Zecon Bhd. · MYX:ZECON
Zecon Bhd — Investor Presentation (August 2026)
35 slides from Zecon Bhd's investor presentation, August 2026
Slide 1: Kota Petra Green Technology Park (KPGTP)
KOTA PETRA GREEN TECHNOLOGY PARK (KPGTP) 1
Slide 2: Kota Petra Green Technology Park (KPGTP)
KOTA PETRA GREEN TECHNOLOGY PARK (KPGTP) 3,000-Acre KPGTP, Zecon Group’s flagship Green Development Masterplan is aligned with Sarawak Government’s PCDS-2030. KPGTP’s 300MWac Large-Scale Agrivoltaics Solar Farm will generate clean power in support of the State’s Green Energy Agenda. Lower land cost
Slide 3: KPGTP – Ideal Investment Destination
KPGTP – Ideal Investment Destination APPROVED GREEN TECHNOLOGY PARK Managed Industrial Scalability Park ✓ 3,000 ACRES OF LAND ✓ Infrastructure Ready ✓ Support Services ✓ Conducive Environment For Business Growth Economic Zone Clean Energy Status ✓ 100% FOREIGN ✓ Powered by 300MWac OWNERSHIP Large-Sc
Slide 4: KPGTP – Locality Map
KPGTP – Locality Map KPGTP PROPOSED NEW KUCHING INT AIRPORT SITE 4
Slide 5: KPGTP – Connectivity
KPGTP – Connectivity Demak Laut Industrial Park (Existing) 5
Slide 6: Demak Laut Industrial Park and Senari Port
SENARI PORT Demak Laut Industrial Park (Existing) 6
Slide 7: St Pac
St Pac . . 5 ® . Low-Carbon / 2) Chemical Island SANTUBONG £ “ a REEN TECHNOLOGY PARK atin SAMARI We me, = xa Kampung sAsajaya\Ulu Goodale Mans
Slide 8: Integrated Green Industrial & Commercial Precinct
INTEGRATED GREEN INDUSTRIAL & COMMERCIAL PRECINCT Aerospace Hub & Logistics Park Green Tech Hub Urban City Centre Solar Farm Agrivoltaics Mixed Development Enterprise Data Centre Hub Education Hub Hub IMMEDIATE FOCUS GROUP Solar Farm Data Centre Agrivoltaics Hub Hi-Tech Industrial Hub Masterplan Com
Slide 9: Development Timeline & Phasing Strategy
Development Timeline & Phasing Strategy Timeline ‘25 ‘26 ‘27 ‘28 ‘29 ‘30 ‘31 ‘32 ‘33 ‘34 ‘35 ‘36 ‘37 ‘38 ‘39 ‘40 ‘41 ‘42 ‘43 ‘44 ‘45 Phase 1 lays the foundation for Solar Farm Agrivoltaics energy and digital infrastructure. Completion Data Centre Phase 1 of connecting bridge Current Status: Mixed De
Slide 10: Key Economic Impact Assessment - KPGTP
KEY ECONOMIC IMPACT ASSESSMENT - KPGTP In Full Operational Capacity in 2045 • GDP contribution of RM6.4% (2% of Sarawak GDP by 2045) Total GDP contribution of RM11 billion with indirect effect, supply chain and economic spending from additional job creation • Approximately 20,000 Direct Jobs and 50,
Slide 11: KPGTP Masterplan Zoning & Blocking
KPGTP MASTERPLAN ZONING & BLOCKING 11
Slide 12: KPGTP Title Blocking: 3,000 acres
KPGTP Title Blocking Lot Acres Years leasehold 505 210.0 60 (Expires in June 2076) 462 500.4 99 (Expires in June 2098) 464 42.2 99 (Expires in June 2098) 470 1,178.5 99 (Expires in June 2098) 471 374.8 60 (Expires in June 2076) 14 694.4 60 (Expires in June 2076) 3,000 acres • Fully Owned by Zecon Gr
Slide 13: KPGTP Masterplan Overall Roading Plan & Solar Transmission Line
KPGTP MASTERPLAN OVERALL ROADING PLAN & SOLAR TRANSMISSION LINE (SPA APPROVAL) 13
Slide 14: KPGTP Proposed Masterplan – Zoning
KPGTP Proposed Masterplan Zoning Approved By SPA (Jan 2026) 14
Slide 15: KPGTP Proposed Masterplan – Roading & Transmission Line
KPGTP Proposed Masterplan Roading & Transmission Line to 132KV SEB Substation Approved By SPA (Jan 2026) 15
Slide 16: KPGTP Masterplan Sarawak Digital Connectivity
KPGTP MASTERPLAN SARAWAK DIGITAL CONNECTIVITY (SDEC, Strategic Partner) 16
Slide 17: Submarine Cable System Designed with Landing Points to Sarawak
Submarine Cable System Designed with Landing points / Branching Unit to Sarawak Project Batam Singapore Internet Cable System (BaSICs) Southeast Asia - Hainan — Hong Kong Express (SEA-H2X) Indonesia Cable Express (ICE) System II CANDLE Route / Key landings Kuching ¢ Batam Hong Kong # Singapore with
Slide 18: Enhanced Sarawak's International Connectivity
Enhanced Sarawak’'s International Connectivity BASICS SEA-H2X = ree ICE Il a CANDLE Terrestrial Fibre Interborder Connectivity <=: Thailand To Hong Kong, Hainan and Phillipines Terrestrial Fibre 18
Slide 19: Trunk Design and Total Cable
Trunk Design Total Cable Cable Capacity Length 8 Fibre 20Tbps per >5,000 km i Fibre Pair Thailand es ey Z Frere oon © “SDEC Digitalising Sarawak S11 SSE Hainan Lingsiar o. Ss Supplier ae HMN | Bosse Philippines OLa Union Tech S64 = ao Connectivity through S5 @ Singapore Kuching o—> @ Hong Kong Singa
Slide 20: KPGTP Masterplan Current Progress
KPGTP MASTERPLAN CURRENT PROGRESS 20
Slide 21: Readiness Progress Schedule
Kota Petra Green Technology Park — Readiness Progress Schedule Phased infrastructure delivery 2026-2028, targeting LSS 100M Wac operational by Q2 2028 and full phase 1 readiness by Q4 2028. v COMPLETED ( @PLANNING/ MOBILISATION NJ CONSTRUCTION / IMPLEMENTATION __) Activity : 2026 2027 2028 : Target
Slide 22: Current Progress at Site as at July 2026
CURRENT PROGRESS AT SITE As At 10 July 2026 Sg. Santubong Bridge Sg. Serai Bridge Earth Bund — Lot 471 Site Clearing — Lot (LSS Area) at 3.5m Height 471 (LSS Area) Embankment wall at the Kuching side Main bridge construction will commence upon the completion of the 18% completed — 1,150m of 6,202m 6
Slide 23: Solar Farm (Lot 471) Site Clearance
Solar Farm (Lot 471) Site Clearance 23
Slide 24: Land Clearing & Earth Bund Works In Progress
Land Clearing & Earth Bund Works In Progress for Phase 1 Large-Scale Solar & Data Centres Sites 24
Slide 25: Land Clearing & Earth Bund Works In Progress
Land Clearing & Earth Bund Works In Progress for Phase 1 Large-Scale Solar & Data Centres Sites sumitoma ~
Slide 26: Bridge Works To Solar Site (Serai) 150 Meters
Bridge Works To Solar Site (Serai) 150 Meters 26
Slide 27: Phase 1 – 100MWac Agrivoltaics Solar Farm Site
KOTA PETRA GREEN TECHNOLOGY PARK Phase 1 – 100MWac Agrivoltaics Solar Farm Site New Sejingkat Bridge Serai Bridge Site 27
Slide 28: Steel Temporary Bridge Fully Completed & Operational
A Steel Temporary Bridge Is Fully Completed & Operational, designed to carry up to 120 tonnes. (The 150m Permanent Bridge will be completed by August 2028) 28
Slide 29: Bridge Works To KPGTP (Santubong) 382m
Bridge Works To KPGTP (Santubong) 382m Meters 29
Slide 30: Bridge Works To KPGTP (Santubong)
Bridge Works To KPGTP (Santubong) Bridge Embankment 30
Slide 31: 31
31
Slide 32: 32
32
Slide 33: KPGTP Masterplan Strategic Collaboration
KPGTP MASTERPLAN STRATEGIC COLLABORATION 33
Slide 34: Zecon Signing of Agreements – MOU
ZECON Signing of Agreements SIGNING OF MOU 16 OCTOBER 2024 Zecon, SDEC and CENTEXS entered into the MOU to achieve mutual benefit for all parties in the development of a 3,000-acre Kota Petra Green Technology Park (KPGTP) • ZECON - landowner & master developer • SDEC - digital technology & telecommu
Slide 35: Zecon Signing of Agreements – Power Purchase Agreement
ZECON Signing of Agreements SIGNING A 30-YEAR POWER PURCHASE AGREEMENT WITH SYARIKAT SESCO BERHAD 100MWac Solar Power Scheduled COD 31 Dec 2027 ON 22 OCTOBER 2025 At IDECS 2025 BCCK, KUCHING 35