Freehill Mining Ltd. · ASX:FHS

Freehill Mining — Corporate Update (June 2020)

11 slides from Freehill Mining's corporate update, Jun 3, 2020

  1. Slide 1: Release of YB6 structure JORC Mineral Resource Estimate

    Freehill Mining Limited (ASX: FHS) Release of YB6 structure JORC Mineral Resource Estimate Investor Stream Webinar Update - June 2020 Peter Hinner – Chief Executive Officer

  2. Slide 2: Important Information and Disclaimer

    Important Information and Disclaimer The information contained in this Presentation is of a general nature and does not purport to include or summarise all information that an investor should consider when making an investment decision. The Presentation does not contain all the information which wou

  3. Slide 3: Project Highlights

    Project Delivered 2 mineral resources & 5 targets remain undrilled All drilling planned and executed in <18 months Highlights Low operating cost & low capital cost Quick path to production – sinter feed model Scaleable production Excellent location Excellent infrastructure Local & unique buyer Alrea

  4. Slide 4: JORC Resource Areas

    JORC Resource Areas Paseene / YB1 resource > 18.4Mt @ 15.1%Fe YB6 resource 49.3 Mt @ 20.6%Fe

  5. Slide 5: 2020 Objectives for YB Magnetite Project

    2020 Objectives for YB Magnetite Project • Focus on tasks that work toward getting a mine up and running • Metallurgical works to develop a processing flowsheet • Conceptual mine plan • Prepare DIA & submit to apply for mining licence • Run Pre-feasibility study in parallel with DIA • Deliver econom

  6. Slide 6: 2020 JORC Mineral Resource Estimate

    2020 JORC Mineral Resource Estimate 2 Mass %Fe Head Concentrate Grades Structure Category Tonnes Mt 1 %Recovery Grade %Fe %Al2O3 %SiO2 %P %S YB1 Inferred 13.4 14.7 14.8 68.1 0.67 1.47 0.023 0.026 Indicated 5.0 15.8 15.9 69.1 0.69 1.36 0.018 0.022 Total 18.4 15 15.1 68.4 0.68 1.44 0.020 0.025 YB6 Inf

  7. Slide 7: Additional Resource

    Additional Resource • 7 magnetic structures identified • 2 drilled and 2 resources confirmed • Both resources in easily developed areas • Investigate at how best to increase grade each resource • 5 more structures to be drilled • Have met or exceeded the tonnes estimated in Conceptual Exploration ta

  8. Slide 8: Geophysics Targets

    Geophysics Targets YB1 Resource 18.4 Mt @ 15.1% Fe & 15% magnetics YB6 Resource 49.3 Mt @ 20.6 %Fe & 27.7% magnetics 5 other magnetic targets yet to be drilled ? 8

  9. Slide 9: Sales & Transport Solutions

    Sales & Transport Solutions • Proven 3 year sales agreement with Chiles largest pellet feed producer • 3-4 sales and transport solutions available • 2 existing ports and 1 port approved for development all within 18-51kms of project 9

  10. Slide 10: Example of a magnetite concentrate

    Example of a magnetite concentrate project 270kms north of Yerbas Buenas that produces a sinter feed for direct export 10

  11. Slide 11: Contact: Freehill Mining Limited (ASX:FHS)

    Contact: Freehill Mining Limited (ASX:FHS) T: 03 8658 5976 E: info@freehillmining.com.au W: www.freehillmining.com.au 11

Freehill Mining — Corporate Update (June 2020) on 6ix