Royal Bafokeng Platinum — Corporate Update (March 2012)
19 slides from Royal Bafokeng Platinum's corporate update, Mar 30, 2012

Slide 1: Styldrift I Shaft Investor Presentation
more than mining more Styldrift I Shaft Investor Presentation than 30 March 2012 Presentation mining

Slide 2: Project Geographic Location
Styldrift I Project Geographic Location 2

Slide 3: Project Overview
Styldrift I Project Overview Description Shaft Infrastructure Features – Expansion project – Twin Vertical Shaft Access – 230 ktpm Merensky mine and concentrator • Main shaft (10.5m dia. lined) – Dual shaft access: main shaft, services shaft • Services shaft (6.5m dia. lined) – Bord and pillar mecha

Slide 4: Shaft Configuration
Styldrift I Shaft Configuration Shaft Infrastructure Shaft Infrastructure • Production › 230ktpm reef › 45ktpm waste • Injury free mine design • Merensky reef mining focus • UG2 mining being investigated • Room & Pillar (Trackless) – thick and central upper reef Mining Access • Conventional breast –

Slide 5: Mine Design
Styldrift I Mine Design Shaft Sinking Footprint Room & Pillar Scattered Breast Shaft Position 8 5

Slide 6: Mining Production, Resources and Reserves
Styldrift I Styldrift Mining Production (mtpa) Styldrift Production Profile 4.00 3.00 2.00 1.00 0.00 2012 2013 2014 2015 2016 2017 2018 2019 2020 Styldrift Merensky Styldrift Resources and Reserves Merensky UG2 Total Mt 4E g/t 4E Moz Mt 4E g/t 4E Moz Mt 4E Moz Measured 25.4 6.73 5.5 13.3 5.26 2.2 38

Slide 7: Mining Footprint
Styldrift I Mining Footprint 7

Slide 8: Project Timetable
Styldrift I Project Timetable Project Phase 2009 2010 2011 2012 2013 2014 2015 2016 2017 Engineering & Design 2009 – 2013 Fabrication & Delivery 2009 – 2016 Pre-Sink Infrastructure 2009 – 2011 Main Shaft Sinking 2011 – 2014 Main Shaft Equipping Services Shaft Sinking 2011 – 2014 Services Shaft Equip

Slide 9: Project Cost and Progress
Styldrift I Project Cost and Progress Capital Budget - Nominal Capital Cash Flow - Nominal Rm Mining Concentrator Total Rm 3 000 Authorised and Contingency 6,289 1,422 7,711 2 500 2 000 Escalation 3,153 938 4,091 1 500 Total Nominal 9,442 2,360 11,802 1 000 Latest Cost Forecast 9,119 2,360 11,479 50

Slide 10: Utilities
Styldrift I Utilities Styldrift Mining Electrical Load Build-up Power Supply • Temporary power : 10 MVA secured from 50 Eskom via Boschkoppie substation 40 • Permanent power: 30 › Eskom budget approved and upfront 20 payment 10 made 0 › Permanent power available by Q1 2014 2010 2011 2012 2013 2014 2

Slide 11: Legal and Permitting
Styldrift I Legal and Permitting • Mining Right Granted March 2008 • EMP Approved March 2008 • Water User Licence Approved April 2010 • Legal Appointments All in place • Social and Labour Plan Approved September 2009 11

Slide 12: Concentrator
Styldrift I Concentrator Process Plant Design • Pre-Feasibility study in progress – completion planned for Q1 2012 • Concentrator design is for a 230 ktpm plant • Site Location of Concentrator and Tailings facility to be finalized • Feasibility study to commence in Q2 2012 and completed by Q2 2013 P

Slide 13: Project Highlights
Styldrift I Project Highlights Completed Activities / Key Dates • Project commencement date – March 2009 • Bulk earthworks complete – June 2010 • Bulk Civils completed – October 2010 • Shaft pre sink commenced – October 2010 • Personnel & Material winder commissioned – March 2011 • Pre sink complete

Slide 14: Optimisation
Styldrift I Optimisation Optimisation study initiated in January 2011 Key components being reviewed are: • Shaft bottom infrastructure layout • Room and pillar mine design • Strike ore handling methodology – truck vs conveyors • Pneumatic vs. electric drilling • Access to the UG2 ore horizon and ass

Slide 15: Major Activities Completed – Headgear Erection
Styldrift I Major Activities Completed – Headgear Erection 15

Slide 16: Major Activities Completed
Styldrift I Major Activities Completed Main Shaft Personnel and Material Winder (5.5m D): Commissioned Main & Service Shafts Stage Winders: Commissioned 16

Slide 17: Activities In Progress
Styldrift I Activities In Progress Sinking in progress 17

Slide 18: Further organic growth in Styldrift II
Further organic growth in Styldrift II Styldrift II project area • Resource area ± 23 million m2 • Depth 900m – 1,400m, average dip 90 • Average Merensky/UG2 middling 35m Potential size of investment similar to Styldrift I Opportunity will be evaluated through: • Study consisting of a concept, pre-f

Slide 19: Thank you
Thank you 19
Source: company website
More decks from Royal Bafokeng Platinum Ltd
Renaissance Capital Metals & Mining Conference 202118 slides · May 2021
H1 2020 Earnings Presentation39 slides · 2020
Merger or Acquisition (October 2019)11 slides · Oct 16, 2019
RBPlat Analyst Roundtable 201910 slides · Aug 6, 2019
Technical Presentation (February 2019)34 slides · Feb 1, 2019
Fact Sheet (2019)11 slides · 2019