Atomic Eagle Ltd · ASX:AEU

Atomic Eagle — Investor Presentation (February 2021)

19 slides from Atomic Eagle's investor presentation, Feb 16, 2021

  1. Slide 1: Company Update Presentation

    Tombador Iron Limited ABN: 20 108 958 274 Suite 5, 85 Forrest Street Cottesloe WA 6011 16 February 2021 ASX ANNOUNCEMENT Company Update Presentation Perth, Australia; 16 February 2021. Tombador Iron Limited (ASX:TI1) (the “Company”) is pleased to release an updated Company presentation which reflect

  2. Slide 2: February 2021 Company Update

    February 2021 Company Update Price Premium Dividend 100% private focused ownership of lease High grade Fe Outcropping 67% BRAZIL massive low Existing: hematite Risk road links & port access Hematite Mineral mining Local Infrastructure: Resource* jurisdiction water, power, roads & towns 10 Crushing a

  3. Slide 3: Disclaimer

    Disclaimer These presentation materials have been prepared by the Company ("Tombador Iron Limited”). These Presentation Materials contain descriptive materials and other data relating to future events. These Presentation Materials are being delivered to certain parties with the understanding that th

  4. Slide 4: Investment Highlights

    Investment Highlights Tombador is a premium grade iron ore lump project moving towards production High-grade hematite lump Mineral Resource1 (Fe 67+%) Premium which is anticipated to command a healthy price Grade TOMBADOR premium Short time to • Production targeted by Q2 2021 Production • Project pl

  5. Slide 5: Update - Offtake Agreement

    Update - Offtake Agreement Offtake Agreement • The Company has executed a binding offtake agreement with Trafigura for the purchase of 100% of ore that Tombador chooses to sell into the export market • Comprehensive terms relating to sale, shipment, delivery and pricing, including additional working

  6. Slide 6: Update - Infill Drilling In Progress

    Update - Infill Drilling In Progress Infill and geotechnical drilling program is continuing: • The Company has drilled over 1700 meters of HQ core • The drill plan has been extended to drill 2500 meters with close-spaced infill to expedite mine planning • The company is currently preparing an initia

  7. Slide 7: Update – Mine Site Construction Complete

    Update – Mine Site Construction Complete • The Company has completed construction of the mine site facilities including the mine site offices, workshop, onsite laboratory and crushing and screening plant • All Construction site works are now complete and the Company is ready for the site inspection

  8. Slide 8: Update – Mine Site Construction Complete

    Update – Mine Site Construction Complete Site offices and administration infrastructure Canteen Site laboratory equipment for chemical analysis Site laboratory equipment for physical analysis 15 February 2021 7

  9. Slide 9: Update – First Blast

    Update – First Blast Pre-stripping underway • The first blast was fired on 5 February 2021 as part of pre-stripping to remove overburden • Access haul roads have been constructed • The mining contractor SEMEP, has completed mobilisation of the mining fleet to the Tombador mine site • Once the Mining

  10. Slide 10: Update - Licensing

    Update – Licensing Crushing and screening plant ready for operations The Company successfully commissioned the crushing and screening plant from Industria Mecânica Irmãos Corgozinho Ltda (“IMIC”) on 5 February 2021. The plant with a design capacity of up to 400 tonnes per hour is now ready to produc

  11. Slide 11: Update - Licensing

    Update - Licensing Mining Concession • PAE (feasibility study*) was approved by the National Mining Agency on the 1st of December 2020. The Company is now awaiting the Ministry of Mines and Energy (“MME”) to grant the Company’s Mining Concession. Operation License • The next licensing step is the si

  12. Slide 12: Mining Licensing on Track

    Mining Licensing on Track Construction Completed Environmental Mining Agency Environmental Licensing Department Tombador (ANM) (INEMA) • Preliminary Licence (LP) granted in 2018 • LP involves Social and Environmental approvals Preliminary Exploration Licence (LP) Licence • Installation Licence (LI)

  13. Slide 13: Development Milestones

    Development Milestones • Offtake agreement executed with Trafigura; • Site construction completed including the commissioning of the crushing and screening plant; • Project is ready for inspection by the environmental bureau (INEMA) for the award of the Operating Licence (LO); • Pre-stripping has co

  14. Slide 14: Company Overview

    Company Overview 15 February 2021 13

  15. Slide 15: Capital Structure

    Capital Structure Prospectus 15 Feb 2021 Substantial Shareholders Shares on issue Colomi Singapore *includes shares under escrow, 1,860,942,816 1,860,942,816 53.2% does not include performance & McRae Investments rights or options Escrowed Shares 102,785,273 102,785,273 12 months Escrowed Shares 1,0

  16. Slide 16: Directors and CEO

    Directors and CEO Proven expertise in Brazil mining, logistics, marketing and finance Anna Neuling (Chairman and Non-executive Director) 15 years of experience in financial and corporate roles in the resources industry with ASX listed companies including Sirius Resources NL, LionOre Mining Internati

  17. Slide 17: Mineral Resource

    Mineral Resource1 Drilling Deposit drilled at close spacing (25m-75m centres), logged, sampled and tested Completed Combined JORC Resource of 10.05Mt, comprising:  7.99Mt of high-grade hematite, and Classification Tonnes (Mt) Fe (%) SiO2 (%) Al2O3 (%) Measured2 1.94 67.04 1.95 0.47 JORC Indicated2

  18. Slide 18: Simple Mining Operation

    Simple Mining Operation Proposed production method • Open pit mine • Standard contract mining - drill & blast, load & haul • Short downhill haul • Simple processing: crush and screen (with no tailings) • Average lump yield of 75% in test work by MOPE1 Operations Flow Chart Mining - drill, Truck haul

  19. Slide 19: Company Contacts

    Company Contacts Gabriel Oliva CEO gabriel.oliva@tombadoriron.com Abby Macnish Niven COMPANY SECRETARY info@tombadoriron.com +61 8 6382 1805 Lucas Robinson INVESTOR RELATIONS lucas@corporatestorytime.com +61 408 228 889 www.tombadoriron.com 15 February 2021 18

Atomic Eagle — Investor Presentation (February 2021) on 6ix