Royal Bafokeng Platinum Ltd

Royal Bafokeng Platinum — Corporate Update (September 2012)

19 slides from Royal Bafokeng Platinum's corporate update, Sep 14, 2012

  1. Slide 1: Styldrift Project Reef intersection ceremony

    Slide 1: Styldrift Project Reef intersection ceremony

    Styldrift Project Reef intersection ceremony 14 September 2012 www.bafokengplatinum.co.za

  2. Slide 2: Disclaimer

    Slide 2: Disclaimer

    Disclaimer The information presented in this presentation is of a general nature and the forward looking information, opinions and beliefs of the Company and its affiliates are based on various market related assumptions. Changes in market circumstances after the production of the information may im

  3. Slide 3: Contents

    Slide 3: Contents

    Contents 1. Project history 2. Project description 3. Mining optimisation 4. Project progress 5. Capital expenditure 6. Operational readiness 7. Community development 8. Concentrator plant www.bafokengplatinum.co.za 2

  4. Slide 4: Project overview

    Slide 4: Project overview

    Project overview www.bafokengplatinum.co.za

  5. Slide 5: Project history

    Slide 5: Project history

    Project history Early Exploration • Drilling on the property was first conducted in 1966 • Potential for possible BRPM expansion to Styldrift identified in 1999 • Several drilling programs undertaken between 1966 and 2008 Project Approvals • Various studies conducted between 2000 and 2006, culminati

  6. Slide 6: Project description

    Slide 6: Project description

    Project description Description Shaft Infrastructure Features: • Expansion project Twin Vertical Shaft Access • 230 ktpm Merensky mine and concentrator • Main shaft (10.5m dia. lined) • Dual shaft access: Main shaft, Services shaft • Services shaft (6.5m dia. lined) • Bord and pillar mechanised mini

  7. Slide 7: Project description continued

    Slide 7: Project description continued

    Project description…..continued • Bord and pillar mechanised mining method • Investment proposal based on Merensky mined in areas between 1.8m and 2m mining only • Conventional mining • UG2 Feasibility study currently underway Merensky UG2 Total Description g/t Moz g/t Moz g/t Moz Mt Mt Mt (4E) (4E)

  8. Slide 8: Mining optimisation

    Slide 8: Mining optimisation

    Mining optimisation Optimisation study Styldrift Ramp-up 3 000 • Detailed mine design and layouts 1.7 Mt lower 2 500 • On-reef strike conveyors in place of 107 koz (4E) lower 2 000 footwall infrastructure for R&P mining ktpa 1 500 • Reduced bord widths from 13m to 8m 1 000 • Shaft depth increased 18

  9. Slide 9: Mining optimisation continued

    Slide 9: Mining optimisation continued

    Mining optimisation……continued Production: 3 500 • Production ramp up commences in Q3 3 000 2015, steady state reached in Q4 2018 2 500 • 16 stoping sections required for full ROM Tonnes (kt) 2 000 production 1 500 • Revised labour plan: 1 000 • Total peak labour R&P mining – 3200 500 • Total peak l

  10. Slide 10: Project progress

    Slide 10: Project progress

    Project progress • Earthworks completed in Q1 2010 • Main civils completed in Q3 2010 • Shaft sinking commenced Q4 2010 • Shaft sinking progress: • Main shaft: Merensky Reef level intersected - 15 August 2012 • Services shaft: 525m depth – 31 August 2012 • Overall progress: 33% • LTIFR to date: 1.61

  11. Slide 11: Project progress continued

    Slide 11: Project progress continued

    Project progress…..continued May 2010 – Bulk Earthworks complete August 2010 – Bulk Civils underway February 2011 – Headgears erected April 2011 – Winders Installed March 2012 – Rock winder civils August 2012 – Reef intersected commenced www.bafokengplatinum.co.za 10

  12. Slide 12: Capital expenditure

    Slide 12: Capital expenditure

    Capital expenditure Description Unit Mining Concentrator Total Rm 3 000 Authorised and Contingency R’m 6,289 1,422 7,711 2 500 2 000 Escalation R’m 3,153 938 4,091 1 500 Total Nominal R’m 9,442 2,360 11,802 1 000 500 Total Cost to Date R’m 1,537 11 1,548 0 2008 2009 2010 2011 2012 2013 2014 2015 201

  13. Slide 13: Operational Readiness

    Slide 13: Operational Readiness

    Operational Readiness • Early appointment of operational team - commenced in Q1 2012 • Focus on strategic mine operational framework creation and systematic capacity building for achieving Operational Readiness prior to commencement of production build up • Primary mining equipment selection process

  14. Slide 14: Community Development

    Slide 14: Community Development

    Community Development Development of local communities through sustainable opportunities within the 5 pillars of development in project “SPEED” initiative, namely: S: Social development and upliftment P: Procurement from local established SMMEs E: Employment directly to on site contractors E: Enterp

  15. Slide 15: Concentrator Plant

    Slide 15: Concentrator Plant

    Concentrator Plant • Pre-feasibility completed in Q1 2012 • Feasibility study commenced in Q2 2012 Process Flow Design • Feasibility study planned completion Q3 2013 • Commissioning completion planned for Q2 2016 • Tailings disposal facility site acquisition in progress www.bafokengplatinum.co.za 14

  16. Slide 16: Project impact: resources versus production

    Slide 16: Project impact: resources versus production

    Project impact • Merensky production growth at Styldrift I from 2017 • 2,760 Mtpa yielding 320koz 4E/annum • Total BRPM JV production 610koz 4E/annum • UG2 mining at Styldrift expected after 2040 with possible early co-extraction Resources versus production Bubble size = 4E PGM production 300 250 Zi

  17. Slide 17: Merensky impact continued: revenue per tonne hoisted

    Slide 17: Merensky impact continued: revenue per tonne hoisted

    Project impact….continued 2000 Revenue per tonne hoisted 1800 1600 1400 Merensky 1200 1000 R/tonne (4E) 800 UG2 600 400 200 0 Styldrift UG2 industry average Source: SFA (Oxford), company reports Styldrift UG2 industry average www.bafokengplatinum.co.za 16

  18. Slide 18: Project impact continued: shallow mines

    Slide 18: Project impact continued: shallow mines

    Project impact….continued • Styldrift at 740 mbs in a shrinking minority of shallow mines South Africa: 2012 South Africa: 2020 Source: SFA (Oxford), company reports 13% 35% 31% 18% 33% 34% 19% 17% <500 mbs 500 - 1000 mbs <500 mbs 500 - 1000 mbs 1000 - 1500 mbs + 1500 mbs 1000 - 1500 mbs + 1500 mbs

  19. Slide 19: Thank you

    Slide 19: Thank you

    Thank you www.bafokengplatinum.co.za

Source: company website

More decks from Royal Bafokeng Platinum Ltd