Knr Constructions Limited · NSE:KNRCON

Knr Constructions — Investor Presentation (May 2016)

51 slides from Knr Constructions's investor presentation, May 2016

  1. Slide 1: Investor Presentation

    Investor Presentation May 2016 KNR House, 3rd & 4th Floor, Plot No.114, Phase-1, Kavuri Hills, Jubilee Hills, Hyderabad - 500 033 A Well Established Name in Roads & Highway Constructions Phone No. 040-40268759/61/62, Fax No. 040-40268760 E-mail: info@knrcl.com

  2. Slide 2: Disclaimer

    Disclaimer This presentation and the accompanying slides (the “Presentation”), which have been prepared by KNR Constructions Limited (the “Company”), have been prepared solely for information purposes and do not constitute any offer, recommendation or invitation to purchase or subscribe for any secu

  3. Slide 3: Key Highlights & Result Update

    Key Highlights & Result Update 3

  4. Slide 4: Standalone Financial Highlights

    Standalone Financial Highlights Revenue EBITDA PAT 16% +30% +138% 2,958 451 580 2,557 347 244 Q4 FY15 Q4 FY16 Q4 FY15 Q4 FY16 Q4 FY15 Q4 FY16 Revenue EBITDA PAT +3% +23% +121% 8,761 9,026 1,554 1,611 1,261 730 FY15 FY16 FY15 9m FY16 FY15 FY16 Rs. in Million 4

  5. Slide 5: Key Highlights

    Key Highlights  Growth in Profit after Tax  Due to tax refund of previous years on account of 80IA benefit and interest on tax refund classified as other Income  Our share of profit in one of the JV entity towards claim which included in other operating income  Robust Orderbook  Received Rs. 28

  6. Slide 6: Standalone Financial Results

    Standalone Financial Results Rs. Million Q4 FY16 Q4 FY15 YoY Total Revenue 2,958.4 2,556.7 16% Operating Expenses 2,029.5 1,591.5 Employees Expenses 115.7 110.3 Other Expenditure 361.9 507.8 EBITDA 451.3 347.1 30% EBITDA margin 15.3% 13.6% Other Income 153.7 54.0 Depreciation 109.8 125.8 Interest 40

  7. Slide 7: Standalone Financial Results

    Standalone Financial Results Rs. Million FY16 FY15 YoY Total Revenue 9,025.5 8,761.3 3% Operating Expenses 6,062.9 5,965.5 Employees Expenses 435.2 380.8 Other Expenditure 973.3 1,153.6 EBITDA 1,554.1 1,261.4 23% EBITDA margin 17.2% 14.4% Other Income 304.9 124.6 Depreciation 431.4 540.6 Interest 12

  8. Slide 8: Standalone Balance sheet

    Standalone Balance sheet Rs. in Million Mar-16 Mar-15 Rs. in Million Mar-16 Mar-15 Shareholder’s Fund 7,270 5,692 Non-Current Assets 7,689 5,254 Share capital 281 281 Fixed Assets 2,468 2,269 Reserves & Surplus 6,988 5,411 Non-current Investments 355 228 Minority Interest 0 0 Deferred Tax Assets (Ne

  9. Slide 9: Business Overview

    Kurc KNR CONSTRUCTIONS LIMITED Business Overview

  10. Slide 10: Business Overview

    Business Overview  One of the leading companies providing Engineering, Procurement and Construction (EPC) services  To develop KNRCL as a  Major Projects in Roads & Highways – one of the fast growing sector Centre of excellence in  Established presence in Irrigation and Urban Water Infrastructur

  11. Slide 11: Transformation

    Transformation 2015 2/4 laning of Madurai – Ramanathapuram Section of NH-49 in the State of Tamil Nadu under NHDP Phase-III on EPC mode worth Rs. 9,371 mm 2013 3rd BOT Toll project worth Rs.9,005 mn in Kerala 2012 Early completion of Biggest Road Project – Bijapur Hungund Section of Rs. 8,250 mn - 1

  12. Slide 12: Management

    Management… Mr. K.Narasimha Reddy – Founder Promoter & Managing Director  Over 46 years of experience in the Highway sector  Started career in 1968 and engaged in the business of undertaking civil and mechanical contracts  Extensive knowledge and experience in multi project planning Scheduling, c

  13. Slide 13: Supported by Professional Team

    Supported by Professional Team Mr. T.L. Verma (Vice President - Projects) Mr. D. Tirupathi Reddy (GM – Projects)  A Bachelor of Engineering (BE) from MITS  Over 24 years of rich experience in various fields Gwalior (MP) with Over 35 years of total of Civil Engineering experience with ~20 years of

  14. Slide 14: Key Business Strengths

    Kurc KNR CONSTRUCTIONS LIMITED Key Business Strengths 14

  15. Slide 15: Project execution

    1. Project execution Significant experience and Strong track record in timely execution of Projects  Top management’s active Scheduled Completion (Days) involvement at all stages of Project Actual Completion (Days) execution  Selection of Major Raw Material  Selection of construction Camp locatio

  16. Slide 16: Pan India Project Execution Capability

    Pan India Project Execution* Capability Arunachal Pradesh Bihar No of Projects 1 Uttar Pradesh Value of Projects Rs. 920 mn No of Projects 4 No of Projects 1 Value of Projects Rs. 1,411 mn Value of Projects Rs. 1,704 mn Assam No of Projects 2 Madhya Pradesh Value of Projects Rs. 1,913 mn No of Proje

  17. Slide 17: Project Execution Highlights

    Project Execution Highlights  Cement Concrete Road  Completed Widening to 4/6 lanes and Strengthening of Existing two lane carriageway of NH – 5 in the State of Orissa for a length of 56.0 Kms with total contract value of work is Rs 2,310 mn  Existing road was widened & strengthened with flexible

  18. Slide 18: In-house Construction Equipment

    2. In-house Construction Equipment World Class Construction Equipments Use of Right tools for right work Sl. No. Name Of The Machinery Qty 1 Tippers 614 2 Excavators 145 3 Compactors 70 4 Concrete Mixers And Pumps 99 5 Loaders 41 6 Pavers 34 7 Crushers 14 8 Graders 31 9 Tractors 28 10 Cranes 34 250

  19. Slide 19: In-house Execution Team

    3. In-house Execution Team In-house team of 800 Qualified and experienced employees led by proven management team 1% 6% 36% 22% Project Engineering Site Supervision Site Engineers Equipment Operators 35% Admin & Office Staff 19

  20. Slide 20: Reputed Clientele

    4. Reputed Clientele National Highways Authority of Andhra Pradesh Road Development India (NHAI) Corporation (APRDC) Ministry of Road Transport & Hyderabad Growth Corridor Limited Highways (MoRTH) (HGCL) Karnataka State Highway Karnataka Road Development Improvement Project (KSHIP) Corporation (KRDC

  21. Slide 21: Reputed Clientele (cont.)

    4. Reputed Clientele (cont.) A.P. Irrigation (Government of Andhra GMR Projects Private Limited Pradesh) Engineers India Limited (Government of India Sadbhav Engineering Limited Undertaking) Public Works Department Oriental Structural Engineers Pvt. (Government of Arunachal Ltd. Pradesh) 21

  22. Slide 22: BOT Portfolio

    Kurc KNR CONSTRUCTIONS LIMITED BOT Portfolio 22

  23. Slide 23: BOT Portfolio – Completed Projects

    BOT Portfolio – Completed Projects Patel KNR Heavy Infrastructures Limited Particulars Patel KNR Infrastructures limited (PKIL) (PKHIL) Stake 40 % 40 % Project Details Project Type Road-Annuity Road-Annuity State Karnataka Telangana JV Partner PEL PEIL Client NHAI NHAI Length(KM) 60.00 53.00 Concess

  24. Slide 24: BOT Portfolio – Completed Projects

    BOT Portfolio – Completed Projects Particulars KNR Walayar Tollways Private Limited Stake 100% Project Detail Project Type Road-Toll State Kerala JV Partner - Client NHAI No of Lanes Two to Four Length(KM) 54.00 Concession Start Date 18th May 2013 Concession Period 20 Years Scheduled COD 15th Nov.20

  25. Slide 25: BOT Portfolio – Under Construction

    BOT Portfolio – Under Construction Particulars KNR Muzaffarpur Barauni Tollway Private Limited Stake 51% Project Detail Project Type Road-Toll State Bihar JV Partner JKM Infra Project Ltd Client NHAI No of Lanes Two Length(KM) 108 Concession Start Date 8th July 2012 Terms Concession Period 21 Years

  26. Slide 26: Walayar–Vadakkancherry Project

    Walayar –Vadakkancherry Project  KNR Walayar Tollways Private Limited is a wholly owned subsidiary of KNR Constructions Limited, incorporated as an SPV for execution of Walayar Road Project  Provisional Completion Certificate for 100% of Project length has been issued for the project on 16th Octob

  27. Slide 27: Muzaffarpur - Barauni Project

    Muzaffarpur - Barauni Project  KNR Muzaffarpur Barauni Tollway Private Limited is a Step down subsidiary of KNR Constructions Limited, incorporated as an SPV for execution of Muzaffarpur -Barauni Road project on BOT (Toll) basis  Overall Progress as on 31st March 2016  Physical Progress: 92.24% a

  28. Slide 28: Order Book & Business Strategy

    Order Book & Business Strategy 28

  29. Slide 29: Order-book Break-up

    Order-book Break-up Order book of Rs. 34,635 million as on 31st March 2016 State Govt. Other 47% 99% Pvt. Cos. Projects Captive 1% 1% International Order* 7% Central Govt. 44% Captive State Govt. Central Govt. International Order* Pvt. Cos. Projects * - Government of People's Repubilc Of Bangladesh

  30. Slide 30: Order-book Highlights

    Order-book Highlights Roads - Key Projects Rs. mln Non Captive Madurai -Ramanathpuram Section of NH-49 8,294 Irrigation 98% 2% Roads - Thiruvananthapuram Bypass 6,055 Captive 0% Upgrading Arcot Villupuram Road 3,180 Two Tier Flyover in Salem, Tamil Nadu 2,952 Chittagong City outer Ring Road,Banglade

  31. Slide 31: Order-book: State-wise

    Order-book: State-wise Madhya Pradesh Arunachal Pradesh No of Projects 3 No of Projects 1 Balance Value Rs. 2,930 mn Balance Value Rs. 557 mn Karnataka AP & Telangana No of Projects 8 No of Projects 8 Balance Value Rs. 1,452 mn Balance Value Rs. 1,583 mn Tamil Nadu Kerala No of Projects 8 No of Proj

  32. Slide 32: Recent Order Wins

    Recent Order Wins Order-book of Rs. 45,542 million as on 30th May, 2016* 10,907 45,542 Key Projects Rs. mln 34,635 Formation of Veeranjaneya Reservoir at Yedula(V), Gopalpet (M) and Earth work excavation of approach channel, Open Canal Including Constructions of CM & 6,758.41 CD Work from Anjanagiri

  33. Slide 33: Business Strategy

    Business Strategy Focus on Projects involving Higher degree of engineering skills Continuously Focus on securing explores growth EPC contracts from opportunities by reputed Clients and forming strategic Concessionaire Joint Ventures (JVs) Capitalise on Opportunity of Execute all the huge Infrastruct

  34. Slide 34: Financial Highlights

    Kurc KNR CONSTRUCTIONS LIMITED Financial Highlights 34

  35. Slide 35: Consolidated Financial Results

    Consolidated Financial Results Rs. Million FY16 FY15 YoY Total Revenue 9,951.2 9,311.9 7% Operating Expenses 6,634.5 6,470.8 Employees Expenses 466.9 382.3 Other Expenditure 1,108.0 1,191.0 EBITDA 1,741.9 1,267.8 37% EBITDA margin 17.5% 13.6% Other Income 424.1 128.9 Depreciation 480.7 551.7 Interes

  36. Slide 36: Consolidated Balance sheet

    Consolidated Balance sheet Rs. in Million Mar-16 Mar-15 Rs. in Million Mar-16 Mar-15 Shareholder’s Fund 6,970 7,885 Non-Current Assets 14,563 15,165 Share capital 281 281 Fixed Assets 12,631 13,432 Reserves & Surplus 6,688 7,604 Non-current Investments 168 236 Minority Interest 807 906 Deferred Tax

  37. Slide 37: Standalone Financial Highlights

    Standalone Financial Highlights Financial Year 2010 2011 2012 2013 2014 2015 2016 Rs. 7,125 Rs. 7,930 Rs. 7,505 Rs. 6,921 Rs. 8,348 Rs. 8,761 Rs. 9,025 Turnover $118.6 $132.0 $125.0 $115.2 $139.0 $140.0 $136.1 Rs. 1,121 Rs. 1,356 Rs. 1,338 Rs. 1,164 Rs. 1,258 Rs. 1,261 Rs. 1,554 EBITDA $18.7 $22.6 $

  38. Slide 38: Standalone Financial Highlights

    Standalone Financial Highlights Revenue & EBITDA (Margin %) EBITDA Margin (%) 15.7% 17.1% 17.8% 16.8% 15.1% 14.4% 17.2% 8,761 9,026 7,930 8,348 7,125 7,505 6,921 Revenue 1,356 1,338 1,164 1,258 1,261 1,554 1,121 EBITDA 2010 2011 2012 2013 2014 2015 2016 Net Profit & Net Worth (RoE) RoE (%) 16.7% 16.

  39. Slide 39: Standalone Net Working Capital Days

    Standalone Net Working Capital Days 79 69 53 52 48 98 43 52 74 66 64 45 51 53 26 23 28 7 10 13 16 16 15 18 15 20 15 17 Mar-10 Mar-11 Mar-12 Mar-13 Mar-14 Mar-15 Mar-16 Inventory Debtors Creditors Net Working Capital 39

  40. Slide 40: Shareholding Pattern as on 31st March 2016

    Shareholding Pattern as on 31st March 2016 Shareholders Holding more than 1% of the Equity % to Equity (Other than Promoters) 11% HDFC Mutual Fund 8.35% Tata Mutual Fund 3.76% 24% 61% ICICI Prudential Mutual Fund 3.04% 3% L&T Mutual Fund 1.08% PROMOTERS Franklin Mutual Fund 1.87% FOREIGN INST. INVES

  41. Slide 41: Other Businesses

    Other Businesses  Strong growth opportunity in development of Agricultural Infrastructure Irrigation & Water Management Projects  Execution of Irrigation & Water Supply Projects with Joint Venture Partners And Urban Water  Executed 3 Projects in Telangana & 1 Project in Infrastructure Bihar Manag

  42. Slide 42: Project Gallery

    Kurc KNR CONSTRUCTIONS LIMITED Project Gallery 42

  43. Slide 43: Completed Projects

    Completed Projects BOT (Annuity) Road Project on NH-7 in the BOT (Annuity) Road Project on NH-7 in the State of Telangana State of Telangana 43

  44. Slide 44: Completed Projects

    Completed Projects BOT (Annuity) Road Project on NH-7 in the Four Lane Highway on NH-50, Bijapur to State of Karnataka Hungund Project in the State of Karnataka 44

  45. Slide 45: Completed Projects

    Completed Projects Road Project in the state of Karnataka - Road Project in the state of Karnataka - Bijapur - Hungund Bijapur - Hungund 45

  46. Slide 46: Completed Projects

    Completed Projects Walayar –Vadakkancherry BOT (Toll Road ) Walayar –Vadakkancherry BOT (Toll Road ) Project, Kerala Project, Kerala 46

  47. Slide 47: Completed Projects

    Completed Projects Bridge across River Godavari in Telangana State 47

  48. Slide 48: Completed Projects

    Completed Projects Bridge across River Godavari in Telangana Bridge across River Godavari in Telangana State State 48

  49. Slide 49: Under-Construction Projects

    Under-Construction Projects Muzaffarpur -Barauni Road project on BOT Muzaffarpur -Barauni Road project on BOT (Toll), Bihar (Toll), Bihar 49

  50. Slide 50: Under-Construction Projects

    Under-Construction Projects Flyover at Coimbatore in the State of Tamil Irrigation Project in Telangana State Nadu 50

  51. Slide 51: For further information, please contact

    For further information, please contact: Company : Investor Relations Advisors : KNR Constructions Ltd Strategic Growth Advisors Pvt. Ltd. CIN: L74210DL1995PLC238364 CIN: U74140MH2010PTC204285 Mr. K. Venkata Ram Rao Mr. Jigar Kavaiya / Mr. Kevin Shah (GM - Finance & Accounts) +91-9920602034 / +91 97