Patel Engineering Limited · NSE:PATELENG

Patel Engineering — Q3 FY24 Earnings Presentation

50 slides from Patel Engineering's earnings presentation, Feb 12, 2024

  1. Slide 1: Submission of Investor/Analysts Presentation cover letter

    CIN: L99999MH1949PLC007039 February 12, 2024 To, BSE Limited The National Stock Exchange of India Limited Phiroze Jeejeebhoy Towers, Exchange Plaza, Dalal Street, Bandra - Kurla Complex, Mumbai - 400 001 Mumbai - 400 051 Company Code No. 531120 Company Code: PATELENG/EQ Dear Sir/Mam, Subject: Submis

  2. Slide 2: Patel Engineering Limited Investor Presentation Q3 FY24

    Patel Engineering Limited Investor Presentation | Q3 FY24

  3. Slide 3: Disclaimer

    Disclaimer This presentation and the accompanying slides have been prepared by Patel Engineering Ltd. (the “Company”), and have been prepared solely for information purposes and do not constitute any offer, recommendation or invitation to purchase or subscribe for any securities, and shall not form

  4. Slide 4: Company Overview

    Company Overview

  5. Slide 5: About Patel Engineering Limited

    About Patel Engineering Limited One of the most integrated infrastructure and construction services conglomerates in India Patel Engineering Limited, founded in 1949 and headquartered in Mumbai, is a prominent player in the civil engineering construction segment. With over seven decades of experienc

  6. Slide 6: Vision and Mission

    Patel Engineering Limited, is one of the MISSION major Infrastructure To be the pioneers in the industry and a and Construction market-driven organization known for its commitment towards excellence, Company quality, performance and reliability. Investor Presentation Q3 FY24 VISION Vision and Missio

  7. Slide 7: Key Facts and Figures

    Key Facts and Figures 7+ decades 14 States 15,000+ Experience Current Domestic Presence MW Hydro Project 87+ 300+ Kms 5.5+ Lakhs Dams of Tunnels Acres Irrigated 1,200+ Kms ₹ 1,91,347 Mn BBB+ Investor Presentation Q3 FY24 Road Order book ( Including L1 Orders) Credit rating Q3 FY24 Cons. Q3 FY24 Cons

  8. Slide 8: Stock Data

    Stock Data NSE: PATELENG BSE: 531120 | ISIN: INE244B01030 Share Holding Pattern As on 09-02-2024 As on 31-12-2023 Share Price (₹) 71.48 4.79% Market Capitalization (₹ Mn) 55,298.20 Promoters No. of Shares Outstanding 77,36,17,228 39.41% Face Value (₹) 1.00 FII 52 week High - Low (₹) 79.00– 13.10 DII

  9. Slide 9: Q3 FY24 Financial Highlights

    Q3 FY24 Financial Highlights

  10. Slide 10: Standalone Results Highlights

    Standalone Results Highlights Quarterly & Nine Month Revenue Performance in ₹ Quarterly & Nine Month Op. EBITDA and Net Profit Million 31,551.18 Performance in Million 4,325.29 26,249.43 3,644.75 Q3 FY23 2,149.97 Q3 FY24 Op. EBITDA 9,293.89 10,523.09 1,447.40 9M FY23 1,307.12 Net Profit 9M FY24 717.

  11. Slide 11: Q3 FY24 Standalone Results Highlights

    Q3 FY24 Standalone Results Highlights In ₹ Mn Particular Q3 FY24 Q3 FY23 Y-O-Y % 9M FY24 9M FY23 Y-O-Y % FY23 Revenue from Operations 10,523.09 9,293.89 13.23% 31,551.18 26,249.43 20.20% 38,171.26 Expenses 9,075.69 7,986.77 27,225.89 22,604.68 32,766.48 Operating EBITDA 1,447.40 1,307.12 10.73% 4,32

  12. Slide 12: Standalone Balance Sheet

    Standalone Balance Sheet In ₹ Mn Assets FY20 FY21 FY22 FY23 Sept - 23 Non Current Assets Fixed Assets 3,118.66 3,655.61 10,753.88 11,973.83 11,902.25 Non Current Investments 6,692.17 6,539.91 2,578.15 2,256.91 2,365.08 Other Non Current Financial Assets 15,446.71 15,083.23 16,318.93 15,220.74 15,476

  13. Slide 13: Standalone Balance Sheet

    Standalone Balance Sheet In ₹ Mn Equities & Liabilities FY20 FY21 FY22 FY23 Sept - 23 Equity 408.18 465.45 479.23 773.62 773.62 Reserves 25,292.65 24,458.04 23,046.11 27,803.89 29,524.11 Net Worth 25,700.83 24,923.49 23,525.34 28,577.51 30,297.73 Non-current Liabilities Long-term Borrowing 6,279.64

  14. Slide 14: Consolidated Results Highlights

    Consolidated Results Highlights Quarterly & Nine Month Revenue Performance in ₹ Quarterly & Nine Month Op. EBITDA and Net Profit Million Performance in ₹ Million 32,009.29 4,527.18 3,926.11 26,860.83 10,610.05 1,407.29 Investor Presentation Q3 FY24 9,546.30 1,401.35 1,420.88 702.43 704.40 194.82 Q3

  15. Slide 15: Q3 FY24 Consolidated Results Highlights

    Q3 FY24 Consolidated Results Highlights In ₹ Mn Particular Q3 FY24 Q3 FY23 Y-O-Y % 9M FY24 9M FY23 Y-O-Y % FY23 Revenue from Operations 10,610.05 9,546.30 11.14% 32,009.29 26,860.83 19.17% 38,911.47 Expenses 9,189.17 8,144.95 27,482.11 22,934.72 33,295.82 Operating EBITDA 1,420.88 1,401.35 1.39% 4,5

  16. Slide 16: Consolidated Balance Sheet

    Consolidated Balance Sheet In ₹ Mn Assets FY20 FY21 FY22 FY23 Sept - 23 Non Current Assets Fixed Assets 17,480.77 13,611.47 14,631.43 15,255.89 15,228.94 Non Current Investments 789.75 678.90 816.08 1,354.12 1,255.98 Other Non Current Financial Assets 6,201.10 6,492.59 11,428.32 10,661.48 10,515.44

  17. Slide 17: Consolidated Balance Sheet

    Consolidated Balance Sheet In ₹ Mn Equities & Liabilities FY20 FY21 FY22 FY23 Sept - 23 Equity 408.17 465.45 479.23 773.62 773.62 Reserves 25,061.78 22,730.21 23,357.76 28,105.94 28,753.77 Net Worth 25,469.95 23,195.66 23,836.99 28,879.56 29,527.39 Minority Interest 330.98 612.90 714.11 878.20 -72.6

  18. Slide 18: Consolidated Debt Highlight

    Consolidated Debt Highlight In ₹ Mn In ₹ Mn In ₹ Mn BG / LC Charges & Other Borrowing Cost Term Debt Working Capital Debt Total Debt Non - Current Current Total Contractee Advance Interest on Contractee Advances Interest to Lenders 12,660.70 21,630.03 Total Finance Cost 19,658.93 1,053.26 5,159.83 1

  19. Slide 19: Q3 FY24 Operational Highlights

    Q3 FY24 Operational Highlights

  20. Slide 20: L1 Projects in Q3 FY24

    Project Name: Project Name: Nira Deoghar Right Bank Nira Deoghar Right Bank Main Canal Km 66 to Km 76 Main Canal Km 77 to Km 87 Project Location: Project Location: Maharashtra Maharashtra L1 Projects in Q3 FY24. Client: LOA Received in Client: Maharashtra Krishna Valley Maharashtra Krishna Valley De

  21. Slide 21: Q3 FY24 Highlights Update

    Best CFO of the Year award Sela pass Company is delighted to The Sela Pass Tunnel Project is the World's Longest Bi-Lane Tunnel at Q3 FY24 Highlights Update announce and commemorate the an altitude of ~ 13,000 Feet located in Arunachal Pradesh. All the works outstanding accomplishment of have been c

  22. Slide 22: Order Book Highlights

    Since 1949 = rS A, Ordér Book Highlights

  23. Slide 23: Yearly Growth In Order Book

    Yearly Growth In Order Book Yearly Order Book 2,08,067 1,91,347* 1,44,660 1,50,110 1,31,840 1,02,150 Investor Presentation Q3 FY24 FY19 FY20 FY21 FY22 FY23 Q3 FY24 *Q3 FY24 Includes Two Projects which is L1 amounting to ₹ 1,745 Mn converted to LOA in Q4 FY24. 22

  24. Slide 24: Order Book Break Up

    Order Book Break Up In % Segment Wise Order Book Client Wise Order Book Project Completion Wise Order Book 4.27% 1.36% 2.99% Hydroelectric 3.31% 5.47% Below 10% Central 11.02% Irrigation Government / 13.47% 10% - 30% PSU’s 38.99% 34.98% 30% - 50% Tunnel 10.38% State Government 50% - 70% 21.05% Depar

  25. Slide 25: Diversly Spread Works De-Risking Business

    Diversly Spread Works De Risking Business Jammu and Kashmir No. of Sr.No. State Project Value Projects Himachal Pradesh 1 Jammu and Kashmir 7 59,218 2 Madhya Pradesh 9 32,381 3 Himachal Pradesh 3 18,289 Arunachal Sikkim Pradesh 4 Maharashtra 12 17,738 Nepal 5 Arunachal Pradesh 2 18,316 Assam 6 Sikki

  26. Slide 26: Major Project Under Execution

    Hydro Power / Tunnelling Irrigation Transportation Urban Infrastructure o Subansiri HEP (2,000 MW) o Sleemanabad Carrier Canal o Shivane to Mhatre bridge o Amarmahal to Trombay Tunnel o IRCON T15 (Railway Tunnel) o Morand & Ganjal Dam o Selapass Road and Tunnel o Hindoli - Nainwa Water Supply Projec

  27. Slide 27: Strong Client Base – Some Major Clients

    Strong Client Base – Some Major Clients Investor Presentation Q3 FY24 26

  28. Slide 28: Our Major Achievements

    Recipient of many national and international awards First Double lake tapping in Asia – Koyna Project More than 4,000 m Largest surge shaft Largest underground shaft boring in Asia – 38 m dia – power house cavern – completed Rampur Project Srisailam HE Project More than 300 Commissioned more Our Maj

  29. Slide 29: Major completed projects - Hydro Power / Tunneling

    Major completed projects - Hydro Power / Tunneling Tuirial Hydro Electro Project Mizoram Parbati Hydro Electro Project (800 MW) USBRL - T2 (60 MW) Investor Presentation Q3 FY24 o Srisailam Left Bank Hydro Power Station (900 MW) o Kameng HEP (600 MW) o Teesta Hydro Electro Project Stage V (510 MW) o

  30. Slide 30: Major completed projects - Irrigation

    Major completed projects - Irrigation Kalwakurty Lift Irrigation Project, Andhra Pradesh PLGC Canal, Uttar Pradesh Investor Presentation Q3 FY24 o Polavaram Project (Right Main Canal), Andhra Pradesh o Indira Sagar Project, Andhra Pradesh o Jawahar Lift Irrigation Project , Andhra Pradesh o Vamsudha

  31. Slide 31: Major completed projects - Transportation

    Major completed projects - Transportation Krishnagiri - Vaniyambadi NH-46, Tamil Nadu 4 laning NH-7 from Madurai to Kanyakumari, Tamilnadu Investor Presentation Q3 FY24 o Hathipali - Hosur (NH-7), Tamil Nadu o Road from Ramwadi to New PMC Limit under JNNURM Project o Nellore - Kaveli NH-5, Andhra Pr

  32. Slide 32: Major completed projects - Urban Infrastructure

    Major completed projects - Urban Infrastructure BYTCO Hospital Mantalia Parliament Building Bhutan Investor Presentation Q3 FY24 o Construction of various water tunneling projects, Maharashtra o Microtunneling & Pipe Jacking for Water Supply & Sewerage, Maharashtra o Dam for Shillong Water Supply, M

  33. Slide 33: Few Landmark Projects That Set Us Apart

    Few Landmark Projects That Set Us Apart Ghatghar Dam – Maharashtra 84m high Koyna HE Project - Maharashtra (260MW) 10th fastest completed dam in the world an India’s first RCC Dam First Lake Tapping in Asia. Investor Presentation Q3 FY24 Srisailam HE Project - Andhra Pradesh (900MW) Sawrakuddu HE Pr

  34. Slide 34: Technology Oriented

    Micro-tunneling First RCC o Micro-tunneling is the only non invasive Dam in India solution for urban areas First Lake o We are one of the largest Micro-tunneling Contractors Tapping in Asia Asia's largest Double Lake Tap Surge Shaft with a dia of 38 m o A unique technology for connecting water to po

  35. Slide 35: Technology Oriented

    New Austrian Tunnelling Method (NATM) Application of Finite Element Method (FEM) Use of Non – technique Destructive Testing Method for assessment of Technology Oriented geological Earth Pressure formation and Balancing material testing Tunnel Boring Machine (TBM) Use of steel Fibre for tunnelling Re

  36. Slide 36: Technology Oriented: Concrete Tower Belt System

    Technology Oriented Concrete Tower Belt System The implementation of the Tower Belt System, a conveyor belt concreting system, was a remarkable technological advancement carried out at the Kiru Hydroelectric Project. This system, powered by electricity, plays a crucial role in transporting aggregate

  37. Slide 37: Industry Overview

    Industry Overview

  38. Slide 38: Hydropower Overview

    Hydro Power – a keen effort taken by the government to boost energy generation — Hydropower supplies at least 50% of electricity production in 66 countries and at least 90% in 24 countries. — India has overtaken Japan, becoming the nation with the fifth-largest hydropower production capacity in the

  39. Slide 39: Hydro Pumped Storage

    Hydro Pumped Storage 39 Hydro PSPs of 47 GW are being pursued to be commissioned by the year 2029-30. Hydro Pumped Storage Projects are necessary to achieve Government of India’s commitment of 500 GW installed capacity from non-fossil fuel sources by the year 2030 and Net Zero carbon emissions by th

  40. Slide 40: Power Industry Overview

    Power Industry Overview The Ministry of Power has made significant efforts over the past few years to turn the country from one with a power shortage to one with a surplus by establishing a single national grid, FDI in India’s renewable fortifying the distribution network, and achieving Investment B

  41. Slide 41: Micro Irrigation The Way Forward

    Micro Irrigation The Way Forward Importance of Micro Irrigation Micro Irrigation in India Government Initiative o Micro-irrigation increases water efficiency as o In India, the average penetration of micro o The government started micro irrigation in the much as 50%-90%. irrigation is 19% (as of Feb

  42. Slide 42: Management Overview

    Management Overview

  43. Slide 43: Professional & Experienced Board Of Directors

    Professional & Experienced Board Of Rupen Patel Kavita Shirvaikar Tirth Nath Singh Chairman & Managing Whole Time Director & CFO Whole Time Director- Projects & Directors Director Corporate Affairs Investor Presentation Q3 FY24 K. Ramasubramanian Sunanda Rajendran Shambhu Singh Ashwin Parmar Indepen

  44. Slide 44: Core Management Team

    Core Management Team Mr. Rupen Patel Promoter, Chairman & Managing Director A third generation entrepreneur, Mr. Rupen Patel, holds an MBA from Babson College, USA. He began his career as an Advisor to the Board of Patel Engineering Limited in 1993. Appointed as Executive Director in 1996, he was el

  45. Slide 45: Core Management Team

    Core Management Team Mrs. Kavita Shirvaikar Whole Time Director & CFO A qualified Chartered Accountant and a Graduate of the Institute of Cost & Works Accountants of India, Ms. Kavita Shirvaikar, who specializes in accounting, tax, audit, banking, finance, and fund management, has completed difficul

  46. Slide 46: The Way Forward

    ee may rs sees a 1 eee Patal Since 1949

  47. Slide 47: Monetization of Non-Core Assets: Sale of Land Bank & Arbitration Awards

    Monetization of Non-Core Assets: Sale of Land Bank & Arbitration Awards Total Available Land Bank Balance Land Approximate Value ~ 2,150 Acres. Bank Details ₹ ~ 10,000 Mn Details Some Of The Major Land Parcels State / City Locality Available Area Karnataka, Bangalore Electronic City ~ 15 acres Mahar

  48. Slide 48: Future Growth Drivers

    Future Growth Drivers Over the past few Reduction of Debt / Infrastructure years the company EBITDA which shall development is prime has monetized non help in improving focus of GOI which has core asset for profitability been continued in the reduction of debt FY25 interim budget which it will conti

  49. Slide 49: Investment Highlights

    A leading player in the hydroelectric space, with a Strong experience and reputation in the track record of participating in some of India's most infrastructure space for over 74 years. prestigious and strategically significant projects. The government's focus on hydroelectric Our focus on niche seg

  50. Slide 50: Thank You

    Thank You Patel Engineering Limited Contact: Rahul Agarwal Phone: +91 22 2676 7500 Website: www.pateleng.com E-mail: investors@pateleng.com Kirin Advisors Private Limited Contact: Vastupal Shah Phone: +91 22 4100 2455 Website: www.kirinadvisors.com E-mail: vastupal@kirinadvisors.com