Slide 1: Building an Australian mid tier gold producer
For personal use only ASX:TAM February 2012 Building an Australian mid tier gold producer RIU Explorers Conference
Slide 2: Corporate
Corporate ASX Code: TAM Value For personal use only Shares on Issue 261.1 million Market Cap (A$0.785)1 A$205.0 million Cash and cash equivalents2 A$4.7 million Debt3 A$21.9 million Enterprise Value A$222.2 million 1. Share price at 20 February 2012 2. As at 31 December 2011 3. As at 20 February 201
Slide 3: Tanami Gold NL – Project Location
For personal use only Tanami Gold NL – Project Location 3
Slide 4: Tanami – A Compelling Investment Opportunity
Tanami – A Compelling Investment Opportunity Quality Gold Resources and Reserves 1 For personal use only Total Resources – 26Mt @ 3.1g/t for 2.6Mozs Total Reserves – 2.8Mt @ 3.9g/t for 0.35Mozs (LG stockpiles 0.05Mozs) Existing Production from Western Tanami Operation Underground operations
Slide 5: Tanami Gold - Project Snapshots
Tanami Gold - Project Snapshots Western Tanami Operations (100%) Central Tanami Project (100%) For personal use only Resources1 3,104,000t @ 5.4g/t for 538,000oz 21,277,000t @ 3.0g/t for 2,031,000oz Resource Class Approx. 55% Measured and Indicated Approx. 70% Measured and Indicated Reserves2 31/3/1
Slide 6: Western Tanami – Coyote & Bald Hill
For personal use only Western Tanami – Coyote & Bald Hill Coyote operations Coyote operations the centre of activity for the Western Tanami tenements Coyote – high grade underground operations commissioned late 2007 Coyote underground Resource1 880,000t @ 11.0g/t 312,000oz as at 30 September 2
Slide 7: Coyote Conceptual Exploration Model
For personal use only Coyote Conceptual Exploration Model 7
Slide 8: Western Tanami Exploration Potential
For personal use only Western Tanami Exploration Potential Multiple prospects to test, all within trucking distance of the Coyote treatment plant 2011-12 exploration budget $3-5M Model – single plant with feed from multiple ore sources 8
Slide 9: Central Tanami - Key Growth Driver
Central Tanami - Key Growth Driver For personal use only 9
Slide 10: Central Tanami Acquisition – March 2010
Central Tanami Acquisition – March 2010 Acquired from Newmont in March 2010 for $22M * For personal use only ~ 2.1Moz historic production Extensive infrastructure (power, water, etc) 0.5Mozs JORC Resource (2010) ~ 2,000 km2 exploration package 1.2Mtpa treatment plant 10
Slide 11: Central Tanami – Plant & Infrastructure In Place
Central Tanami – Plant & Infrastructure In Place For personal use only Central Tanami Plant 90km to the east of the Western Tanami operations 1.2Mtpa treatment plant ceased operations in 2005 after Newmont completed processing Groundrush open pit ore. Feasibility study to refurbish and increas
Slide 12: Central Tanami Project – Under Explored
Central Tanami Project – Under Explored 43 historic open pits For personal use only Historic production of >2 million oz Average depth of pits ~100m Majority drilled to ONLY 150m 64km of contiguous mining & exploration licences covering the main mineralised trend 12
Slide 13: Central Tanami Schematic Long Section
For personal use only Central Tanami Schematic Long Section 13
Slide 14: Central Tanami Schematic Long Section
For personal use only Central Tanami Schematic Long Section 14
Slide 15: Groundrush Open Pit – ML 22934
For personal use only Groundrush Open Pit – ML 22934 15
Slide 16: Groundrush - Minimal Historic Deep Drilling
For personal use only Groundrush - Minimal Historic Deep Drilling
Slide 17: Groundrush - Resource Growth April 2011
For personal use only Groundrush - Resource Growth April 2011
Slide 18: Groundrush - Resource Growth Sept 2011
For personal use only Groundrush - Resource Growth Sept 2011
Slide 19: Groundrush Resource Growth – Sept 2011
For personal use only Groundrush Resource Growth – Sept 2011
Slide 20: Groundrush Proposed Mine Plan
For personal use only Groundrush Proposed Mine Plan
Slide 21: Groundrush Open Pit – ML 22934
For personal use only Groundrush Open Pit – ML 22934 21
Slide 22: Groundrush – Drill Targets
For personal use only Groundrush – Drill Targets
Slide 23: Groundrush - high grade vein in NE end of current Resource
Groundrush - high grade vein in NE end of current Resource For personal use only 23
Slide 24: Groundrush Schematic Cross Section
For personal use only Groundrush Schematic Cross Section 24
Slide 25: Exploration Potential of Groundrush Dolerite
For personal use only Exploration Potential of Groundrush Dolerite ML 22934 – Ripcord evaluation and study suggests a Groundrush analogue...near term drill target 25
Slide 26: Central Tanami Exploration Potential
For personal use only Central Tanami Exploration Potential Over 100kms of highly prospective “trend” to test (to date mostly shallow <50 metre drilling) All clearances in place to commence drilling on the exploration licences (Central Tanami exploration budget 2011-12 $10M) Priority prospects
Slide 27: Resource Growth Since 2009
For personal use only Resource Growth Since 2009 27
Slide 28: Board & Senior Management
Board & Senior Management Board/Management Member Experience For personal use only Arthur is a non-practising barrister with a broad range of corporate and business experience and has served as a director, and in Arthur Dew some instances chairman of the board of directors, of a number of public lis
Slide 29: Company Highlights
For personal use only Company Highlights Tanami Gold NL is an Australian gold company - 100% of assets in Australia Targeting total WT and CT production - 180,000 to 200,000ozpa Strong platform for growth - 2.6Moz Resource1 and 0.4Moz Reserve2 Groundrush deposit - developing into a company m
Slide 30: Any Questions?
For personal use only ASX:TAM ANY QUESTIONS? Building an Australian mid tier gold producer February 2012 RIU Explorers Conference
Slide 31: Disclaimer & Competent Person's Statement
Disclaimer & Competent Person’s Statement Disclaimer & Forward-Looking Statements For personal use only Certain statements contained in this presentation, including information as to the future financial or operating performance of Tanami Gold NL and its projects, are forward-looking statements. S
Slide 32: Tanami Gold NL Ore Reserves as at March 2011
Tanami Gold NL Ore Reserves as at 31 March 2011 Reserve Category For personal use only Project Proven Probable Total Tonnes Grade Ounces Tonnes Grade Ounces Tonnes Grade Ounces WT 84,100 10.5 28,500 692,600 4.7 104,400 776,700 5.3 132,900 CT 355,000 5.5 62,400 1,689,000 2.9 159,000 2,044,000 3.4 221
Slide 33: Central Tanami Project Ore Reserves as at March 2011
Central Tanami Project Ore Reserves as at 31 March 2011 Reserve Category For personal use only Mineral Lease Proven Probable Total Tonnes Grade Ounces Tonnes Grade Ounces Tonnes Grade Ounces MLS153 - - - 363,100 2.4 27,500 363,100 2.4 27,500 MLS167 355,000 5.5 62,400 120,500 5.4 21,100 475,500 5.5 8
Slide 34: Western Tanami Project Ore Reserves as at March 2011
Western Tanami Project Ore Reserves as at 31 March 2011 For personal use only Reserve Category Deposit Proven Probable Total Tonnes Grade Ounces Tonnes Grade Ounces Tonnes Grade Ounces Coyote 84,100 10.5 28,500 231,600 8.4 62,400 315,700 9.0 90,900 Sandpiper - - - 53,000 3.0 5,000 53,000 3.0 5,000 K
Slide 35: Tanami Gold NL Mineral Resources as at September 2011
Tanami Gold NL Mineral Resources as at 30 September 2011 Resource Category For personal use only Project Measured Indicated Inferred Total Tonnes Grade Ounces Tonnes Grade Ounces Tonnes Grade Ounces Tonnes Grade Ounces WT 497,000 5.5 88,000 1,214,000 6.5 255,000 1,393,000 4.3 194,000 3,104,000 5.4 5
Slide 36: Central Tanami Project Mineral Resources by tenement
Central Tanami Project Mineral Resources by tenement as at 30 September 2011 Resource Category Mineral Measured Indicated Inferred Total For personal use only Lease Tonnes Grade Ounces Tonnes Grade Ounces Tonnes Grade Ounces Tonnes Grade Ounces MLS153 1,051,000 2.2 73,000 3,046,000 2.2 217,000 849,0
Slide 37: Western Tanami Project Mineral Resources as at September 2011
Western Tanami Project Mineral Resources as at 30 September 2011 Resource Category For personal use only Measured Indicated Inferred Total Deposit Tonnes Grade Ounces Tonnes Grade Ounces Tonnes Grade Ounces Tonnes Grade Ounces Coyote * 78,000 25.6 64,000 473,000 11.5 174,000 329,000 7.0 74,000 880,0