Royal Bafokeng Platinum Ltd

Royal Bafokeng Platinum — Corporate Update (March 2012)

19 slides from Royal Bafokeng Platinum's corporate update, Mar 30, 2012

  1. Slide 1: Styldrift I Shaft Investor Presentation

    Slide 1: Styldrift I Shaft Investor Presentation

    more than mining more Styldrift I Shaft Investor Presentation than 30 March 2012 Presentation mining

  2. Slide 2: Project Geographic Location

    Slide 2: Project Geographic Location

    Styldrift I Project Geographic Location 2

  3. Slide 3: Project Overview

    Slide 3: Project Overview

    Styldrift I Project Overview Description Shaft Infrastructure Features – Expansion project – Twin Vertical Shaft Access – 230 ktpm Merensky mine and concentrator • Main shaft (10.5m dia. lined) – Dual shaft access: main shaft, services shaft • Services shaft (6.5m dia. lined) – Bord and pillar mecha

  4. Slide 4: Shaft Configuration

    Slide 4: Shaft Configuration

    Styldrift I Shaft Configuration Shaft Infrastructure Shaft Infrastructure • Production › 230ktpm reef › 45ktpm waste • Injury free mine design • Merensky reef mining focus • UG2 mining being investigated • Room & Pillar (Trackless) – thick and central upper reef Mining Access • Conventional breast –

  5. Slide 5: Mine Design

    Slide 5: Mine Design

    Styldrift I Mine Design Shaft Sinking Footprint Room & Pillar Scattered Breast Shaft Position 8 5

  6. Slide 6: Mining Production, Resources and Reserves

    Slide 6: Mining Production, Resources and Reserves

    Styldrift I Styldrift Mining Production (mtpa) Styldrift Production Profile 4.00 3.00 2.00 1.00 0.00 2012 2013 2014 2015 2016 2017 2018 2019 2020 Styldrift Merensky Styldrift Resources and Reserves Merensky UG2 Total Mt 4E g/t 4E Moz Mt 4E g/t 4E Moz Mt 4E Moz Measured 25.4 6.73 5.5 13.3 5.26 2.2 38

  7. Slide 7: Mining Footprint

    Slide 7: Mining Footprint

    Styldrift I Mining Footprint 7

  8. Slide 8: Project Timetable

    Slide 8: Project Timetable

    Styldrift I Project Timetable Project Phase 2009 2010 2011 2012 2013 2014 2015 2016 2017 Engineering & Design 2009 – 2013 Fabrication & Delivery 2009 – 2016 Pre-Sink Infrastructure 2009 – 2011 Main Shaft Sinking 2011 – 2014 Main Shaft Equipping Services Shaft Sinking 2011 – 2014 Services Shaft Equip

  9. Slide 9: Project Cost and Progress

    Slide 9: Project Cost and Progress

    Styldrift I Project Cost and Progress Capital Budget - Nominal Capital Cash Flow - Nominal Rm Mining Concentrator Total Rm 3 000 Authorised and Contingency 6,289 1,422 7,711 2 500 2 000 Escalation 3,153 938 4,091 1 500 Total Nominal 9,442 2,360 11,802 1 000 Latest Cost Forecast 9,119 2,360 11,479 50

  10. Slide 10: Utilities

    Slide 10: Utilities

    Styldrift I Utilities Styldrift Mining Electrical Load Build-up Power Supply • Temporary power : 10 MVA secured from 50 Eskom via Boschkoppie substation 40 • Permanent power: 30 › Eskom budget approved and upfront 20 payment 10 made 0 › Permanent power available by Q1 2014 2010 2011 2012 2013 2014 2

  11. Slide 11: Legal and Permitting

    Slide 11: Legal and Permitting

    Styldrift I Legal and Permitting • Mining Right Granted March 2008 • EMP Approved March 2008 • Water User Licence Approved April 2010 • Legal Appointments All in place • Social and Labour Plan Approved September 2009 11

  12. Slide 12: Concentrator

    Slide 12: Concentrator

    Styldrift I Concentrator Process Plant Design • Pre-Feasibility study in progress – completion planned for Q1 2012 • Concentrator design is for a 230 ktpm plant • Site Location of Concentrator and Tailings facility to be finalized • Feasibility study to commence in Q2 2012 and completed by Q2 2013 P

  13. Slide 13: Project Highlights

    Slide 13: Project Highlights

    Styldrift I Project Highlights Completed Activities / Key Dates • Project commencement date – March 2009 • Bulk earthworks complete – June 2010 • Bulk Civils completed – October 2010 • Shaft pre sink commenced – October 2010 • Personnel & Material winder commissioned – March 2011 • Pre sink complete

  14. Slide 14: Optimisation

    Slide 14: Optimisation

    Styldrift I Optimisation Optimisation study initiated in January 2011 Key components being reviewed are: • Shaft bottom infrastructure layout • Room and pillar mine design • Strike ore handling methodology – truck vs conveyors • Pneumatic vs. electric drilling • Access to the UG2 ore horizon and ass

  15. Slide 15: Major Activities Completed – Headgear Erection

    Slide 15: Major Activities Completed – Headgear Erection

    Styldrift I Major Activities Completed – Headgear Erection 15

  16. Slide 16: Major Activities Completed

    Slide 16: Major Activities Completed

    Styldrift I Major Activities Completed Main Shaft Personnel and Material Winder (5.5m D): Commissioned Main & Service Shafts Stage Winders: Commissioned 16

  17. Slide 17: Activities In Progress

    Slide 17: Activities In Progress

    Styldrift I Activities In Progress Sinking in progress 17

  18. Slide 18: Further organic growth in Styldrift II

    Slide 18: Further organic growth in Styldrift II

    Further organic growth in Styldrift II Styldrift II project area • Resource area ± 23 million m2 • Depth 900m – 1,400m, average dip 90 • Average Merensky/UG2 middling 35m Potential size of investment similar to Styldrift I Opportunity will be evaluated through: • Study consisting of a concept, pre-f

  19. Slide 19: Thank you

    Slide 19: Thank you

    Thank you 19