  1. Slide 1: Investor Presentation: Fast-Tracking Australia's Next Lithium Mine

    For personal use only INVESTOR PRESENTATION Global Lithium Resources Fast-Tracking Australia’s Next Lithium Mine ASX:GL1 July 2026 1

  2. Slide 2: Disclaimer

    Disclaimer These presentation materials and the accompanying verbal presentation (together, the Presentation Materials) have Company, are inherently subject to significant technical, business, economic, competitive, political and social been prepared by Global Lithium Resources Limited ABN 58 626 09

  3. Slide 3: Investment Highlights

    Investment Highlights Globally significant Manna project: 51.6Mt @ 1.0% Li2O (64% Indicated) mineral resource and a reserve of 19.4Mt @ 0.91% Li2O For personal use only Prime location: Manna located just 100km east of WA’s mining hub of Kalgoorlie. Developed infrastructure, road and railway access w

  4. Slide 4: Company-Making Transactions Are Driving GL1 Forward

    Company-Making Transactions Are Driving GL1 Forward 22 April 2026 22 April 2026 15 July 2026 For personal use only Nova Operation Acquisition Lopal Strategic Funding Marble Bar Divestment • Binding Agreement to acquire 100% of IGO Nova • Placement of c.13.84m shares at c.A$0.53 per • Binding Tenemen

  5. Slide 5: Corporate Snapshot

    Corporate Snapshot Board of Directors Market Capitalisation1 Share Price1 Richard • 40+ years experience as a commercial lawyer and c.A$142m A$0.51 For personal use only O’Shannassy involvement in the resources sector Non-Executive Chair • Current non-executive director for Focus Minerals Shares on

  6. Slide 6: Manna Lithium Project

    MANNA LITHIUM PROJECT For personal use only • 100% owned project Manna - Nova Project • Tier 1 mining jurisdiction • Outcropping spodumene bearing pegmatite • Current Indicated & Inferred Mineral Resource of 36.0Mt @ 1.13% Li O 2 6

  7. Slide 7: Accelerated Pathway to Production

    Accelerated Pathway to Production Manna Project Binding Term Sheet with Jiangsu Lopal Tech. Group Co., Ltd (Lopal)1 Capex Funding Bridge A$m For personal use only Original Manna Project Capex 439.0 Key Commercial Terms Less: Current cash 25.0 1. Equity Placement of A$7.32m • Following the issue of t

  8. Slide 8: Kalgoorlie: Established Mining Province

    Kalgoorlie: Established Mining Province Leading mining jurisdiction • Western Australia remains the world’s largest producer of lithium For personal use only spodumene and the broader Goldfields region around Kalgoorlie is emerging as a significant lithium province Tier 1 global miners operate and a

  9. Slide 9: Manna Highlights

    Manna Highlights • 100%-owned flagship lithium project, located just 100km east of WA’s Well Defined Orebodies1 mining hub of Kalgoorlie For personal use only • Manna Project ranked the 3rd largest lithium resource in the Kalgoorlie province  MRE of 51.6Mt at 1.00% Li2O following the 43% mineral re

  10. Slide 10: Planned Manna Mining Operations

    Planned Manna Mining Operations For personal use only Open Cut • Ore Mined 15.5Mt @ 0.91% Li2O • Total Waste Mined 231Mt • Strip Ratio: 14.9 • Open Cut Mine Life: 8.5 Years Underground (PFS Level) • 8.2Mt @ 0.82% Li2O • Underground Mine Life: 7 Years 10

  11. Slide 11: Nova Highlights

    Nova Highlights Nova Processing Plant For personal use only • 135km direct distance to Manna • Miscellaneous license with 170km road readily available • 1.8mtpa sulfide ore processing plant • 26.6MW Diesel/Solar power plant • Sealed runway and airport • 500 bed camp • Bore-field (1GL License) with O

  12. Slide 12: Multiple Logistics Pathways

    Multiple Logistics Pathways Port of Esperance For personal use only • Discussions well advanced for DSO and spodumene concentrate to be shipped from Port of Esperance • Loading at Manna – Loose bulk haulage via triple road trains; payload of 98 tonnes per combo permitted • Trucking to Nova – Crushin

  13. Slide 13: A Glance at Operating Considerations

    A Glance at Operating Considerations For personal use only Pegmatite lithium ore mining will be carried out at Manna site with a 200-bed camp, Mining at Manna small power plant, bore-fields and other infrastructure Ore produced from Manna is hauled to Nova for crushing, sorting and processing Haulin

  14. Slide 14: Project Approvals / Permits

    Project Approvals / Permits Native Title Mining Agreement For personal use only • Native Title Mining Agreement (NTMA) signed with Kakarra Part B Native Title Group Mining Lease • 21 years Mining Lease (MLA 28/414) granted in August 2025 by the Department of Mines, Petroleum and Exploration (DMPE) E

  15. Slide 15: Manna-Nova Project Key Milestones

    Manna-Nova Project Key Milestones 2026 2027 Q3 2026 MILESTONE Q4 2026 Q1 2027 Q2 2027 Q3 2027 Q4 2027 ▼ NOW For personal use only PRE-FID ACTIVITIES Manna-Nova Operation Integration Study Construction Water Supply / Storage Project Approvals & Permits ◆ Contract & Procurement — Pre-FID Basic Enginee

  16. Slide 16: Community Engagement

    Community Engagement GL1 is actively participating in the local Goldfields For personal use only community • GL1 has an open, ongoing relationship with the Kakarra people as part of our Native Title Mining Agreement • We maintain regular engagement between Directors, our community team and local lea

  17. Slide 17: Why Invest in Global Lithium

    MANNA LITHIUM PROJECT For personal use only • 100% owned project Why Invest in Global Lithium • Tier 1 mining jurisdiction • Outcropping spodumene bearing pegmatite • Current Indicated & Inferred Mineral Resource of 36.0Mt @ 1.13% Li O 2 17

  18. Slide 18: Why Invest in Global Lithium Resources

    Why Invest in Global Lithium Resources •1 One of Australia’s major UNDEVELOPED hard-rock lithium projects For personal use only •2 Located in a TIER 1 mining jurisdiction within WA •3 The Manna-Nova Operation Integration Study, expected to be released THIS QUARTER, potential to significantly lower C

  19. Slide 19: Appendix

    MANNA LITHIUM PROJECT For personal use only • 100% owned project Appendix • Tier 1 mining jurisdiction • Outcropping spodumene bearing pegmatite • Current Indicated & Inferred Mineral Resource of 36.0Mt @ 1.13% Li O 2 19

  20. Slide 20: Global Lithium – Mineral Resource and Reserves

    Global Lithium – Mineral Resource and Reserves Resources1 Project Name Category Million Tonnes (Mt) Li2O% Ta2O5 ppm For personal use only Marble Bar2 Indicated 3.8 0.97 53 Inferred 14.2 1.01 50 Subtotal 18.0 1.00 51 Manna3 Indicated 32.9 1.04 52 Inferred 18.7 0.92 50 Subtotal 51.6 1.00 52 Combined T

  21. Slide 21: Contact us

    Contact us For personal use only DIANMIN CHEN au.linkedin.com/company/ Managing Director global-lithium-resources +61 8 6103 7488 info@globallithium.com.au @Global_Lithium MICHAEL CAIRNDUFF Subscribe to our mailing list at: Media and Investor Relations globallithium.com.au +61 (0) 406 775241 mcairnd