Linq Minerals Limited · ASX:LNQ

Linq Minerals — Noosa Conference 2025

26 slides from Linq Minerals's conference presentation, Jul 23, 2025

  1. Slide 1: Gilmore Gold Copper Project – Noosa Conference

    GILMORE For personal use only GOLD COPPER PROJECT JULY 2025 NOOSA CONFERENCE ASX: LNQ www.linqminerals.com

  2. Slide 2: Important Notice

    IMPORTANT NOTICE Nature of Document: This presentation has been prepared and issued by LinQ Minerals Limited (ACN 665 642 820) (LinQ or the Company) to provide general information about the Company. The information in this document is in summary form and contains only a synopsis of more detailed inf

  3. Slide 3: Investment Proposition – A Rare Opportunity

    INVESTMENT PROPOSITION – A RARE OPPORTUNITY Strategic Asset Significant Scale Growth Tier 1 Location (NSW) Global JORC MRE 6 JORC Resources For personal use only 100% owned Au Cu Project ~516Mt +20 mineralised prospects Not publicly visible for ~40 yrs ~3.7Moz Au & ~1.2Mt Cu1 Extensive target pipeli

  4. Slide 4: Company Overview

    COMPANY OVERVIEW • Listed on the ASX in June 2025 Corporate Structure • Tight capital structure with Board and management ownership of >60% Shares on Issue 175.8m Unlisted Options1 18.2m • Well funded to drill numerous targets & prospects in a +16,000m drill program Share Price2 15.0c • Drilling com

  5. Slide 5: What Are We Looking For?

    WHAT ARE WE ARE LOOKING FOR? Target porphyry intrusives, source higher grade tonnes & extend known resources 279Mt @ 0.34% CuEq Southern Zone Exploration & Drilling Strategy 0.25% Cu, 0.12g/t Au, 35 ppm Mo • Confirming continuity of the current higher-grade cores of current resources. • Resource ext

  6. Slide 6: Upcoming Company Activities

    UPCOMING COMPANY ACTIVITIES • Well funded to drill numerous targets & prospects in a +16,000m drill program • Drill rig mobilised with drilling commencing at Gidginbung in July • Substantial news flow updates For personal use only Upcoming Company Activities Q3 CY25 Q4 CY25 Q1 CY26 Q2 CY26 Indicativ

  7. Slide 7: Macquarie Arc Location and Regional Endowment

    MACQUARIE ARC LOCATION AND REGIONAL ENDOWMENT Why New South Wales? • >160Moz AuEq inventory in region • Hotspot for M&A and Exploration: For personal use only >$16bn in M&A for producing assets1 >$385m in exploration earn-in / JV’s2 Two >10Moz AuEq Discoveries2 • Infrastructure availability and l

  8. Slide 8: Gilmore Project Overview

    GILMORE PROJECT OVERVIEW Ownership • Tenements 100% owned 279Mt @ 0.34% CuEq 0.25% Cu, 0.12g/t Au, 35 ppm Mo • ~597km2 tenement package Tenure & Access • Key land access agreements in place • Project situated on freehold land (no native title claims) 1 • Global MRE: ~516Mt containing ~3.7Moz Au & ~1

  9. Slide 9: Project Geology

    PROJECT GEOLOGY • The Gilmore tenements are prospective for the entire range of economic deposits found in the Macquarie Arc, including intrusive Cu/Au (+/- Mo) all the way through to high and low sulphidation epithermal deposits over a 40km strike. • Current Resources are only estimated to a maximu

  10. Slide 10: Gilmore Exploration Pipeline

    GILMORE EXPLORATION PIPELINE Blue = Yiddah Alteration Zone Green = Mandamah Alteration Zone LNQ EL’s Red = Rosevale Alteration Zone For personal use only Epithermal related Au Cu/Au/Mo porphyry Gidginbung Dam, Estoril, Cullingeri, Mandamah, Yiddah Resources - 6 Monza, Donnington Advanced prospects -

  11. Slide 11: Gilmore South Brownfield Gold Project

    For personal use only GILMORE SOUTH BROWNFIELD GOLD PROJECT Core Yard – West Wyalong LINQ MINERALS LIMITED 11

  12. Slide 12: Gilmore South Brownfield Gold Project

    GILMORE SOUTH BROWNFIELD GOLD PROJECT • Last in production in 1996 when the gold price was ~A $460/oz Gilmore South • Gidginbung historical oxide production ~0.54Moz Au  large sulphide resource remains • Gilmore South JORC MRE ~55Mt for ~1.2Moz Au and ~120Kt Cu1 For personal use only Gidginbung: ~

  13. Slide 13: Gilmore South – Large Growth Opportunity

    GILMORE SOUTH – LARGE GROWTH OPPORTUNITY >6km strike – limited drilling to date Commentary Fields (epithermal) • Gidginbung/Dam part of much larger system. • 25m @ 8.90g/t Au & 0.16%Cu • Significant potential for additional porphyry and epithermal resources/ • 16m @ 1.96 g/t Au & 0.07% Cu • 3 m @ 5.

  14. Slide 14: Gidginbung & The Dam – Plan View

    GIDGINBUNG & THE DAM – PLAN VIEW Potential underlying JORC Resource Gidginbung porphyry ~55Mt - ~1.2Moz Au & ~120Kt Cu1 Cu/Au  Gidginbung: 21Mt at 1.00g/t Au, 0.07% Cu Gidginbung North porphyry Intersections vectoring at depth  Dam: 34Mt at 0.7% CuEq (0.44g/t Au, 0.32% Cu) Gidginbung Drill Holes F

  15. Slide 15: Gidginbung Long Section – View to West

    GIDGINBUNG LONG SECTION – VIEW TO WEST Ore body at surface – gold intersections open at depth 1km 1.3km 1km For personal use only Gidginbung South Along strike Gidginbung epithermal Gidginbung North porphyry mineralisation Intersections vectoring at depth System open at depth – limited by depth of d

  16. Slide 16: Dam Long Section – View to West

    DAM LONG SECTION – VIEW TO WEST Ore starts near surface 1.2km For personal use only 300m Along strike Dam mineralisation Downdip Dam mineralisation outside resource Open. Open down dip. DAM (Cut Off) Green = 0.2CuEq, 77Mt @ 0.5%CuEq Red/brown = 0.4CuEq, 34Mt @ 0.7%CuEq LINQ MINERALS LIMITED 16

  17. Slide 17: Mandamah – Follow Up High Grade Copper/Gold

    MANDAMAH – FOLLOW UP HIGH GRADE COPPER/GOLD Current drilling only to 350m depth Surface CuEq*thickness Base of cover Base of weathering For personal use only 134m @ 0.8% CuEq 150m @ 0.8% CuEq 63m @ 0.5% CuEq 40m @ 2.4% CuEq 76m @ 1.1% CuEq 41m @ 0.5% CuEq 105m @ 0.9% CuEq OPEN (long section view to

  18. Slide 18: Donnington – New Discovery

    DONNINGTON – NEW DISCOVERY (long section view to the west) Commentary • Gold rich porphyry system. • TMMRD046 - 125m @ 0.6%CuEq (Inc 44m @ 1.2%CuEq) • TMMRD011 - 77m @1% CuEq • Drilling to date intersected volcanic hosted sheeted quartz- magnetite-porphyry veins. For personal use only • Currently de

  19. Slide 19: Monza – Gilmore's Ridgeway?

    MONZA – GILMORE'S RIDGEWAY? • High grade porphyry related copper-gold mineralisation Monza hole TMZD001 127-140m • 150m @ 1.02%Cu, 0.75g/t Au High-grade copper gold breccia core • Including 12.7m @ 8.9% Cu, 6.15g/t Au • Open along strike north and south and at depth TMDD043 59m @ 0.6%CuEq, 49ppmMo •

  20. Slide 20: Gilmore Project – Summary

    GILMORE PROJECT – SUMMARY  Tier 1 Jurisdiction in mining district adjacent to valuable infrastructure with skilled labour availability  Project has not been publicly visible for ~40 years and tenement ownership has previously been fragmented For personal use only  Well funded to drill numerous ta

  21. Slide 21: Contact Us

    For personal use only Contact Us Clive Donner – Executive Chair E: info@linqminerals.com Jane Morgan – Investor & Media Relations E: jm@janemorganmanagement.com.au M: +61 405 555 618 Principal Place of Business LinQ House Level 1, 17 Ord Street West Perth WA 6005 Australia www.linqminerals.com

  22. Slide 22: Appendix

    For personal use only APPENDIX LINQ MINERALS LIMITED 22

  23. Slide 23: Experienced Leadership Team

    EXPERIENCED LEADERSHIP TEAM BOARD OF DIRECTORS AND EXECUTIVE MANAGEMENT Clive Donner - Executive Chair Scott Munro - Chief Geologist • 40+ years experience in both Private Equity and mining project finance, financed 50+ mines throughout career. • Experienced geologist with substantial experience in

  24. Slide 24: Gilmore South JORC MRE

    GILMORE SOUTH JORC MRE Table 1 Mineral Resources for Gilmore South (Gidginbung & Dam) – Global grade cut off Competent Persons Statement – Mineral Resources INDICATED INFERRED TOTAL METAL The information in this report that relates to Exploration Results and Mineral DEPOSIT Cut-off Cu Cu Cu Cu Resou

  25. Slide 25: Gilmore Project Global JORC MRE

    GILMORE PROJECT GLOBAL JORC MRE Global Resource: 516Mt containing ~3.7Moz Au and ~1.2Mt Cu Table 1 Total Mineral Resources for the Gilmore Project INDICATED INFERRED TOTAL METAL Competent Persons Statement – Mineral Resources DEPOSIT Cut-off tonnes Cu Cu Cu Cu The information in this report that rel

  26. Slide 26: Gilmore Project JORC MRE – Multiple Cut Offs

    GILMORE PROJECT JORC MRE – MULTIPLE CUT OFFS INDICATED INFERRED TOTAL METAL DEPOSIT Cut-off Cu equiv tonnes (Mt) Cu equiv % Cu % Au g/t Mo g/t tonnes (Mt) Cu equiv % Cu % Au g/t Mo g/t tonnes (Mt) Cu equiv % Cu % Au g/t Mo g/t Cu (Kt) Au (Koz) Mo (t) (Kt) Oxide Resources reported to a gold g/t cut-o

LinQ Minerals — Noosa Conference 2025 on 6ix