Ze Pak Sa · GPW:ZEP

Ze Pak Sa — Q1 2026 Earnings Presentation

23 slides from Ze Pak Sa's earnings presentation, May 29, 2026

  1. Slide 1: 1Q'26 financial results

    1Q’26 financial results 29 May 2026

  2. Slide 2: Speakers

    Speakers ANDRZEJ MACIEJ KOŃSKI MACIEJ NIETOPIEL BARTŁOMIEJ DRYWA JANISZOWSKI VICE PRESIDENT OF THE VICE PRESIDENT OF THE VICE PRESIDENT OF THE MANAGEMENT BOARD MANAGEMENT BOARD, CFO MANAGEMENT BOARD VICE PRESIDENT OF THE ZE PAK S.A. ZE PAK S.A. ZE PAK S.A. MANAGEMENT BOARD ZE PAK S.A.

  3. Slide 3: Agenda

    Agenda 1. Key highlights 2. Energy market in Q1’26 3. Operating results 4. Development projects 5. Employment 6. Financial results

  4. Slide 4: Key highlights

    Key highlights Bartłomiej Drywa Vice President of the Management Board ZE PAK S.A.

  5. Slide 5: Key highlights in Q1'26

    Key highlights in Q1’26 o We are executing the CCGT unit in Turek according to plan – EPC works progress at 86% as at the end of Q1’26 o Discontinuation of coal operations in their current form – we have ceased continuous coal extraction and continuous electricity generation o We are accelerating th

  6. Slide 6: Energy market in Q1'26

    Energy market in Q1’26 Andrzej Janiszowski Vice President of the Management Board ZE PAK S.A.

  7. Slide 7: Energy market situation

    Energy market situation Energy prices TGeBASE (PLN/MWh) Futures contract price for EUA delivery (EUR/tonne) 700 650 95 600 90 550 85 80 500 450 75 76 450 70 70 400 443 65 350 60 300 55 kwiApr majMay czeJun lip Jul sie Aug wrzSep paźOct lis Nov gruDec sty Jan lut Feb mar Mar Apr May Jun Jul Aug Sep O

  8. Slide 8: Operating results

    Operating results Andrzej Janiszowski Vice President of the Management Board ZE PAK S.A.

  9. Slide 9: Growing pressure on the margins of conventional producers

    Growing pressure on the margins of conventional producers Electric energy sales Margin Q1’25 o Stable energy production +0.9% 458 462 o Slight decrease in average selling 597.1 46 65 price in Q1’26 by 2.3% y/y o Unit CO₂ emission cost increased by PLN/ MWh 273.3 412 397 36.2% y/y due to a significan

  10. Slide 10: Development projects

    Development projects Maciej Koński Vice President of the Management Board ZE PAK S.A.

  11. Slide 11: Construction of a gas-steam unit (CCGT) in Turek

    Construction of a gas-steam unit (CCGT) in Turek Progess status: o EPC progress: approx. 86% at the end of Q1’26 o Installation of the turbine-generator set, condenser, and heat recovery steam generator (HRSG) o Commencement of piping installation works in the turbine hall and boiler house o Complet

  12. Slide 12: Opole 500MW wind farm

    Opole 500MW wind farm Progress status : o Documentation works are ongoing to prepare the project for construction o Environmental monitoring has been completed, and all 7 environmental procedures have been launched – decisions expected in 2027 o Target timeline for achieving “Ready-to-Build” status

  13. Slide 13: Land reclamation

    Land reclamation o Land reclamation is being conducted in accordance with applicable legal requirements and environmental permits o In Q1’26, we submitted an application to have water-direction reclamation deemed complete at the Drzewce open pit (approx. 134 ha) o In Q1’26, we filed an application f

  14. Slide 14: Employment

    Employment Andrzej Janiszowski Vice President of the Management Board ZE PAK S.A.

  15. Slide 15: Employment restructuring in line with the principles of social responsibility

    Employment restructuring in line with the principles of social responsibility Change in employment o In Q1’26, workforce restructuring covered a total of 163 employees, including 76 who opted for one-off severance payments under the Social Protection Act o As at the end of Q1’26, 137 employees were

  16. Slide 16: Financial results

    Financial results Maciej Nietopiel Vice President of the Management Board ZE PAK S.A.

  17. Slide 17: Summary of ZE PAK Group's financial results

    Summary of ZE PAK Group’s financial results Revenue EBITDA Net result +34 mPLN 343 +0.1 mPLN +3.4 mPLN 309 36 74 22 29 -10.4 mln PLN mln PLN -5.4 -5.3 -13.8 mln PLN Q1'25 Q1'26 Q1'25 Q1'26 252 240 Q1'25 Q1'26 Own production Resale Other

  18. Slide 18: Revenue decomposition in Q1'26

    Revenue decomposition in Q1’26 o The dominant revenue stream – sales of own energy – remains in a downward trend due to lower production volumes and lower energy prices mPLN o Higher capacity market revenue due to a low base effect (no primary capacity Electricity Electricity Capacity Construction O

  19. Slide 19: EBITDA decomposition in Q1'26

    EBITDA decomposition in Q1’26 o EBITDA from the sale of energy from own production was impacted by the decline in the spread between the average energy mln PLN sales price and the average cost of CO2 emissions Electricity Electricity Capacity Construction Reclamation Share in Other EBITDA o Higher E

  20. Slide 20: Group indebtedness

    Group indebtedness Indebtedness structure Gross debt (as of 31.03.2026) 1 180 100% 100% 100% 582 mPLN Bank loan Currency - PLN Variable interest rate 31.12.2025 31.03.2026 Debt maturity profile (as of 31.03.2026) 141 141 141 141 141 141 0 35 mPLN 2026 2027 2028 2029 2030 …… 2040 2041 2042 Scheduled

  21. Slide 21: Q&A

    Q&A

  22. Slide 22: Disclaimer

    Disclaimer The information contained in this presentation may contain forward-looking statements, which are defined as all statements (except those relating to historical facts) regarding our financial results, business strategy, and objectives and plans for future operations (including plans for th

  23. Slide 23: Investor Relations

    Investor Relations ri@zepak.com.pl www.zepak.com.pl