Slide 1: Yorbeau Resources Inc December 2018
YORBEAU RESOURCES INC december 2018

Slide 2: Properties in world class mining region
Properties in world class mining region X X

Slide 3: Four projects hosting a mineral deposit
Four projects hosting a mineral deposit ! 1. Rouyn • Project optioned to IAMGOLD • Resources of 500,000 ounces of gold (NI 43-101) • Potential of more than 2 million ounces 2. Scott Lake • Resources of 17,8 millions tonnes (NI 43-101) 3. Joutel (Explo Zinc) • Resources of 861,000 tonnes (NI 43-101)

Slide 4: Rouyn Project on Cadillac Break, Rouyn-Noranda
ROUYN PROJECT ON CADILLAC BREAK, Rouyn-Noranda Infrastructures Augmitto

Slide 5: Rouyn property (view northeast)
Rouyn property (view northeast) Rouyn-Noranda Astoria Astoria Lac Gamble Cinderalla Lac Gamble Cinderella Augmitto Augmitto

Slide 6: Regional Geology & Historic Production
Regional Geology & Historic Production

Slide 7: Rouyn Property map
Rouyn Property map • 12 km segment of Cadillac Break • Proximity of past gold producers

Slide 8: Rouyn Project: Agreement with IAMGOLD
Rouyn Project: Agreement with IAMGOLD 1. Cash payment to Yorbeau of C$1 million on signing 2. Additional cash payments totalling C$3 million from year 2 to year 4 3. Expenditures of C$9 million over 4 years • Includes 20,000 m of diamond drilling within first 2 years 4. Resource estimate done with p

Slide 9: Resources (NI 43-101 compliant) 2011
Resources (NI 43-101 compliant) 2011 TOTAL (oz) M&I: 286,214 Inf. : 211,536 Does not include drilling at Cinderella, Lac Gamble, 2017 drilling

Slide 10: Augmitto: Cinderella, Astoria, East-Bay
AUGMITTO: CINDERELLA ___ ASTORIA (| EAST-BAY {) bag ; > - . 3 6 400E 9 800 9 YORBEAU RESOURCES INC

Slide 11: Estimate of Potential for Astoria + Lac Gamble (40m)
Estimate of « Potential » for Astoria + Lac Gamble (summary) Potential* (cut-off: 3.4 g/t Au) maximum hole influence of 40m tonnes grade (g/t Au) ounces of gold Lac Gamble 1.0-1.4 Mt 7.2-8.8 0.3-0.4 Moz Astoria 2.9-3.6 Mt 6.1-7.4 0.6-0.9 Moz Total Gamble + Astoria 4.1 – 5.0 Mt 6.4 – 7.8 0.8 – 1.3 Mo

Slide 12: Estimate of Potential for Astoria + Lac Gamble (75m)
Estimate of « Potential » for Astoria + Lac Gamble (summary) Potential* (cut-off: 3.4 g/t Au) maximum hole influence of 75m tonnes grade (g/t Au) Ounces of gold Lac Gamble 1.7-2.0 Mt 7.7-8.5 0.4-0.6 Astoria 4.0-5.0 Mt 6.6-7.4 0.9-1.2 Total Gamble + Astoria 6.0 – 7.0Mt 6.3 – 7.7 1.2 – 1.7 Moz * Subje

Slide 13: Potential as a function of drill hole influence
Potential as a function of drill hole influence (40m and 75m) 1000 mètres Influence 40m : 0.8-1.3 Moz gold Influence 75m : 1.2-1.7 Moz gold

Slide 14: After a century, the Cadillac Break continues to deliver gold
After more than a century of production, the Cadillac Break continues to deliver gold! • Over 24,000 metres drilled by Kinross in 2017 • « Potential » up to 1.7 Moz Au for Gamble and Astoria • Resources of 48,200 oz (M+Ind) plus 159,000 (Inf.) at Augmitto • Agreement with IAMGOLD (producer with oper

Slide 15: Scott Project – looking North-West
Scott Project – looking North-West

Slide 16: Chibougamau Mining Camp
CHIBOUGAMAU MINING CAMP _Chapais i — s ~ ad si -" “== 1.2 B lbs copper 0.8 Moz gold j 9 ; Lemoine Mine Legend te _< il i phere roe : F 4 4.2% Cu, 9.8% Zn ( , D | | EnereHive horizon tae } , Sf 4,2g/t Au, 83g/t Ag |_| CHES SEE Cones knlometres: to ays, } f~ Lac Doré Complex St. Felicien \\ ~_—s Cait

Slide 17: 3D Isometric View of Scott Lake Wireframes
3D Isometric View of Scott Lake Wireframes Looking Northeast «“g00" ; CFO | Scott Lake Rhyolite Ss RPA ree Cometh eps

Slide 18: Mineral Resources - Scott
Mineral Resources * - Scott Category Tonnes %Cu %Zn g/t Au g/t Ag Indicated 3,567,000 0.95 4.17 0.2 37 Inferred 14,281,000 0.78 3.49 0.2 22 Total 17,847,000 0.8 3.6 0.2 25 * 2017, in accordance with NI 43-101 Technical Report

Slide 19: Metallurgical tests completed in 2017
Metallurgical tests Copper concentrate completed in 2017 85% recovery in 25% Cu conc. Zinc concentrate 87% recovery in 55% Zn conc.

Slide 20: Scott Lake Project - EW Section mining development
Scott Lake Project- EW Section mining development

Slide 21: High potential to increase resources
High potential to increase resources!!!

Slide 22: Étude Économique Préliminaire – Sommaire
Étude Économique Préliminaire – Sommaire Zn: $US1.30/lb - Cu: $US3.50/lb - $C1.00=$US0.80 Ventes Nettes (NSR) $1.98 milliard Flux de trésorerie Flux avant impôt de $519.2 million TRI TRI avant impôt de 16.5% avec période de recouvrement de 6 ans Valeur Actuelle Nette VAN(8%) avant impôt de $

Slide 23: Preliminary Economic Assessment - Details
Preliminary Economic Assessment - Details Operating costs Pre-production capital costs ($/t milled) $(millions) Mining 54.14 Mining 52.58 Processing 27.49 Processing 60.00 General & Administration 7.40 Infrastructure 15.78 TOTAL 89.02 Tailings 4.65 Sub Total 133.01 EPCM* 46.55 Contingency 35.92 TOTA

Slide 24: Preliminary Economic Assessment - Details: peak annual production
Preliminary Economic Assessment - Details Peak annual production Peak period Average (per year) Zinc concentrate 72,400 tonnes years 9-12 Zinc metal (payable) 75 million pounds Copper concentrate 28,467 tonnes Copper metal (payable) years 5-8 15 million pounds Silver metal (payable) 395,835 ounces

Slide 25: Low cash cost zinc producer (net of by-products)
Low cash cost zinc producer (net of by-products) millions $ Cdn pounds of payable zinc 810.9 $/lb payable zinc mining 650.9 0.80 $ processing 330.5 0.41 $ G&A 85.6 0.11 $ Treatment (Zn conc.) 177.0 0.22 $ Transport (Zn conc.) 47.0 0.06 $ total operating 1,291.0 1.59 $ Cu credits 673.5 0.83 $ Ag cred

Slide 26: Next steps – Scott Project
Next steps* – Scott Project * Subject to financing Phase 1: $30 millions – Underground exploration • Duration 24 months • Excavation of ramp and drill stations (3,000 metres of developpement) • 15,000 metres of underround drilling • 4,400 metres of surface driling (including exploration west of Gwil

Slide 27: Estrades-Caribou
Estrades- Caribou i] er | ORVILLIERS Twp. SELBAIE MINE ] s ESTRADES MINE } i « Total Production + resources : H 5 884 118 t @ 0.9% Cu, 10.4% Zn, 1} | 5.5 g/t Au & 165 g/t Ag iN t CARIBOU DEPOSIT RAYMOND Two} PUISEAUX Tp. CASA-BERARDI | ESTREES Tp. Twp. \ et ESTRADES MINE SITE ACCESS ROAD CASA BERARD

Slide 28: Caribou Project
Caribou Project average 10 holes 2.8% Cu, 6.9% Zn, 1.1 g/t Au, 53 g/t Ag over 1.8 m

Slide 29: Caribou Project
Caribou Project Drilling program 2018 • One hole (CAR-36W) • 3.7m @ 2.2% Cu, 1.5% Zn, 36 g/t Ag • Conductor (borehole PEM) to the east

Slide 30: Joutel (Explo Zinc)
Joutel (Explo Zinc) Conductor! Next steps • Field mapping to confirm structuraI interpretation • Drilling (with partner SOQUEM)

Slide 31: Drilling targets - Joutel
Drilling targets - Joutel category tonnes % Zinc % Copper indicated 587,961 7.6 0.35 inferred 273,485 6.6 0.21 Total 861,446 7.3 0.3

Slide 32: Projet KB
Projet KB • Showing of zinc-copper-gold-silver • Average of 4 grab samples of massive sulphides : 1.4% Cu, 9.2% Zn, 56 g/t Ag and 2.2 g/t Au. (Incl. 8.25 g/t Au !) • drilling (1965): 1.9% Cu and 11.0% Zn over 1.0 metre

Slide 33: KB Project
KB Project outcropping massive sulphides… Airborne VTEM survey • Completed • Anomalies under evaluation

Slide 34: Airborne VTEM Survey – KB Project
AIRBORNE VTEM SURVEY – KB PROJECT 1.4% Cu, 9.2% Zn, 56 g/t Ag and 2.2 g/t Au 0 Km 1

Slide 35: What's next?
What’s next ? • Scott • Marketing and unlocking value • Partnership?, spin-off?, etc. • Phase 1 – underground exploration and feasibility study • Phase 2 - construction • Rouyn: Drilling to start in January 2019 with IAMGOLD • JOUTEL (zinc): drilling in 2019 (partner with SOQUEM) • KB: Diamond drill

Slide 36: Steps to success!
Steps to success! Technical studies production Drilling and discovery

Slide 37: Merci! Thank you!
Source: Internet Archive copy of yorbeauresources.com
More decks from Yorbeau Resources, Inc. Class A
Investor Presentation (April 2018)43 slides · April 2018
Investor Presentation (April 2018)37 slides · April 2018
Investor Presentation (November 2017)42 slides · November 2017
Investor Presentation (October 2014)29 slides · October 2014
Investor Presentation (June 2014)22 slides · June 2014
Investor Presentation (September 2012)22 slides · September 2012