  1. Slide 1: Global Lithium Resources: Becoming Australia's Next Lithium Producer

    For personal use only Global Lithium Resources Becoming Australia’s Next Lithium Producer ASX:GL1 April 2026 1

  2. Slide 2: Disclaimer

    Disclaimer These presentation materials and the accompanying verbal presentation (together, the Presentation Materials) have • are necessarily based upon a number of estimates and assumptions that, while considered reasonable by the been prepared by Global Lithium Resources Limited ABN 58 626 093 15

  3. Slide 3: Investment Highlights

    Investment Highlights Globally significant project: 51.6Mt @ 1.0% Li2O (64% Indicated) mineral For personal use only resource and a reserve of 19.4Mt @ 0.91% Li2O Strategic location: Located just 100km east of WA’s mining hub of Kalgoorlie. Developed infrastructure, road and railway access with conn

  4. Slide 4: Corporate Snapshot

    Corporate Snapshot Board of Directors Market Capital Share Price Richard O’Shannassy • 40+ years experience as a commercial lawyer and A$157.8m A$0.60 For personal use only Non-Executive Chair involvement in the resources sector • Current non-executive director for Focus Minerals Shares on Issue Opt

  5. Slide 5: Lithium Market Outlook

    MANNA LITHIUM PROJECT For personal use only • 100% owned project Lithium Market Outlook • Tier 1 mining jurisdiction • Outcropping spodumene bearing pegmatite • Current Indicated & Inferred Mineral Resource of 36.0Mt @ 1.13% Li O 2 5

  6. Slide 6: Lithium Demand and Pricing Forecasts

    Lithium Demand and Pricing Forecasts Lithium Spodumene 6% Li2O price history1 Lithium Hydroxide / Lithium Carbonate $25,000 For personal use only $20,000 $15,000 $10,000 $5,000 $0 2026 2027 2028 2029 2030 Long Term Lithium Hydroxide (US$/t) Lithium Carbonate (US$/t) Global Shipments of EV Batteries

  7. Slide 7: Outlook – Supply and Demand

    Outlook – Supply and Demand Mined lithium supply from existing and announced projects and $116 billion needed in lithium investment to meet the high case lithium For personal use only primary supply requirements by scenario1 demand scenario by 20302 1500 6,000,000 kt Li Tonnes LCE 5,000,000 1200 4,0

  8. Slide 8: Manna Project

    MANNA LITHIUM PROJECT For personal use only • 100% owned project Manna Project • Tier 1 mining jurisdiction • Outcropping spodumene bearing pegmatite • Current Indicated & Inferred Mineral Resource of 36.0Mt @ 1.13% Li O 2 8

  9. Slide 9: Kalgoorlie: Established Mining Province

    Kalgoorlie: Established Mining Province Leading mining jurisdiction • Western Australia remains the world’s largest producer of lithium spodumene and For personal use only the broader Goldfields region around Kalgoorlie is emerging as a significant lithium province Tier 1 global miners operate and a

  10. Slide 10: Manna Project Highlights

    Manna Project Highlights Well Defined Orebodies1 • 100% owned flagship lithium project, located just 100km east of WA’s For personal use only mining hub of Kalgoorlie • Manna Project ranked the 3rd largest lithium resource in the Kalgoorlie province ✓ MRE of 51.6Mt at 1.00% Li2O following the 43% mi

  11. Slide 11: DFS Overview

    DFS Overview Economic Snapshot 1 Manna Lithium Project Plant 3D Model For personal use only A$439.1m A$472m A$1.15B Total pre-production Post-tax NPV8 Project free cashflow capex2 25.7% 3.5 Years 14.3 Years Post-tax IRR Payback Period Mine life US$738/t (SC5.5)3 US$784/t (SC6.0) US$1,400/t (SC6) Pri

  12. Slide 12: DFS Overview – Continued

    DFS Overview – Continued DFS Key Metrics Summary1 Processing Flow-chart For personal use only Key Metrics • First 8.5 years contractor open cut mining followed by ROM ore feed 1.8Mt per annum underground mining Mill feed 1.53Mt per annum • Three-stage crushing, ore sorting and conventional Spodumene

  13. Slide 13: Multiple Logistics Pathways

    Multiple Logistics Pathways • Discussions well advanced for Port of Esperance For personal use only spodumene concentrate to be shipped from Port of Esperance • Loading at Manna – Loose bulk haulage via triple road trains; payload of 98 tonnes per combo permitted • Unloading at storage facility – In

  14. Slide 14: Huge Upside Potential

    Huge Upside Potential1 For personal use only DFS Assumed U$1,400/t SC6 Current Price U$2,500/t SC6 Notes: 14 1 Key assumptions Refer ASX release titled “MANNA LITHIUM PROJECT ROBUST DFS RESULTS” 4 December 2025

  15. Slide 15: Operating Considerations

    Operating Considerations For personal use only Potential Upsides (subject to further studies and optimisations) Processing Opportunities exist to improve processing recovery beyond the DFS assumption of 72.8% optimisation through ongoing metallurgical testwork, reagent optimisation and flowsheet ref

  16. Slide 16: Project Approvals / Permits

    Project Approvals / Permits Native Title Mining Agreement For personal use only • Native Title Mining Agreement (NTMA) signed with Kakarra Part B Native Title Group Mining Lease • 21 years Mining Lease (MLA 28/414) granted in August 2025 by the Department of Mines, Petroleum and Exploration (DMPE) E

  17. Slide 17: Manna Project Key Milestones

    Manna Project Key Milestones Q1 2026 Q2 2026 Q3 2026 Q4 2026 Q1 2027 Q2 2027 Q3 2027 Q4 2027 Q1 2028 Q2 2028 Milestones For personal use only Pre-FID Contracts and Planning Financial and Project Approvals Contract and Procurement Packages - Pre FID Basic Engineering and Design Pilot/Temporary Access

  18. Slide 18: Community engagement

    Community engagement Actively participating in and supporting For personal use only Kakarra local community • GL1 has signed the Native Title Mining Agreement with the Kakarra Part B community group • Our Directors and engagement team are in close contact with the community and continue to support a

  19. Slide 19: Why invest in Global Lithium Resources

    Why invest in Global Lithium Resources •1 One of Australia’s major UNDEVELOPED hard-rock lithium projects For personal use only •2 Located in a TIER 1 mining jurisdiction within WA •3 NPV of $472m1, 25.7% IRR, $439m pre-production capex, 3.5 year payback, 14.3 year mine life, 236Kt per annum SC5.5 p

  20. Slide 20: Appendix

    MANNA LITHIUM PROJECT For personal use only • 100% owned project Appendix • Tier 1 mining jurisdiction • Outcropping spodumene bearing pegmatite • Current Indicated & Inferred Mineral Resource of 36.0Mt @ 1.13% Li O 2 20

  21. Slide 21: Global Lithium – Mineral Resource and Reserves

    Global Lithium – Mineral Resource and Reserves Resources 1 Project Name Category Million Tonnes (Mt) Li2O% Ta2O5 ppm For personal use only Marble Bar 2 Indicated 3.8 0.97 53 Inferred 14.2 1.01 50 Subtotal 18.0 1.00 51 Manna 3 Indicated 32.9 1.04 52 Inferred 18.7 0.92 50 Subtotal 51.6 1.00 52 Combine

  22. Slide 22: Global Lithium Resources Asset Portfolio

    Global Lithium Resources Asset Portfolio Manna Lithium Project For personal use only • 100% owned and Located 100km east of Kalgoorlie in WA • Mineral Resource Estimate: 51.6Mt @1.0% Li2O (64% Indicated) • Ore Reserve Estimate: 19.4Mt @ 0.91% Li2O Divested Marble Bar Lithium Project (Divested) • Ten

  23. Slide 23: Contact us

    Contact us For personal use only DIANMIN CHEN au.linkedin.com/company/ Managing Director global-lithium-resources +61 8 6103 7488 info@globallithium.com.au @Global_Lithium MICHAEL CAIRNDUFF Subscribe to our mailing list at: Media and Investor Relations globallithium.com.au +61 (0) 406 775241 mcairnd