Slide 1: Styldrift Project Progress Update
STYLDRIFT PROJECT 20 PROGRESS UPDATE RBPLAT ANALYST ROUNDTABLE 6 AUGUST 2019 19
Slide 2: At Steady State 2021 vs Where we are (H1 2019)
10.5mØ 6.5mØ 32 14 Equipped 0 Trucking 4 IMS Main# - Services# - 2 Settlers 4 Ore Silos Trackless Stoping Stoping Sections 758m deep 723m deep Workshops Sections Sections 4.30g/t (4E) 320koz pa delivered 230ktpm (4E) grade At Steady State 2021 Where we are (H1 2019) 3.81g/t (4E) 75.6koz 163ktpm deli
Slide 3: Safety, Financial, Operations and Focus Areas
Safety Financial Operations Focus Areas > 1.63 Million > Prudent > Successful transition from > Infrastructure creation contractor to own construction > Crew efficiency > 39.4% i > Steady and mining > 35.1% > > > > > Silo 4 > > Milestones completed with current consistency despite > challenges > > E
Slide 4: 230ktpm Milestone vs Current Production
230KTPM MILESTONE VS CURRENT PRODUCTION Sustainable steady state production at 230ktpm Performance improvement roadmap Area Requirement Q4'19 Q1'20 Q2'20 Q3'20 Q4'20 Q1’21 Area Current Future Comment Reach 5N and 4S All mining crews to be on 12 Operational crews 14 Operational crews Development in t
Slide 5: Crews
Flexibility improvement Description Complete 2019 2020 Date Description Complete 2019 2020 Date 18 2 2 Rock handling Logistics 16 4 4 4 2 2 Temporary Main shaft 14 4 4 4 4 OPC 1,2 Rock hoist 1 12 1 642 Level Y-Leg Man hoist Silo 1 Service shaft Crews 10 4 4 6 8 OPC 3,4 Water pipes
Slide 6: Stoping performance and Infrastructure
Stoping performance Improvement area Description 16 000 Improved efficiency Tipping point at close proximity to the 12 000 when section becomes face tonnes 8 000 equipped Improved tramming fleet efficiency 4 000 Tip to face distance - Capacity to extend conveyor belts Jan Feb Mar Apr May Jun d
Slide 7: Styldrift milled tonnes forecast
Legend Main Shaft Services Shaft Ventilation Mined out up to end of June 2019 Shaft 1,2,3 Remainder of 2019 development Installed conveyor belts at end of June 2019 H2 2019 conveyor belt and ore handling infrastructure 2020 conveyor belt and ore handling infrastructure Section N5 Q1 2021 Section N4
Slide 8: Sections Total Stoping
Sections Total Stoping 12 IMS sections 5 TNA with stoping crews 4 Spare sections 0
Slide 9: Sections Total Stoping
Sections Total Stoping 12 IMS sections 7 TNA with stoping crews 4 Spare sections 0
Slide 10: Sections Total Stoping
Sections Total Stoping 14 IMS sections 18 TNA with stoping crews 0 Spare sections 4