Royal Bafokeng Platinum Ltd

Royal Bafokeng Platinum — FY2017 Earnings Presentation

33 slides from Royal Bafokeng Platinum's earnings presentation, 2018

  1. Slide 1: Audited Annual Results

    Slide 1: Audited Annual Results

    Audited Annual Results For the year ended 31 December 2017

  2. Slide 2: Contents

    Slide 2: Contents

    CONTENTS Overview Market Review Operational Review Financial Review Outlook

  3. Slide 3: Overview

    Slide 3: Overview

    OVERVIEW

  4. Slide 4: Strong performance despite challenging conditions

    Slide 4: Strong performance despite challenging conditions

    Strong performance despite challenging conditions > No fatalities, in line with our commitment to zero harm > Two million fatality-free shifts on 20 July 2017 SAFETY, HEALTH and ENVIRONMENT > Reduction in the HIV prevalence rate and the TB incidence rate > Awarded a position on the 2017 CDP A list f

  5. Slide 5: Market Review

    Slide 5: Market Review

    oe, ¥ ee” = / MARKET

  6. Slide 6: Platinum demand to increase marginally in 2018

    Slide 6: Platinum demand to increase marginally in 2018

    Platinum demand to increase marginally in 2018 Global platinum supply forecast Global platinum demand forecast 9,0 8 200 Peak = 6.9 2.0 8,0 2.0 8 000 7,0 2014 = 4.9 6,0 5.9 7 800 35 (46) (97) 60 5,0 110 138 Moz 7 600 4.2 (70) 50 koz 4,0 5.3 3,0 7 400 2,0 3.1 7 580 7 580 7 200 7 490 7 490 1,0 0,0 7 0

  7. Slide 7: Palladium market set to be in a structural deficit of >1Moz in 2018

    Slide 7: Palladium market set to be in a structural deficit of >1Moz in 2018

    Palladium market set to be in a structural deficit of >1Moz in 2018 Global palladium supply forecast Global palladium demand forecast 10,0 10 600 2.3 2.4 9,0 Peak = 7.0 10 400 65 35 (35) (70) 8,0 (17) (85) 2014 = 6.4 (1) (71) 7,0 6.8 10 200 6,0 Moz koz 5,0 10 000 4,0 9 800 10 270 10 270 3,0 10 180 1

  8. Slide 8: Operational Review

    Slide 8: Operational Review

    OPERATIONAL REVIEW

  9. Slide 9: Strategy continues to drive value creation and competitive operating platform

    Slide 9: Strategy continues to drive value creation and competitive operating platform

    Strategy continues to drive value creation and competitive operating platform Towards Operational Excellence Build Flexibility > Two million fatality free shifts, > BRPM operational flexibility however disappointing injury maintained frequency rates > Maseve acquisition – additional > Continued labo

  10. Slide 10: Operational flexibility enhanced by the acquisition of Maseve

    Slide 10: Operational flexibility enhanced by the acquisition of Maseve

    Operational flexibility enhanced by the acquisition of Maseve Phase I – Plant transaction Phase II – Share transaction > Key assets include: > Key assets include: • Concentrator plant • Maseve mineral rights • Associated surface infrastructure and TSF • Surface rights • Surface rights for purposes o

  11. Slide 11: Safe production remains our number one priority

    Slide 11: Safe production remains our number one priority

    Safe production remains our number one priority Description Unit 2015 2016 2017 % Var Serious injury frequency rate Total injury frequency rate 0,35 2,50 Fatal injuries No. 5 1 - 100 2,112 0,30 0,287 2,035 LTIFR rate 0.409 0.380 0.562 (47.9) 2,00 0,25 SIFR rate 0.133 0.216 0.287 (32.9) 0,216 /200 00

  12. Slide 12: Employee health is a critical factor for our strategic objective

    Slide 12: Employee health is a critical factor for our strategic objective

    Employee health is a critical factor for our strategic objective Health Environment > Roll out of personalised hearing protection > Long-term environmental economic sustainability > Our efforts to improve the health of our employees: > A global leader in sustainable water management (CDP) HIV > Impr

  13. Slide 13: Solid mining performance at BRPM and Styldrift

    Slide 13: Solid mining performance at BRPM and Styldrift

    Solid mining performance at BRPM and Styldrift Description Unit 2015 2016 2017 % Var > BRPM development  6.1% − remains aligned with depletion rates Total development km 35.5 36.2 36.1 (0.3) > BRPM IMS panel ratio of 1.68 BRPM km 33.9 31.1 29.3 (5.8) Styldrift capital development km 1.6 5.0 6.8 36.

  14. Slide 14: 250ktpm concentrator upgrade supports Styldrift ramp-up

    Slide 14: 250ktpm concentrator upgrade supports Styldrift ramp-up

    250ktpm concentrator upgrade supports Styldrift ramp-up Tonnes milled - total Pt metal in concentrate Description Unit 2015 2016 2017 % Var 3 500 Styldrift 250 572 Total tonnes milled kt 2 461 2 762 3 021 9.4 Styldrift 212 3 000 Styldrift 414 196 BRPM kt 2 389 2 348 2 449 4.3 72 200 180 2 500 Styldr

  15. Slide 15: Restructuring process drives improved business performance

    Slide 15: Restructuring process drives improved business performance

    Restructuring process drives improved business performance Total working cost labour Mining capital labour Description Unit 2015 2016 2017 % Var 7 000 3 000 Total labour No. 7 255 7 374 8 350 (13.2) 6 256 6 271 2 659 6 000 5 691 2 500 Working cost labour No. 6 256 6 271 5 691 9.2 5 000 Capital labou

  16. Slide 16: Year-on-year reduction in cash operating unit costs

    Slide 16: Year-on-year reduction in cash operating unit costs

    Year-on-year reduction in cash operating unit costs Cash operating cost / tonne milled Cash operating cost / Pt oz Description Unit 2015 2016 2017 % Var 1 400 18 000 Cash operating costs R'm 2 548 2 765 2 815 (1.8) 1 177 1 149 15 639 15 414 1 200 16 000 1 066 14 504 Cash operating cost/tonne milled

  17. Slide 17: Increase in expansion capital aligned to Styldrift 150ktpm ramp-up

    Slide 17: Increase in expansion capital aligned to Styldrift 150ktpm ramp-up

    Increase in expansion capital aligned to Styldrift 150ktpm ramp-up Description Unit 2015 2016 2017 % Var Stay-in-business capital (SIB) R'm 112 110 118 7.3 Stay-in-business R118 million - 4.2% of operating cost SIB % of operating cost % 4.4% 4.0% 4.2% 5.0 capital ˃ Expenditure in line with ongoing o

  18. Slide 18: Styldrift I project progress: ramp-up to 150ktpm in Q4 2018

    Slide 18: Styldrift I project progress: ramp-up to 150ktpm in Q4 2018

    Styldrift I project progress : ramp-up to 150ktpm in Q4 2018 Styldrift ramp-up Description Unit 2015 2016 2017 Capital expenditure 3 000 2 760 2 760 Annual R’bn 1.66 0.97 2.01 2 455 2 500 Project-to-date R’bn 5.48 6.45 8.46 2 050 2 000 Project progress Development m 1 602 5 018 6 834 kt 1 500 1 400

  19. Slide 19: Flexibility key to successful ramp-up

    Slide 19: Flexibility key to successful ramp-up

    Flexibility key to successful ramp-up Key focus areas: Services Shaft Ventilation shafts 1,2 and 3 Main Shaft > Ore handling infrastructure > Ore reserve development > Production infrastructure Legend Development completed end 2016 Shaft infrastructure development completed 2017 Decline and infrastr

  20. Slide 20: Financial Review

    Slide 20: Financial Review

    FINANCIAL REVIEW

  21. Slide 21: Increase in profitability due to improved operational performance

    Slide 21: Increase in profitability due to improved operational performance

    Increase in profitability due to improved operational performance YoY Description Unit 2017 2016 % change Average basket price R/Pt oz 19 156 18 906 1.3 Average R:US$ exchange rate R:US$ 13.29 14.21 (6.5) Revenue R’m 3 498.5 3 342.2 4.7 Cost of sales R’m (3 186.5) (3 101.5) (2.7) Gross profit R’m 31

  22. Slide 22: Strong cash generation and cash position at year end

    Slide 22: Strong cash generation and cash position at year end

    Strong cash generation and cash position at year end YoY Description Unit 2017 2016 % change Cash generated by operating activities R’m 618.4 585.3 5.7 Cash and cash equivalents R’m 1 333.1 835.5 59.6 - 100% BRPM R’m 571.2 370.5 54.1 - RBPlat corporate office R’m 696.5 426.0 63.5 – RBRP (housing pro

  23. Slide 23: Improvement in all US$ metal prices except platinum

    Slide 23: Improvement in all US$ metal prices except platinum

    Improvement in all US$ metal prices except platinum Revenue contribution - 2017 Description Unit 2017 2016 2,2% 1,0% 5,9% 1,0% Volume* US$ Volume* US$ 1,7% 6,8% Platinum oz 182 638 934/oz 176 777 984/oz 3,4% 2017 55,1% Palladium oz 75 593 939/oz 73 668 658/oz 22,9% Gold oz 8 220 1273/oz 7 989 1 238/

  24. Slide 24: Diminished correlation between US$ metal prices and ZAR:US$ exchange rate

    Slide 24: Diminished correlation between US$ metal prices and ZAR:US$ exchange rate

    Diminished correlation between US$ metal prices and ZAR:US$ exchange rate 7 Year 5 Year 3 Year 2 Year 1 Year 0,3 0,2 0,2 0 -0,1 -0,1 -0,1 -0,1 -0,2 -0,2 -0,4 -0,5 -0,6 -0,8 -0,8 -0,8 -0,8 -1 -0,9 Platinum Gold Rhodium Palladium Source: Treasury One Audited Annual Results For The Year Ended 31 Decemb

  25. Slide 25: Marginal increase in cost of sales

    Slide 25: Marginal increase in cost of sales

    Marginal increase in cost of sales 2017 2017 YoY 2016 2016 Description R million % of total % change R million % of total Labour 1 077.5 38.2% (0.5%) 1 072.4 38.4% Utilities 264.9 9.3% (4.9%) 252.5 9.1% Contractor costs 791.8 28.0% (12.9%) 701.6 25.2% Materials and other mining costs 681.0 24.1% 7.7

  26. Slide 26: Increase in depreciation, amortisation, restructuring costs

    Slide 26: Increase in depreciation, amortisation, restructuring costs

    Cents/share 0 25 50 75 100 125 150 175 Headline earnings per share: 2016 86.7 Revenue - improved realised average rand 10.0 basket Revenue - increased volumes 29.1 Audited Annual Results For The Year Ended 31 December 2017 Increase in other income 19.5 Headline earnings per share Restructuring costs

  27. Slide 27: "Normalised" headline earnings per share

    Slide 27: "Normalised" headline earnings per share

    “Normalised” headline earnings per share Group Year ended 31 December YoY Description Unit 2017 2016 % change Headline earnings R million 108.8 166.7 (34.7) Weighted average shares outstanding #m 192.7 192.1 0.3 Headline earnings per share R/share 0.56 0.86 (34.9) Restructuring costs R/share 0.17 -

  28. Slide 28: Decrease in non-controlling interest

    Slide 28: Decrease in non-controlling interest

    R’million -50 50 150 250 350 450 550 Headline earnings - 2016 166.7 Revenue - volume increase 116.4 Increase in costs due to increased volumes 114.0 Restructuring costs 49.0 194.6 controllable Increase in admin and other costs, 36.2 decrease in net finance income Audited Annual Results For The Year

  29. Slide 29: Cash flow movement and strong operational cash generation

    Slide 29: Cash flow movement and strong operational cash generation

    R’million RBPlat -400 -200 0 200 400 600 800 1 000 1 200 1 400 1 600 1 800 2 000 2 200 2 400 2 600 BRPM JV Cash and cash equivalents - 1 January 2017 465.0 370.5 835.5 Cash generated by operations 569.5 Interest, dividends and tax 48.9 1 069.5 Cash generated from Stydrift Incidental revenue 451.1 SI

  30. Slide 30: In summary

    Slide 30: In summary

    In summary > Year of two halves > Flat revenue basket price for the year > Completed successful restructuring/organisational redesign • 1.4% reduction in year-on-year cash unit costs • 2.6% reduction in cash fixed cost base from 74.4% to 71.8% of total cash costs • Enhanced quality of revenue stream

  31. Slide 31: Outlook

    Slide 31: Outlook

    f Tl Ml ee OUTLOOK ya

  32. Slide 32: Strongly positioned to achieve our goals in 2018

    Slide 32: Strongly positioned to achieve our goals in 2018

    Strongly positioned to achieve our goals in 2018 > Prospects of a market improvement for platinum in 2018 • A market that is close to balance, after investment, is likely > Ramp up Styldrift I to 150ktpm by year-end and incorporate Maseve into our business > Forecast 4E built-up head grade of 3.95g/

  33. Slide 33: Audited Annual Results

    Slide 33: Audited Annual Results

    Audited Annual Results For the year ended 31 December 2017