Royal Bafokeng Platinum — H1 2012 Earnings Presentation
37 slides from Royal Bafokeng Platinum's earnings presentation, Aug 20, 2012

Slide 1: Interim results for the six months ended 30 June 2012
Interim results for the six months ended 30 June 2012 20 August 2012 www.bafokengplatinum.co.za

Slide 2: Disclaimer
Disclaimer The information presented in this presentation is of a general nature and the forward looking information, opinions and beliefs of the Company and its affiliates are based on various market related assumptions. Changes in market circumstances after the production of the information may im

Slide 3: Contents
Contents 1. Overview 2. Safety 3. Market review 4. Operational review 5. Financial review 6. Outlook www.bafokengplatinum.co.za 3

Slide 4: Overview
Overview www.bafokengplatinum.co.za 4

Slide 5: A half-year of challenges…
A half-year of challenges… Key features • LTIFR reduced by 39% to 0.67 • regrettably one employee fatally injured in fall of ground incident • 10, 504 (4E) ounces lost due to safety related stoppages, 144% increase from first half of 2011 • Production down 9% to 128, 847 PGM ounces • 6% reduction in

Slide 6: Safety
Safety www.bafokengplatinum.co.za 6

Slide 7: Improving safety performance
Improving safety performance Description Unit H1 2012 H1 2011 Var Fatal injuries no. 1 0 -100% LTIFR / 200,000 hours rate 0.67 1.10 39% SIFR / 200,000 hours rate 0.32 0.43 25% Injury free days days 116 98 18% LTIFR SIFR • One fatal injury (FOG) 0.60 1.40 • Improved LTIFR and SIFR 0.53 • LTIFR 39% Yo

Slide 8: Safety stoppages
Safety stoppages Tonnes lost due to safety stoppages Safety stoppages: H1 2012 70,000 61,618 60,000 50,000 Tonnes Routine Visits 23% 40,000 33,672 28,925 25,812 30,000 22,563 Fatal Accident Ministerial & Follow Up 20,000 Audit 64% 6,402 13% 10,000 - Q1 Q2 Q3 Q4 Q1 Q2 2011 2011 2011 2011 2012 2012 •

Slide 9: Market review
Market review www.bafokengplatinum.co.za 9

Slide 10: Weak PGM demand drives prices down…
Weak PGM demand drives prices down… • Weaker demand from Europe in particular Net platinum demand, Moz +730koz (+10% increase) drove prices down 8.5 • Platinum price currently at around $1,400/oz compared to an average 8.0 price of $1,790/oz in H1 2011 • Platinum price for 2012 forecast at 7.5 $1,47

Slide 11: Palladium automotive demand still in better shape…
Palladium automotive demand still in better shape… • Total palladium demand for 2012 is estimated at Palladium demand, Moz +2.7Moz (+32% increase) 9.5Moz, up from 9.2Moz in 2011 12.0 • Automotive demand for palladium forecast at 6.9Moz for 2012, the highest it’s ever been in five 11.0 years, and 8.3

Slide 12: Lower PGM basket price and above inflation costs eat away at margins
Lower PGM basket price, particularly rhodium and above inflation costs eat away at margins $/4E oz Source: SFA, Oxford 1,800 TCC $/4E oz (90th centile) 1,600 Basket price ($/4E oz) Rh today: $1,330/oz 1,400 Rh $2,000/oz 1,200 Rh $3,000/oz 1,000 UG2 shaft closure Rh $4,000/oz risk 800 600 400 Avg. ME

Slide 13: Operational review
Operational review www.bafokengplatinum.co.za 13

Slide 14: Mining
Mining Description Unit H1 2012 H1 2011 Var Major production disruptions Tonnes delivered – total kt 1,190 1,167 2% Merensky kt 976 1,032 -5% RDO absenteeism 26.9kt, Surface sources kt 60 0 100% 2,604 4E oz UG2 kt 153 135 14% UG2 % % 13.5 11.5 2% Combined headgrade (4E) g/t 4.04 4.32 -6% Merensky (4

Slide 15: 4E grade trend and variations in grade
Grade 4E Grade trend Variations in Grade (H1 2012 vs H1 2011) 5.00 40% 4.52 UG2 4.50 4.31 4.35 4.01 Contribution 4.18 4.22 4.14 4.17 35% 4.04 4.06 In Situ Grades 9% 4.00 5% 30% 3.50 Percentafe UG2 25% 3.00 Low Grade Stockpile g/t 2.50 20% 41% Mine Call Factor 2.00 19% 15% 1.50 10% 1.00 5% 0.50 - 0%

Slide 16: Development
Development Total development Shaft sinking 20.0 5% 18.0 18.0 17.0 16.4 16.7 Capital development 16.0 10% Primary development 14.0 13.5 43% 12.0 km 10.0 8.0 6.0 4.0 2.0 Redevelopment 42% - Description Unit H1 2012 H1 2011 Var Total development km 18.0 13.5 33% Working cost development km 15.3 11.5 3

Slide 17: Mining reserves
Mining reserves IMS face length : per shaft 2500 • 494m (+13%) increase in IMS face length from 2300 3,669m in Jan 2012 to 4,163m in June 2012 2100 • IMS panel ratio 1.12 panels/team will Face Length (m) 1900 continue to be improved – aim 1.50 1700 panels/team 1500 1300 Dec Jan Feb Mar Apr May Jun S

Slide 18: Concentrating
Concentrating Description Unit H1 2012 H1 2011 Var BRPM concentrator recovery (4E) 100 16.0% BRPM concentrator tonnes milled kt 1,097 1,072 2% 87.8 87.5 90 86.3 86.5 BRPM Merensky tonnes milled kt 990 1,037 -5% 14.0% BRPM UG2 tonnes milled kt 107 35 203% 80 12.0% BRPM UG2% % 10 3 7 70 10.0% 60 UG2 %

Slide 19: Labour
Labour Description Unit H1 2012 H1 2011 Var Working cost labour variance H1 2011 vs H1 2012 Labour – total no. 8,501 7,789 -9% 6,800 11 6,744 34 46 Labour – operating no. 6,744 6,398 -5% 6,700 52 Labour – capital no. 1,757 1,391 -26% 203 6,600 Stoping efficiency – total m2/crew 281 315 -11% 6,500 No

Slide 20: Operating expenditure
Operating expenditure Description Unit H1 2012 H1 2011 Var Total cash costs Rm 969 896 -8% Total cash cost/tonne delivered R/t 814 768 -6% Total cash cost/tonne milled R/t 851 765 -11% Total cash cost/4E oz M&C R/oz 7,519 6,306 -19% Total cash cost/Pt oz M&C R/oz 11,606 9,732 -19% 900 1.6 1.8 3.3 21

Slide 21: Operating expenditure (continued)
Operating expenditure (continued) Process costs Cost breakdown 900 H1 2011 H1 2012 800 Sundries 124 Sundries 12% 15% 124 Utilities 700 8% Utilities 7% Labour costs Labour costs 125 37% 104 111 37% 600 120 Stores 99 106 Stores 20% 21% R/t milled 500 Contractor costs Contractor costs 20% 23% 400 300 6

Slide 22: Capital expenditure
Capital expenditure Description Unit H1 2012 H1 2011 Var SIB projects Stay in business capital Rm 116 52 -122% SIB % of operating cost % 12% 6% -105% South Shaft North Shaft Chairlift Chairlift 13% Replacement capital Rm 156 169 9% 12% Phase II Rm 63 107 41% Phase III Rm 90 59 -53% Information BRPM

Slide 23: BRPM replacement projects
BRPM replacement projects Phase II Phase II (Extend N# and S# from level 6 to level 10) • North shaft complete Description Unit Plan Act Var • South shaft completion Sept 2012 N# % complete % complete complete complete • Estimate at completion – N# project completion date complete complete complete

Slide 24: Operating strategy
Operating strategy Expand UG2 production • Shallow UG2 accessible on levels where Merensky is depleted • Requires significant initial development (10m2/m) Increase stopeable reserves • Development replacement rate (30m2/m) • Ledging and equipping – restructuring / resources • Re-development resource

Slide 25: Styldrift I Project
Styldrift I Project • Significant improvement in sinking Description Unit Plan Act Var rates Overall progress % 31.7 31.7 0.0 • Merensky intersection Q3 2012 Main shaft m 594 513 -81 Services shaft m 594 408 -186 • Appointment of operational team Expenditure • Permanent rock winder presently Project

Slide 26: Styldrift I Project (continued) – studies
Styldrift I Project (continued) – studies Styldrift optimisation study Styldrift Ramp-up 3,000 • Detailed mine design and layouts 1.7 Mt lower 2,500 • On-reef strike conveyors 107 koz (4E) lower 2,000 • Reduced bord widths from 13m to 8m ktpa 1,500 • Shaft depth increased 18 metres 1,000 • Hydropowe

Slide 27: Financial review
Financial review www.bafokengplatinum.co.za 27

Slide 28: Key financial performance indicators
Key financial performance indicators 6 months ended 6 months ended Description Unit % Change 30 June 2012 30 June 2011 Average basket price* R/Pt oz 15,638 16,394 4.6 Average Rand : US$ received R/US$ 7.94 6.90 15.1 Revenue Rm 1,305.3 1,510.4 13.6 Cost of sales Rm 1,142.3 1,171.1 2.5 Gross profit Rm

Slide 29: Key financial performance indicators (continued)
Key financial performance indicators (continued) 6 months ended 6 months ended Description Unit % Change 30 June 2012 30 June 2011 Headline earnings Rm 70.6 171.9 58.9 Weighted average shares outstanding #m 164.0 163.7 0.2 HEPS R/share 0.43 1.05 59.0 Fair value depreciation and amortisation R/share

Slide 30: Key financial performance indicators (continued)
Key financial performance indicators (continued) 6 months ended 6 months ended Description Unit % Change 30 June 2012 30 June 2011 Cash generated by operating activities Rm 302.3 390.2 22.5 Cash, net of debt (incl. pref share investment) Rm 1,167.8 1,289.8 9.5 Capital expenditure Rm 520.9 592.4 12.1

Slide 31: Revenue contribution by metal
Revenue contribution by metal H1 2012 6 months ended 30 Ni Cu Co Average price Ru 10% 2% 0% Description June 2012 Sales 1% achieved* (US$) Ir volumes 1% Rh 6% Platinum (oz) 83,472 1,541/oz Au 3% Palladium (oz) 34,335 647/oz Pd 12% Pt Gold (oz) 4,272 1,694/oz 65% Rhodium (oz) 6,768 1,308/oz H1 2011 N

Slide 32: Cost of sales breakdown
Cost of sales breakdown H1 2012 H1 2012 H1 2011 H1 2011 Description R million % of Total R million % of Total Labour 359.9 35.9% 330.6 35.1% Utilities 78.9 7.9% 63.0 6.7% Contractor costs 220.7 22.0% 179.6 19.1% Materials and other mining costs 309.2 30.8% 297.9 31.6% Total cash costs excl once–off

Slide 33: Headline earnings variance analysis
Headline earnings variance analysis 400 191.2 300 200 171.9 R million -231.1 100 28.2 70.6 61.7 48.9 0 14.8 -165.2 -5.6 3.4 90.2 -12.8 -100 -77.7 -47.3 -200 www.bafokengplatinum.co.za 33

Slide 34: Cash flow analysis
Cash flow analysis 1600 319.4 1400 1,167.8 1,099.3 -116.9 1200 250.0 22.5 -153.6 1000 895.3 R million -250.4 -2.5 800 600 400 200 0 www.bafokengplatinum.co.za 34

Slide 35: Outlook
Outlook www.bafokengplatinum.co.za 35

Slide 36: Stronger operational performance expected in second half
Stronger operational performance expected in second half • Further supply cuts in the industry anticipated to keep up with weak demand for platinum • Market shortfall of around 500koz for palladium is expected for the year • RBPlat expects stronger operational performance in second half • improving

Slide 37: Contact details
Contact details Lindiwe Montshiwagae Investor Relations Manager Royal Bafokeng Platinum The Pivot, No 1 Monte Casino Boulevard, Block C, Floor 4, Fourways, 2021 Tel: +27 (0) 10 590 4517 Fax: +27 (0) 86 219 5131 Mobile: +27 (0) 82 920 7803 Email: lindiwe@bafokengplatinum.co.za www.bafokengplatinum.co
Source: Internet Archive copy of implats.co.za
More decks from Royal Bafokeng Platinum Ltd
Renaissance Capital Metals & Mining Conference 202118 slides · May 2021
H1 2020 Earnings Presentation39 slides · 2020
Merger or Acquisition (October 2019)11 slides · Oct 16, 2019
RBPlat Analyst Roundtable 201910 slides · Aug 6, 2019
Technical Presentation (February 2019)34 slides · Feb 1, 2019
Fact Sheet (2019)11 slides · 2019