Slide 1: May 2009 Investor Presentation
May 2009 Investor Presentation Presented by: Jamie L. Buskill Senior Vice President & Chief Financial Officer 1

Slide 2: Forward-looking statements disclosure
2 Forward-looking statements disclosure NYSE:BWP Statements made at this conference or in the materials distributed in conjunction with this conference that contain "forward-looking statements" include, but are not limited to, statements using the words “believe”, “expect”, “plan”, “intend”, “antici

Slide 3: Investment Highlights
3 Investment Highlights § Pipelines access prolific unconventional supply reserves and conventional producing basins and deliver to diversified markets § Expanded footprint provides opportunities for future growth projects § Strong stable cash flow backed by long-term firm contracts with high qualit

Slide 4: sumer aur
sumer aur KOSCIUSKO “TRANSCO STATION 85 ALAND — Gulf CrossingPipeline — Gulf South Pipeline — Texas Gas Transmission _ BoardwalkStorage Fields @ Henry Hub

Slide 5: Boardwalk Overview
5 Boardwalk Overview Complementary Interstate Pipelines § Gulf Crossing Pipeline, Gulf South Pipeline, Texas Gas Transmission § ~14,200 miles of operational pipeline § 72 compressor stations Underground Storage Facilities § ~ 160 Bcf working gas capacity expanding by an additional 3 Bcf with the com

Slide 6: Access to Diversified Supply Sources
6 6 6 Access to Diversified Supply Sources Canadian Imports & Rockies Gas Conventional Production Midcontinent

Slide 7: Access to Diversified Supply Sources
7 Access to Diversified Supply Sources § Access to unconventional supply sources with significant reserves § Access to conventional supply sources throughout Gulf Coast and Offshore Gulf of Mexico regions § Direct and/or indirect access to Gulf Coast LNG terminals Barnett, Caney Woodford, Fayettevil

Slide 8: Delivery to Diversified Markets
8 8 8 Delivery to Diversified Markets Texas Eastern Transco Tennessee Dominion Columbia Gas Midwestern ANR MRT Columbia Gulf Trunkline NGPL Destin FGT Gulfstream SESH SONAT PIPELINE INTERCONNECTS

Slide 9: Delivery to Diversified Markets
9 9 9 Delivery to Diversified Markets Over 300 LDC delivery locations Including locations for: § Atmos Energy Corp. § CenterPoint Energy Resources § Louisville Gas and Electric Co. § Memphis Light Gas & Water § Vectren Corporation LOCAL DISTRIBUTION COMPANIES

Slide 10: Delivery to Diversified Markets
10 10 10 Delivery to Diversified Markets Delivers to over 30 Power Plants Including plants owned by: § American Electric Power (AEP) § Entergy Corporation § Kentucky Utilities § Southern Companies § Tennessee Valley Authority (TVA) POWER PLANTS

Slide 11: Delivery to Diversified Markets
11 11 11 Delivery to Diversified Markets Delivers to ~140 Industrial Delivery Locations Including locations for the following companies: § Air Products & Chemicals Inc. § Occidental Chemical Corporation § PPG Industries § Shell Chemical § Valero Energy Corp INDUSTRIALS East Side Baton Rouge New Orle

Slide 12: Diversified Customer Base
12 Diversified Customer Base 2008 Revenues by Delivery Type

Slide 13: Stable Revenues
13 § Business model of interstate pipelines is relatively stable § Majority of revenues are under firm contracts § Capacity reservation charges are received monthly regardless of utilization § Boardwalk expansions increase this stability Stable Revenues

Slide 14: Boardwalk Pipeline Partners
BOARDWALK lefere) PIPELINE PARTNERS®

Slide 15: Expansion Project Update
15 § All pipeline expansions were placed in service and transporting natural gas as of the first quarter 2009 § Completed the Little Red River drill and have pulled the 36” pipe under the river; we are now working to tie in the new 36” pipe with the existing Fayetteville system § Assessing and remed

Slide 16: Pipe Anomaly Update
16 Pipe Anomaly Update § Boardwalk was in the process of seeking authority from PHMSA to operate new expansion pipelines at higher operating pressures under special permits § As a result of the permitting process, anomalies (slight expansions of the pipe) were discovered in certain pipe segments; th

Slide 17: Expansion Project Cost Update
17 Expansion Project Cost Update ($ in millions)

Slide 18: Western Kentucky Storage Expansion Phase III
18 Western Kentucky Storage Expansion Phase III KENTUCKY Texas Gas Transmission Texas Gas Storage Field

Slide 19: Haynesville Expansion
19 § Signed agreements for 0.4 Bcf per day in the first quarter 2009 § Project will consist of adding compression facilities to the Gulf South system, subject to FERC approval § Estimated cost up to $200 million § Expected in service date of late 2010 § Weighted-average contract life in excess of 11

Slide 20: Boardwalk Pipeline Partners
BOARDWALK lefere) PIPELINE PARTNERS®

Slide 21: Recent Financial Performance
21 Recent Financial Performance 2006 2007 2005 2008 1Q 2008 1Q 2009 Financial Performance Comparison $349.8 $607.6 $643.2 2006 2007 $560.5 2005 $289.0 2008 $784.8 $474.6 1Q 2008 1Q 2009 $197.3 $223.4 $133.8 $125.2 1Q09 Key Drivers § Higher transportation revenues associated with expansion projects §

Slide 22: Capitalization
22 Capitalization as of March 31, 2009 § On May 1, 2009, BWP entered into a $200 million subordinated loan agreement with Loews. $100 million has been drawn to date.

Slide 23: Corporate Structure
23 Loews Corporation Subsidiary Boardwalk Pipeline Partners, LP NYSE: BWP Public Unitholders Partners’ Capital Unit Type 154.9 million units Common Units 22.9 million units Class B Units Boardwalk Pipelines, LP 72% L.P. interest* 2% G.P. interest 26% L.P. interest Corporate Structure 100% 100% 100%

Slide 24: Distribution Growth
24 Distribution Growth (a) Represents cash distributions related to the quarter and declared and paid to unitholders within 60 days after quarter end. (b) For the period from November 15, 2005, through December 31, 2005, reflecting a quarterly distribution rate of $0.35 per unit.

Slide 25: Quarterly EBITDA Reconciliation
25 Quarterly EBITDA Reconciliation Non-GAAP Financial Measures EBITDA is used as a supplemental financial measure by Boardwalk's management and by external users of Boardwalk's financial statements, such as investors, commercial banks, research analysts and rating agencies, to assess Boardwalk’s ope

Slide 26: Annual EBITDA Reconciliation
26 Annual EBITDA Reconciliation Non-GAAP Financial Measures EBITDA is used as a supplemental financial measure by Boardwalk's management and by external users of Boardwalk's financial statements, such as investors, commercial banks, research analysts and rating agencies, to assess Boardwalk’s operat

Slide 27: May 2009 Investor Presentation
27 May 2009 Investor Presentation Presented by: Jamie L. Buskill Senior Vice President & Chief Financial Officer
Source: SEC EDGAR · 8-K filed May 26, 2009
More decks from Boardwalk Pipeline Partners LP
Wells Fargo presentation (May 2017)28 slides · May 16, 2017
2015 Wells Fargo Energy Symposium32 slides · Dec 7, 2015
2014 Citi 1x1 MLP/Midstream Infrastructure Conference36 slides · Aug 19, 2014
NAPTP 2014 MLP Annual Investor Conference33 slides · May 20, 2014
Corporate Update (October 2011)9 slides · Oct 17, 2011