Slide 1: Mt Carlton
For personal use only Mt Carlton May 2014 Arlene Rofe – General Manager
Slide 2: Disclaimer
Disclaimer For personal use only This presentation has been prepared by Evolution Mining Limited (“Evolution Mining”) and consists of slides for a presentation concerning the company. By reviewing/attending this presentation, you acknowledge and agree the following. This presentation includes fo
Slide 3: Location
For personal use only Location 3
Slide 4: Site layout
For personal use only Site layout 4
Slide 5: Mt Carlton
Mt Carlton For personal use only Lowest cost mine in the portfolio Mine Type Open pit Workforce: approximately 140 including Minerals Gold, silver and copper contractors Mineralisation type High-sulphidation epithermal Roster: 8 days on, 6 days off Throughput 800,000tpa Mining method: open p
Slide 6: Safety, Environment & Community
For personal use only Safety, Environment & Community
Slide 7: Safety, environment & community
Safety, environment & community For personal use only • TRIFR reduced by 30% • Feedback and consultation with workforce Safety • Behavioural safety key focus – Beyond Zero Program • Culture of reporting hazards, near-misses, incidents • Responsible environmental management and performance Environmen
Slide 8: Mining
For personal use only Mining
Slide 9: Mining
Mining Current Fleet: 1 x 1200 excavator For personal use only 4 x CAT 777 trucks 1 x 980 loader 1 x 14M grader 1 x 773 water cart 2 x dozers 1x 30t rock breaker Completion of A39 Pit mining scheduled in Q4 FY14 Optimising mine scheduling V2 pit 9
Slide 10: V2 and A39 pit current bench and material moved
For personal use only Current bench Elevation: Stage1– 95mRL, Stage 2 – 125mRL V2 Pit Total Material moved – 5M BCM Current bench Elevation – 80mRL A39 Pit 6 Total Material moved – 2M BCM
Slide 11: Mining
Mining For personal use only Total material movement significantly reduced in H2 FY14 Life of mine strip ratio: V2 = 2.7:1, A39 = 3.3:1 A39 pit scheduled for completion of mining in Q4 FY14. Evaluation in progress to assess further exploitation of the remaining resource A39 ore Mark-Up 85mRL –
Slide 12: Physicals
Physicals For personal use only Ore and waste mined Mining costs 3,500 3,000 2,500 2,000 (kt) 1,500 1,000 Drill and Blast 500 Load and Haul Rock Breaking Crusher and Feed - Jun 2013 Qtr Sep 2013 Qtr Dec 2013 Qtr Mar 2014 Qtr Support Services Rehabilitation Capital Waste (kt) Operating Waste (kt) Ore
Slide 13: Processing
For personal use only Processing
Slide 14: Process flowsheet
For personal use only Process flowsheet 14
Slide 15: Physicals FY14 YTD
Physicals FY14 YTD July 2013 to March 2014 Units A39 V2 Total/Average For personal use only Mining Capital waste kt 0 1,894 1,894 Operating waste kt 141 2,219 2,359 Ore mined kt 211 341 553 Mined Grade - gold g/t - 5.1 5.1 Mined Grade - silver g/t 373 48 172 Processing Ore processed kt 174 318 492 G
Slide 16: Plant performance
Plant performance For personal use only Plant throughput 800kt per annum Plant availability 91.3% Plant Performance 100 95 90 80 90 70 Throughput (t/h) Edna May Crushing Circuit Recovery (%) 60 85 50 40 80 30 20 75 10 0 70 Jul Aug Sep Oct Nov Dec Jan Feb Mar A39 - Ag, % V2 - Au, % Avg t/h 16
Slide 17: Concentrate sales
Concentrate sales For personal use only 47,000dmt concentrate shipped to date Total revenue USD110m A39 Silver Concentrate V2 Gold Concentrate 12 shipments @ Av. size 2,000dmt 11 shipments @ Av. size 2,100dmt Average Ag grade: 3,750g/t Average Au grade: 63g/t Average revenue: US$4M per shipment
Slide 18: Cost saving initiatives
Cost saving initiatives For personal use only More favourable contracts negotiated Power, fuel, lime, explosives, equipment Review of rates being charged on all hired equipment on site Reduced grinding media consumption Contractor management and selection Material selection to reduce mai
Slide 19: Production and cash cost
Production and cash cost FY14 YTD production of 67,749oz AuEq already within FY14 For personal use only guidance (65,000 – 75,000oz AuEq) FY14 YTD cash cost of A$603/oz well below guidance of A$700 – $750 per ounce A$795 80,000 800 A$578 Production Au eq (oz) 60,000 600 Cost A$/oz A$454 40,000 4
Slide 20: Geology
For personal use only Geology
Slide 21: Exploration – Strategy and Plan
Exploration – Strategy and Plan For personal use only Transformational discovery – maximise opportunity Capability of the orebody drives the business 4D and Seismic – opportunity to increase geological knowledge Think like scientists to increase prospectivity Lithogeochemistry and ASD de
Slide 22: Alteration mapping with ASD
Alteration mapping with ASD For personal use only Camp-scale alteration zonation Defining preservation levels Prioritising targets Strathmore Castle Capsize MCU V2 Ortiz Alunite Pyrophyllite Dickite Boundary Kaolinite Illite
Slide 23: Geochemistry
Geochemistry For personal use only Alteration and geochemical mapping reflect the styles and ability to target high sulphidation deposits New targets identified Castle Capsize MCU V2 Strathmore Ortiz Boundary
Slide 24: Near-mine opportunities
Near-mine opportunities For personal use only Central E, Far East area. Herbert Creek East Narrow HG intercepts Potential low strip at depth. Generally resource shallow drilling V2 East Depth extensions under HG underground and surrounding A39 and V2 pits, limited deep drilling Mt Carlton United 24
Slide 25: Greenfields opportunities
Greenfields opportunities For personal use only 25
Slide 26: Discovery project pipeline
Discovery project pipeline For personal use only Curve shows incremental value creation 26
Slide 27: Appendix
For personal use only Appendix
Slide 28: Resources
Resources Gold - Mt Carlton Mineral Resources - December 2012 For personal use only Measured Indicated Inferred Total Resource Mineral Resource Cont. Cont. Cont. Cont. Tonnes Grade Tonnes Grade Tonnes Grade Tonnes Grade Metal Metal Metal Metal (Mt) Au (g/t) (Mt) Au (g/t) (Mt) Au (g/t) (Mt) Au (g/t)
Slide 29: Reserves
Reserves Gold - Mt Carlton Ore Reserves - December 2012 For personal use only Proved Probable Total Reserve Ore Reserve Cont. Cont. Cont. Tonnes Grade Tonnes Grade Tonnes Grade Metal Au Metal Au Metal Au (Mt) Au (g/t) (Mt) Au (g/t) (Mt) Au (g/t) (koz) (koz) (koz) A39 - - - - - - - - - V2 4.52 3.1 44
Slide 30: Competent person statement
Competent person statement The information in this presentation that relates to exploration results, Mineral Resources or Ore For personal use only Reserves listed in the table below is based on work compiled by the person whose name appears in the same row, who is employed on a full-time basis by t