Azarga Metals Corp. · TSXV:AZR
Azarga Metals — Investor Presentation (September 2016)
23 slides from Azarga Metals's investor presentation, September 2016

Slide 1: Unkur – A Russian Silver-Copper Project
UNKUR – A RUSSIAN SILVER-COPPER PROJECT Investor Presentation – September 2016 TSX-V: AZR

Slide 2: Disclaimer
Disclaimer Certain statements in this presentation are forward-looking statements. Forward-looking statements consist of statements that are not purely historical, including any statements regarding beliefs, plans, expectations or intentions regarding the future. Often, but not always, forward-looki

Slide 3: Overview
Overview Summary: establishing a large high-grade silver-copper deposit, right next door to China § Azarga Metals acquired 60% of Unkur Silver-Copper Project in eastern Russia in late- May 2016, with a ‘put and call’ arrangement over the remaining 40% § Historical exploration (including drilling and

Slide 4: Capitalization and key assets
Overview Capitalization and key assets Capitalization Key assets Shares outstanding1 43.0m Azarga Metals Share price (TSX-V: AZR)1 C$0.30/share Corp. (TSX-V: AZR) Market cap (CAD) C$12.9m Cash (CAD)2 C$1.6m Insider ownership ~36% Notes: 1. As at 16 September 2016. 2. As at 30 June 2016. (60%) (25%)

Slide 5: Unkur Silver-Copper Project: Project history
Unkur Silver-Copper Project Project history § Discovered in 1962 with historical physical exploration undertaken from 1969 to 1978, including: surface sampling; trenching; and drilling § Historical drilling results included significant copper and silver over >4.5km of strike § Multiple intersections

Slide 6: Unkur Silver-Copper Project: Location
Unkur Silver-Copper Project Location Regional location of Zabaikalye Unkur, local geography and infrastructure Source: Azarga Metals Commentary § Zabaikalye has a direct land border with China § It includes the world’s third and 14th largest undeveloped copper deposits, both, which have been moved f

Slide 7: Unkur Silver-Copper Project: Terrain and infrastructure
Unkur Silver-Copper Project Terrain and infrastructure Unkur area terrain þ Terrain § 400 – 500m above sea level § Relatively flat þ Transport § 7km from BAM Railway § 2,800km to Vladivostock (Pacific port) þ Power BAM Railway near Chara § High voltage substation at Novaya Chara (within 10km) with c

Slide 8: Current first phase drilling program
Unkur Silver-Copper Project Current first phase driling program § 10-15 diamond drill holes (approx. 3,000 cumulative linear meters) § Covering approximately 3km of historic strike area § Objectives § Verify high-grade historic intercepts § Compile sub-surface data for NI 43-101 Resource § Better co

Slide 9: First phase drilling program results so far
Unkur Silver-Copper Project First phase driling program results so far Source: Azarga Metals 9

Slide 10: Azarga Metals leadership
Azarga Metals leadership Board of directors § CEO European Uranium (now Azarga Metals) (2008 – present) § 40-years international experience in exploration and mining § Successful track record of managing exploration and development projects worldwide Dorian (Dusty) Nicol § Member of the American Ins

Slide 11: Appendix 1: Additional information on Unkur geology
APPENDIX 1 Additional information on Unkur Silver-Copper Project geology 11

Slide 12: Regional deposit map
Appendix 1: Unkur geology Regional deposit map Source: Azarga Metals 12

Slide 13: Regional geology
Appendix 1: Unkur geology Regional geology Source: Technical Report. 13

Slide 14: Geological setting
Appendix 1: Unkur geology Geological setting § Unkur is situated in the North of trans-Baikal territory in the Baikal-Amur railway area § Copper ore occurrences in area relate to formation of cupriferous sandstones, cupriferous siltstones, cupriferous carbonaceous rocks and composite copper sulphide

Slide 15: Summary of metal bearing minerals at Unkur
Appendix 1: Unkur geology Summary of metal bearing minerals at Unkur § Principal minerals that bear commercial copper grades are bornite, chalcocite, chalcopyrite § Malachite, brochantite, covellite, chalcocite, hydrous ferric oxides are developed in a hypergenesis zone 15

Slide 16: Map of historical exploration activities
Appendix 1: Unkur geology Map of historical exploration activites 16 Source: Azarga Metals

Slide 17: Historical plan view and selected cross-sections
Appendix 1: Unkur geology Historical plan view and selected cross-sections indicate a syncline of copper-bearing ore 17

Slide 18: Outcrop photos and 2013 rock chip samples
Appendix 1: Unkur geology Outcrop photos and 2013 rock chip samples Summer 2013 rock chip sample results Outcropping mineralization Silver content Copper Sample (g/t) content Ref. 1310 106 2.95% Ref. 1311 230 6.12% Ref. 1312 50 1.79% Ref. 1313 49 2.66% Ref. 1314 82 2.79% Source: Azarga Metals Unkur

Slide 19: Appendix 2: Terms of 2016 acquisition of Unkur
APPENDIX 2 Terms of 2016 acquisition of Unkur Silver-Copper Project 19

Slide 20: Summary of relevant acquisition terms
Appendix 2: Unkur acquisition terms Summary of relevant acquisition terms § Azarga Metals (formerly European Uranium Resources) acquired 60% of Unkur’s 100% beneficial owner, Azarga Metals Limited (AML) on 30 May 2016 § Key acquisition terms include: § 15,776,181 shares (issued 31 May 2016 and inclu

Slide 21: Appendix 3: Status of Kuriskova
APPENDIX 3 Status of Kuriskova 21

Slide 22: Kuriskova litigation is third-party funded
Appendix 3: Status of Kuriskova European Uranium’s litigation with regards to the project claim is third-party funded § European Uranium filed suit against the Government of Slovakia for failing to renew its Kuriskova Exploration License in 2015 § The Company is seeking up to EUR23 million as compen

Slide 23: TSX-V: AZR
Unit 1 – 15782 Marine Drive White Rock, B.C. V4B 1E6 604-536-2711 Email: info@azargametals.com www.azargametals.com TSX-V: AZR
Source: Internet Archive copy of azargametals.com
More decks from Azarga Metals Corp.
Investor Presentation (May 2026)20 slides · May 2026
Investor Presentation (October 2025)20 slides · October 2025
Investor Presentation (May 2024)21 slides · May 2024
Investor Presentation (July 2023)21 slides · July 2023
Investor Presentation (June 2022)20 slides · June 2022
Investor Presentation (October 2020)19 slides · October 2020