Grupo Aeroportuario Del Pacifico Sab De Cv Class B · BMV:GAP/B

Grupo Aeroportuario Del Pacifico Sab De Cv Class B — Investor Presentation (2013)

23 slides from Grupo Aeroportuario Del Pacifico Sab De Cv Class B's investor presentation, Jun 18, 2013

  1. Slide 1: Airport Infrastructure - An Overview

    Airport Infrastructure - An Overview: Current Projects Underway - GDL , TIJ Completed Projects - SJD, PVR, MLM, BJX Iñaki Ascacíbar Technical Officer

  2. Slide 2: Current Projects – Guadalajara

    Current Projects – Guadalajara Increase capacity for international operations • Total investment: US$ 20 million • Refurbishing and expansion of 10,000m2, including international arrivals and departures • 2 new gates and jetways • 2 new baggage carrousels • 20 immigration counters and 12 customs pos

  3. Slide 3: Current Projects – Guadalajara: Terminal building expansion

    Terminal building expansion Current Projects – Guadalajara Ground floor. Arrivals Page 3

  4. Slide 4: Current Projects – Tijuana: Terminal building expansion

    Terminal building expansion Current Projects – Tijuana First floor. Departures Page 4

  5. Slide 5: Current Projects – Guadalajara: Terminal building expansion

    Terminal building expansion Current Projects – Guadalajara Page 5

  6. Slide 6: Current Projects – Guadalajara: Apron expansion

    Refurbishing and apron expansion Current Projects – Guadalajara Increase Apron capacity • Total investment: US$ 20 million • 3 new positions for aircraft type C, in front of cargo facilities. • Refurbishing of 75,000m2 and 20 parking positions. Currently, general aviation and type B aircrafts are pa

  7. Slide 7: Current Projects – Guadalajara: Apron expansion

    Refurbishing and apron expansion Current Projects – Guadalajara Page 7

  8. Slide 8: Current Projects – Tijuana: Cross Border Facility

    Cross Border Facility Current Projects – Tijuana … on schedule • Civil Aviation has authorized a US$ 14.5 milliion investment for the airport integration with CBF. It will include the changes and expansion for customs, inmigration and international arrivals as well as bridge and building up to the a

  9. Slide 9: Current Projects – Tijuana: Cross Border Facility

    Cross Border Facility Current Projects – Tijuana IMMIGRATION CUSTOMS Southbound Northbound Page 9

  10. Slide 10: Current Projects – Tijuana: Cross Border Facility

    Cross Border Facility Current Projects – Tijuana Page 10

  11. Slide 11: Current Projects – Tijuana: Cross Border Facility

    Cross Border Facility Current Projects – Tijuana Page 11

  12. Slide 12: Completed Projects – Los Cabos: New Terminal T2

    New Terminal T2 Completed Projects – Los Cabos New Terminal 2 • Operational November 2012, with a total investment of US$ 63 million • New building with 35,000m2 in three levels and a capacity for 1,500 pax/hour on peak hours, (simultaneous arrival or departures) • 4 new jetways and connections with

  13. Slide 13: Completed Projects – Los Cabos: Level 0 Checking

    New Terminal T2 Completed Projects – Los Cabos Level 0. Checking TORRE DE ABORDAJE TORRE DE ABORDAJE TORRE DE ABORDAJE TORRE DE ABORDAJE CARRITOS BHS BACK OFFICE EN MEZZNINE TERMINAL 3 SALA DE DOCUMENTACION PUENTE VEHICULAR Page 13

  14. Slide 14: Completed Projects – Los Cabos: Arrivals

    New Terminal T2 Completed Projects – Los Cabos Level -6.60. Arrivals Page 14

  15. Slide 15: Completed Projects – Los Cabos: Departures

    New Terminal T2 Completed Projects – Los Cabos Level +6.60. Departures AEROPASILLO AEROPASILLO AEROPASILLO AEROPASILLO TERMINAL 3 ERPE Page 15

  16. Slide 16: Completed Projects – Los Cabos: New Terminal T2

    New Terminal T2 Completed Projects – Los Cabos Page 16

  17. Slide 17: Completed Projects – Puerto Vallarta

    Increase satellite terminal capacity Completed Projects – Puerto Vallarta Satellite terminal • Operational June 2012, with a Total investment US$ 12 million • 2.500 m2 in two levels, 4 new gates and jetways • Operational tower for apron management Rearrangement of airport access and parking • 150 ca

  18. Slide 18: Completed Projects – Puerto Vallarta

    Increase satellite terminal capacity Completed Projects – Puerto Vallarta Page 18

  19. Slide 19: Completed Projects – Guanajuato

    Increase terminal capacity Completed Projects – Guanajuato Arrivals and baggage area • Operational Feb 2013, US$ 4.5 million investment • 500m2 with two new baggage carrousels • Rearrangement of customs and immigration controls Page 19

  20. Slide 20: Completed Projects – Guanajuato

    Increase terminal capacity Completed Projects – Guanajuato Page 20

  21. Slide 21: Completed Projects - Morelia

    Increase terminal capacity Completed Projects - Morelia International arrivals • Operational March 2013 US$ 1.5 million investment • 400 m2 with a new baggage carrousel • Rearrange immigration and customs controls Page 21

  22. Slide 22: Completed Projects - Morelia

    Increase terminal capacity Completed Projects - Morelia Page 22

  23. Slide 23: Forward-looking statements notice (Spanish)

    Este documento puede contener en las declaraciones ciertas estimaciones. Estas declaraciones son hechos no históricos, y se basan en la visión actual de la administración de GAP de las circunstancias económicas futuras, de las condiciones de la industria, el desempeño de la com pañía y resultados fi