2.89 Au recovery - Saprolite % 94 Au recovery - Fresh Rock % 94 -200m Selling cost US$ / Oz 13.82 Au Price US$

  40. Slide 40: Grota Seca - Block Model Cross Section 2575 W

    Grota Seca – Block Model Cross Section 2575 W SSW NNE MR Open Pit Mining - Saprolite US$/t 1.06 Mining - Fresh rock Open Pit US$/t 1.41 Processing US$/t 11.98 G&A US$/t 2.89 Au recovery - Saprolite % 94 Au recovery - Fresh Rock % 94 Selling cost US$ / Oz 13.82 Au Price US$ / Oz 1,400.00 Block Size:

  41. Slide 41: Grota Seca - Block Model Cross Section 1875 W

    Grota Seca – Block Model Cross Section 1875 W SSW NNE 75m 0m g/t Au 90m MR Open Pit Mining - Saprolite US$/t 1.06 -200m Mining - Fresh rock Open Pit US$/t 1.41 Processing US$/t 11.98 G&A US$/t 2.89 Au recovery - Saprolite % 94 Au recovery - Fresh Rock % 94 30m Selling cost US$ / Oz 13.82 Au Price US

  42. Slide 42: Grota Seca - Block Model Cross Section 825 W

    Grota Seca – Block Model Cross Section 825 W SSW NNE 130m 190m g/t Au 0m MR Open Pit -200m Mining - Saprolite US$/t 1.06 Mining - Fresh rock Open Pit US$/t 1.41 60m Processing US$/t 11.98 G&A US$/t 2.89 Au recovery - Saprolite % 94 Au recovery - Fresh Rock % 94 Selling cost US$ / Oz 13.82 Au Price U

  43. Slide 43: Breakdown by Elevation

    Breakdown by Elevation VGP - Pit Constrained MR – Sep 2013 (Belo Sun) Tonnage AU_CUT_OK ELEVATION Au Oz T x 1000 g/t 100MD 2,064.839 1.65 109,696 90MD 2,483.037 1.63 130,030 80MD 2,799.670 1.68 150,979 70MD 3,078.703 1.71 169,315 60MD 3,197.871 1.73 177,571 50MD 3,158.016 1.73 175,800 40MD 3,081.058

  44. Slide 44: The Right Deposit, Place, Time, People

    THE RIGHT DEPOSIT….. THE RIGHT PLACE ….. THE RIGHT TIME….. THE RIGHT PEOPLE….. TSX: BSX 44

  45. Slide 45: Volta Grande - Potential Crushing Plant

    Appendix Volta Grande – Potential Crushing Plant Crushing Annual processing rate 7,000,000 t/y Crushing availability 70.0 % Nominal capacity 1,142 t/h Installed power 375 kW Type Gyratory Crusher Feed top size 1,000 mm Product P80 175 mm Number of units 1 unit Feed silo capacity: 128 t (86 m3) 5 min

  46. Slide 46: Volta Grande - Potential Milling Plant

    Appendix Volta Grande – Potential Milling Plant Milling Plant Annual processing rate 7,000,000 t/y Availability 90.0 % Nominal capacity 888 t/h Feed P80 175 mm SAG discharge target P80 2.5 mm Ball mill discharge target P80 0.074 mm SAG mill 36 ft diam. X 20 ft EGL 1 unit Ball mill 26 ft diam. X 33 f

  47. Slide 47: Volta Grande - Potential Leach Plant

    Appendix Volta Grande – Potential Leach Plant Leach Plant Annual processing rate 7,000,000 t/y Availability 90.0 % Nominal capacity 888 t/h Feed P80 0.074 mm Leach feed thickener diameter 57.0 m Calculated leach plant recovery 89,23 - 90,91 % Calculated gold produced/week 5,921 - 6,048 oz Calculated

  48. Slide 48: Appendix Pre-feasibility

    Appendix Pre-feasibility Life of Mine 10 years Annual production throughput 7 million tpy Metallurgical Recovery 94% Avg annual gold production 313,100 oz/yr Avg waste to ore strip ratio 6.88:1 Avg head grade 1.48 g/t CAPEX US$ 749 million OPEX US$ 31.70/t of Ore Cost per ounce US$ 711.50 NPV @ 5% U

  49. Slide 49: Appendix Pre-feasibility

    Appendix Pre-feasibility Mine Fleet Trucks 180 t, Shovels 15m3 Process Gyratory Crusher, SAG and 2 ball mills Gravity Circuit Carbon in Leach Elution and Carbon Regeneration Electrowinning Smelting Cyanide Destruct Tailings Management Facility Situated in a natural basin TSX: BSX 49

  50. Slide 50: Appendix Pre-feasibility

    Appendix Pre-feasibility CRUSHING THICKENING STOCKPILE CARBON IN LEACH CYANIDE DETOX SEMI AUTOGENOUS ELUTION CARBON MILLING, BALL REGENERATION MILLING TAILINGS TREATMENT GRAVITY SEPARATION ELECTROWINNING INTENSIVE LEACHING SMELTING DORE BARS TSX: BSX 50

  51. Slide 51: Appendix Comparing PFS x April 2013 (CF)

    Appendix Comparing PFS x April 2013 (CF) TSX: BSX

  52. Slide 52: Volta Grande Capital Cost Estimate

    Appendix Volta Grande Capital Cost Estimate Value without Taxes Value with Taxes Area Description % of CAPEX (USDx1000) (USDx1000) General (Assemblies) 52,573 57,551 7.68% Mine 121,528 126,127 16.84% Plant – General 91,471 101,508 13.55% Crushing 11,412 12,186 1.63% Storage/Ore transference 5,087 5,

  53. Slide 53: The Largest Developing Gold Project in Brazil

    TSX: BSX The LARGEST developing GOLD PROJECT in BRAZIL Corporate Headquarters Helia Bento 65 Queen Street West Investor Relations Suite 815, P.O. Box 75 416-309-2137 Toronto, Ontario M5H 2M5

Belo Sun Mining — Investor Presentation (November 2013) on 6ix