Royal Bafokeng Platinum Ltd

Royal Bafokeng Platinum — Corporate Update (November 2013)

44 slides from Royal Bafokeng Platinum's corporate update, Nov 27, 2013

  1. Slide 1: RBPlat Investor and Analyst Site Visit

    Slide 1: RBPlat Investor and Analyst Site Visit

    RBPlat Investor and Analyst Site Visit 27 November 2013 RBPlat Investor and Analyst Site Visit – 27 November 2013

  2. Slide 2: Disclaimer

    Slide 2: Disclaimer

    Disclaimer The information presented in this presentation is of a general nature and the forward looking information, opinions and beliefs of the Company and its affiliates are based on various market related assumptions. Changes in market circumstances after the production of the information may im

  3. Slide 3: Introduction

    Slide 3: Introduction

    Introduction > Geological overview > Operational review • Continued improvement in safety performance • Steady ounce production • Below inflation unit cost increase during 2013 • Healthy pre-developed ore reserves position • Replacement and SIB project expenditure in line with project execution • St

  4. Slide 4: Geological overview

    Slide 4: Geological overview

    Geological overview

  5. Slide 5: Bafokeng Rasimone Platinum Mine JV - locality

    Slide 5: Bafokeng Rasimone Platinum Mine JV - locality

    Bafokeng Rasimone Platinum Mine JV - locality Styldrift II# Styldrift I# RBPlat Investor and Analyst Site Visit – 27 November 2013 > Slide 5

  6. Slide 6: Geological setting

    Slide 6: Geological setting

    Geological setting > Exploiting Merensky and UG2 Reefs in the Western Bushveld Complex > Ore body avg. 12°dip NE (SD1 ~ 4°) RBPlat Investor and Analyst Site Visit – 27 November 2013 > Slide 6

  7. Slide 7: BRPM Resources & Reserves Dec 2012

    Slide 7: BRPM Resources & Reserves Dec 2012

    BRPM Resources & Reserves Dec 2012 67% attributable interest Resources inclusive of Reserves Tonnes 4E Grade Contained 4E Reef Resource classification (Mt) (g/t) (Moz) Measured 10 7.58 2.4 Merensky Indicated 5 6.97 1.2 Inferred 5 8.03 1.4 Total 20 7.54 5.0 Measured 30 5.40 5.1 UG2 Indicated 11 4.82

  8. Slide 8: Styldrift Resources & Reserves Dec 2012

    Slide 8: Styldrift Resources & Reserves Dec 2012

    Styldrift Resources & Reserves Dec 2012 67% attributable interest Resources Inclusive of Reserves Tonnes 4E Grade Contained 4E Reef Resource classification (Mt) (g/t) (Moz) Measured 38 7.47 9.2 Merensky Indicated 34 6.98 7.7 Inferred 16 7.72 3.9 Total 88 7.33 20.8 Measured 22 5.20 3.7 UG2 Indicated

  9. Slide 9: RBPlat Resources & Reserves Dec 2012

    Slide 9: RBPlat Resources & Reserves Dec 2012

    RBPlat Resources & Reserves Dec 2012 67% attributable interest Resources Inclusive of Reserves Tonnes 4E Grade Contained 4E Reef Resource classification (Mt) (g/t) (Moz) Measured 49 7.49 11.7 Merensky Indicated 39 6.98 8.8 Inferred 21 7.80 5.2 Total 109 7.37 25.7 Measured 51 5.31 8.8 UG2 Indicated 5

  10. Slide 10: RBPlat Resources & Reserves Dec 2012 continued

    Slide 10: RBPlat Resources & Reserves Dec 2012 continued

    RBPlat Resources & Reserves Dec 2012……continued Resources classification Merensky Reef Reserves classification UG2 Reef RBPlat Investor and Analyst Site Visit – 27 November 2013 > Slide 10

  11. Slide 11: Styldrift II project area

    Slide 11: Styldrift II project area

    Resource optimization Styldrift II 66.84 > Potential size of investment similar to 70.00 Styldrift I 49.51 60.00 50.00 Pre-feasibility 23.99 > 21.60 40.00 23.11 14.57 • Initiated in November 2012 16.25 30.00 7.56 • Completion planned for H2 2014 20.00 10.71 6.73 10.00 > Styldrift II project area 0.0

  12. Slide 12: Operational performance

    Slide 12: Operational performance

    Operational performance

  13. Slide 13: BRPM safety performance – ongoing improvement

    Slide 13: BRPM safety performance – ongoing improvement

    BRPM safety performance – ongoing improvement Description Unit YTD Q3 2012 YTD Q3 2013 Variance LTIFR /200 000 0.57 0.51 10% SIFR /200 000 0.32 0.22 32% > Achieved 2.0 million fatality free shifts (2nd April SIFR LTIFR 2013) 0.45 0.43 1.20 0.40 > Improved LTIFR and SIFR (YoY) 0.40 0.37 1.00 1.00 • L

  14. Slide 14: Production performance

    Slide 14: Production performance

    Production performance Description Unit YTD Q3 2012 YTD Q3 2013 Variance > Concentrator offline for 15 days Total tonnes milled kt 1 760 1 634 -7% • Primary mill discharge end replacement UG2 % milled % 15.1% 18.6% 23% Surface stockpiles kt 97 135 39% • 7% lower milled tonnes Headgrade (4E) – Total

  15. Slide 15: Cash operating costs

    Slide 15: Cash operating costs

    Cash operating costs Description Unit YTD Q3 2012 YTD Q3 2013 Variance Cash operating cost / Pt oz delivered R/oz 9 807 10 179 -4% Cash operating cost / tonne milled R/t 859 948 -10% Cash operating cost / Pt oz M&C R/oz 11 805 12 205 -3% Cash operating cost / 4E oz M&C R/oz 7 650 7 913 -3% > Increas

  16. Slide 16: Capital expenditure

    Slide 16: Capital expenditure

    Capital expenditure Description Unit YTD Q3 2012 YTD Q3 2013 Variance Total capital R'm 904.0 720.9 20% Expansion R'm 489.9 504.0 -3% Replacement R'm 225.4 127.0 44% SIB capital R'm 188.7 89.9 52% SIB / Operating Cost % % 12.5% 5.8% 54% > Lower capital expenditure (20% or R183 million) aligned with

  17. Slide 17: Social and Labour

    Slide 17: Social and Labour

    Social and Labour > Employee and organised labour engagement > Community engagement > SLP commitments • Poverty alleviation & job creation • Education support • Infrastructure Housing project Sports fields in 5 local schools Chaneng community vegetable garden RBPlat Investor and Analyst Site Visit –

  18. Slide 18: Styldrift I

    Slide 18: Styldrift I

    Styldrift I

  19. Slide 19: Styldrift safety performance

    Slide 19: Styldrift safety performance

    Styldrift safety performance Description Unit YTD Q3 2012 YTD Q3 2013 Variance LTIFR /200 000 1.51 1.59 5% SIFR /200 000 0.84 0.84 0% > Styldrift Project 1000 fatality free days (14 Aug SIFR LTIFR 2013) 1.20 1.80 1.68 1.05 1.49 > Project activities and associated risk profile have 1.60 1.00 changed

  20. Slide 20: Major surface activities completed

    Slide 20: Major surface activities completed

    Major surface activities completed • Permanent headgears erected • Personnel and material winder - commissioned • Rock winder – commisioned • Central workshops – completed • Main consumer substation – commissioned • Emergency generators – commissioned RBPlat Investor and Analyst Site Visit – 27 Nove

  21. Slide 21: Styldrift on schedule and below budget

    Slide 21: Styldrift on schedule and below budget

    Styldrift on schedule and below budget Description Unit Plan Actual Var Progress Progress > Service shaft sink to 642 level Overall progress % 33.7 34.6 0.9 Main shaft sinking m 708 708 - > Main shaft sink to 708 level Service shaft sinking m 642 642 - Expenditure > 1730m of lateral development comp

  22. Slide 22: Milestones

    Slide 22: Milestones

    Milestones Current Description COS 2 Actual forecast Activity 2013 Services shaft: Sink to 642 L Jan – 13 Jan - 13 - Main shaft: Sink to 642 L Jan – 13 Jan - 13 - Commence rock winder installation Feb - 13 Feb - 13 - Main shaft: Sink to 708 L Apr – 13 Apr – 13 - Commence change house construction Ju

  23. Slide 23: Styldrift schedule & cash flow

    Slide 23: Styldrift schedule & cash flow

    Styldrift schedule & cash flow Project Phase 2008 2009 2010 2011 2012 2013 2014 2015 2016 2017 2018 2019 Engineering & Design 2008 - 2015 Pre-Sink Infrastructure 2009 - 2011 • Rock winder Surface Infrastructure 2010 - 2016 • Main offices • Change house Main Shaft Sinking 2011 - 2014 708m • Surface s

  24. Slide 24: Styldrift key issues

    Slide 24: Styldrift key issues

    Styldrift key issues > Primary trackless mining fleet • Supplier selected • Contract for manufacturing of primary fleet placed in Q1 2013 • Fleet delivery planned in advance of ramp-up schedule • Artisan and operator training programs initiated > Mining contract • Preferred mining contractor selecte

  25. Slide 25: Ore processing strategy

    Slide 25: Ore processing strategy

    Ore processing strategy

  26. Slide 26: Strategic considerations

    Slide 26: Strategic considerations

    Strategic considerations Market conditions > Global economic slowdown > Metals prices remain relatively flat in near term > Recycling of PGMs set to grow > Operating cost escalation UG2 > Central high facies – North shaft: robust operating margins > General facies – South shaft: low operating margin

  27. Slide 27: Styldrift concentrator (230ktpm)

    Slide 27: Styldrift concentrator (230ktpm)

    Styldrift concentrator (230ktpm) Key design parameters Two stage crushing circuit > Primary and secondary crushing in close circuit Milling and classification > 2 x 8 MW mills (MF2 configuration) > 150g/t concentrate grade Flotation > Primary rougher, cleaner and re-cleaner circuits > Secondary roug

  28. Slide 28: Anglo Platinum ore transport options

    Slide 28: Anglo Platinum ore transport options

    Anglo Platinum ore transport options Transnet rail > Conveyor linking Styldrift with Transnet line > New rail siding south of Styldrift > 4 x 50 hopper train on Transnet network daily > Maintenance workshop for rolling stock > Rail link and rail siding between Transnet and Anglo rail network > Shunt

  29. Slide 29: Impala ore transport options

    Slide 29: Impala ore transport options

    Impala ore transport options Ore transport options 1. Conveyor: Styldrift to Impala 20 shaft 2. Rail: Impala rail extension to Styldrift 3. Road: Road train from Styldrift to Impala 20 shaft 4. Doppelmayr: Two flight from Styldrift to Impala 20 shaft 5. Hybrid: Combination of conveyor and rail to Im

  30. Slide 30: Impala ore transport options (continued)

    Slide 30: Impala ore transport options (continued)

    Impala ore transport options (continued) Capital (R’m) Option Description Opex (R/t) System ready nominal Conveyor with new rail siding 1. Conveyor and silo position east of Impala 846 40 Q4 2016 20 shaft New rail system linking into the 2. Rail existing Impala rail system east 958 35 Q1 2017 of Imp

  31. Slide 31: Styldrift/Wesizwe joint concentrator

    Slide 31: Styldrift/Wesizwe joint concentrator

    Styldrift/Wesizwe joint concentrator Joint concentrator location Two stage crushing circuit > Primary and secondary crushing in closed circuit > Milling and classification (MF2 configuration) 280ktpm and 180ktpm modules RoM conveyor from Wesizwe Description Units Module 1 Module 2 Silo for Wesizwe o

  32. Slide 32: Concentrator project schedules

    Slide 32: Concentrator project schedules

    Concentrator project schedules Start Finish 2012 2013 2014 2015 2016 2017 2018 Activity date date Q2 Q3 Q4 Q1 Q2 Q3 Q4 Q1 Q2 Q3 Q4 Q1 Q2 Q3 Q4 Q1 Q2 Q3 Q4 Q1 Q2 Q3 Q4 Q1 Q2 Q3 Q4 Styldrift I concentrator (230ktpm) Feasibility study Q2 2012 Q4 2013 Execution & commissioning Q3 2014 Q3 2016 Anglo Amer

  33. Slide 33: Key outcomes of treatment of ore at neighbouring mines

    Slide 33: Key outcomes of treatment of ore at neighbouring mines

    Key outcomes of treatment of ore at neighbouring mines > Capital requirements to deliver Styldrift ore to neighbouring mines is significant • R750 million to R1.4 billion (excluding Impala concentrator plant upgrade) • Increases treatment cost per tonne by between R35/t to R55/t > No added value as

  34. Slide 34: Upgrade BRPM concentrator (350ktpm)

    Slide 34: Upgrade BRPM concentrator (350ktpm)

    Upgrade BRPM concentrator (350ktpm) Overland conveyor Styldrift to BRPM > 6 km of overland conveyor > Primary crushing at Styldrift 200ktpm to 250ktpm upgrade > 10 kt silo (storage of ROM Merensky) > Primary mill conversion (to grate discharge) > Upgrade of the existing LAROX filter building > Prima

  35. Slide 35: Tonnage and treatment profile of upgraded BRPM concentrator

    Slide 35: Tonnage and treatment profile of upgraded BRPM concentrator

    Tonnage and treatment profile of upgraded BRPM concentrator Tonnage profile (2014-2018) 5.0 Concentrator capacity appropriate for Merensky 4.5 production 4.0 UG2 production provides flexibility Deliver UG2 to fill shaft capacity Million tonnes per annum > 3.5 > Toll treat excess UG2 3.0 2017: Commis

  36. Slide 36: Key outcomes

    Slide 36: Key outcomes

    Key outcomes Description Unit Standalone 230ktpm concentrator BRPM concentrator upgrade BRPM concentrator upgrade to co-process UG2 R’m 300 - Blending facility for UG2 at BRPM R’m 50 - Styldrift I concentrator R’m 2400 - Conveyor from Styldrift to BRPM R’m - 332 Upgrade BRPM concentrator to 250ktpm

  37. Slide 37: Styldrift revised capital

    Slide 37: Styldrift revised capital

    Styldrift revised capital Description Unit Optimised Current Variance > Revised capital cost Total (mining and concentrating) R'm 11 386 11 014 372 • Project budget reduced from R 11.38 billion Project schedule to R 11.01 billion Start date Date Mar-08 Mar-08 - • Cash flow in accordance with revised

  38. Slide 38: Styldrift project schedule

    Slide 38: Styldrift project schedule

    Styldrift project schedule Project Progress: Mining & Infrastructure Major surface activities: 2014 > Changehouse and office construction > Stores construction > Reef and waste surface silos > Service water storage tanks Major underground activities: 2014 > Main shaft sinking to shaft bottom (50m) >

  39. Slide 39: RBPlat competitively positioned

    Slide 39: RBPlat competitively positioned

    RBPlat competitively positioned

  40. Slide 40: Competitive position on the industry cost curve

    Slide 40: Competitive position on the industry cost curve

    Competitive position on the industry cost curve J.P. Morgan Cazenove Platinum Industry Break-even Analyser (cash cost + SIB) Mechanised operations Source: J.P. Morgan Cazenove – 25 September 2013 RBPlat Investor and Analyst Site Visit – 27 November 2013 > Slide 40

  41. Slide 41: High quality, shallow Merensky assets

    Slide 41: High quality, shallow Merensky assets

    High quality, shallow Merensky assets 100% 3% 4% 5% 5% 11% 8% 9% 14% 15% 15% 2000 16% MERENSKY (70%) UG2 (30%) 90% 80% 70% Merensky : UG2 % 2012 MERENSKY (30%) UG2 (70%) 60% Source : Chamber of Mines – 21 January 2013, RSA PGM Mining Sector Briefing Note 50% 40% > BRPM JV 30% 20% • Long-term Merensk

  42. Slide 42: Funding requirements

    Slide 42: Funding requirements

    Funding requirements

  43. Slide 43: Spending to grow

    Slide 43: Spending to grow

    Spending to grow R’million Expansion capital > Styldrift I expenditure for 2013 is forecast at R728 million > Conveyor belt linking Styldrift to BRPM concentrator (2014/2015) > BRPM concentrator upgrade to 250ktpm in 2015 > BRPM concentrator 100ktpm module commission in 2017 Replacement capital > Ph

  44. Slide 44: Funding of Styldrift I

    Slide 44: Funding of Styldrift I

    Funding of Styldrift I > R992.1 million cash on hand (BRPM JV R369 million – 67% attributable to RBPlat) - as at end June 2013 > R1 billion unutilised Revolving Credit Facility > R458 million Working Capital Facilities • R152.5m utilised for Eskom, Rehab & Rental Guarantees • R200m utilised for Empl

Source: Internet Archive copy of implats.co.za

More decks from Royal Bafokeng Platinum Ltd