Orvana Minerals Corp. · TSX:ORV
Orvana Minerals — FY2012 Earnings Presentation
19 slides from Orvana Minerals's earnings presentation, Jan 4, 2013

Slide 1: Orvana Minerals Corp. FY-2012 Results
O R VANA MINERALS CORP. FY-2012 RESULTS January 4, 2013

Slide 2: Forward Looking Statements
O RVANA MINERALS CORP. FORWARD LOOKING STATEMENTS Certain statements in this presentation constitute forward-looking statements or forward-looking information within the meaning of applicable securities laws (“forward-looking statements”). Any statements that express or involve discussions with resp

Slide 3: Experienced Management Team
O RVANA MINERALS CORP. EXPERIENCED MANAGEMENT TEAM BILL WILLIAMS, Ph.D., CPG, President and Chief Executive Officer; previously VP, Americas, Freeport- McMoRan Exploration Corporation. 30 years of international resource exploration and mine development experience DANIELLA DIMITROV, B.A., LL.B., EMBA

Slide 4: Diverse Board
O RVANA MINERALS CORP. DIVERSE BOARD ROBERT MITCHELL, CA,: Acting Chairman; retired partner from Ernst and Young; extensive financial expertise in mining sector BILL WILLIAMS, Ph.D., CPG, President and CEO since 2011; previously VP, Americas, Freeport-McMoRan Exploration Corporation. 30 years of int

Slide 5: Company Snapshot
O RVANA MINERALS CORP. COMPANY SNAPSHOT Market Overview, as at December 20, 2012 Stock Chart (1 Year) Ticker TSX:ORV Shares Outstanding 136.6 M Options 2.8 M Warrants 1.8 M Market Cap. (Basic) ~$116 M Major Shareholder Fabulosa Mines Ltd. (52%) Balance Sheet (09/30/12, US$M) Analyst Coverage Unrestr

Slide 6: Financial Performance
O RVANA MINERALS CORP. FINANCIAL PERFORMANCE Q1 Q2 Q3 Q4 FY-2012 Revenue $15,373 $31,245 $43,691 $50,608 $140,917 Gross Margin $354 $9,029 $11,031 $21,912 $42,326 EBITDA $438 $8,938 $12,892 $22,182 $44,450 Adjusted Net Income (loss)¹ ($3,254) $2,791 $3,612 $12,325 $15,474 Operating Cash Flow $5,290

Slide 7: Total Production
O RVANA MINERALS CORP. TOTAL PRODUCTION Gold oz Copper k/lbs Silver k/oz FY2013 Forecast Gold Copper Silver 75,000 18 million 850,000 ounces pounds ounces 7

Slide 8: El Valle-Boinás Carlés (EVBC) Spain
EL VALLE-BOINÁS CARLÉS (“EVBC”) SPAIN 8

Slide 9: El Valle-Boinás Carlés EVBC
O RVANA MINERALS CORP. EL VALLE-BOINÁS CARLÉS “EVBC” First full year of commercial production Ground instability and power issues addressed 420-metre deep shaft Commissioned Q4-2012 Operational Q1-2013 50,000 ounces of reserve gold added in FY2012 2P: 812koz 9

Slide 10: EVBC Production
O RVANA MINERALS CORP. EVBC PRODUCTION 63,000 oz 42,864 oz 9,336 oz 6 Mlbs 200,000 oz 3.95 Mlbs 117,113 oz 1.05 Mlbs 28,456 oz 10

Slide 11: EVBC Improving Performance
O RVANA MINERALS CORP. EVBC Improving Performance FY 2012 cash cost of ~ $850/oz gold sold net of by-product revenue 1,300 Cash Cost net of by-product /oz sold 1,200 1,100 1,000 900 800 700 600 Q1 Q2 Q3 Q4 11

Slide 12: Don Mario Upper Mineralized Zone UMZ Bolivia
DON MARIO UPPER MINERALIZED ZONE “UMZ” BOLIVIA

Slide 13: Don Mario Upper Mineralized Zone UMZ
O RVANA DON MARIO MINERALS CORP. UPPER MINERALIZED ZONE “UMZ” Commercial Production Commenced Q2, 2012 10th year of production Complex ores Concentrates committed High-Pb Cu con Oxide cement (>50% Cu) No COMIBOL contract Updated reserve estimate (Dec) Mine life into 2018 13

Slide 14: UMZ Production
O RVANA MINERALS CORP. UMZ PRODUCTION 13,065 oz 12,000oz 9,977oz 12 Mlbs 650,000oz 599,167oz 11.42 Mlbs 2,218oz 14

Slide 15: UMZ Improving Performance
O RVANA MINERALS CORP. UMZ Improving Performance Co-product cash costs decreasing Continuous optimization efforts FY 2012 cash cost $1,143/oz gold sold $2.39/lb copper sold $22.00/oz silver sold Au, $/oz Cash Cost Cu, $/lb Cash Cost Ag, $/oz Cash Cost 1,800 4.00 35.00 1,600 3.50 31.00 1,400 3.00 27.

Slide 16: Copperwood Michigan USA
COPPERWOOD MICHIGAN USA 16

Slide 17: Copperwood
O RVANA MINERALS CORP. COPPERWOOD Strong community support 632 permit received: April, 2012 30 km west of White Pine 936 hectares under lease 480 hectares land for infrastructure & access 17

Slide 18: Copperwood Moving Forward
O RVANA MINERALS CORP. COPPERWOOD MOVING FORWARD Permits: BFS completed 2P: 27.4Mt @ 1.41% Cu, 3.62 g/t Ag Apr 2012 – Part 632 (Nonferrous Metallic Mining) Jul 2012 – Permit to Install, or Air Quality Permit ~$213M pre-prod CAPEX Nov 2012 – National Pollutant Discharge Underground room & pillar Elim

Slide 19: Summary
O RVANA MINERALS CORP. SUMMARY Multi Project Producer Strategy Strong Future Cash Flow/Income Generation Major European Gold Producer Significant and Growing Copper Producer Maximize Value – Both Gold and Copper Production 19
Source: Internet Archive copy of orvana.com
More decks from Orvana Minerals Corp.
Investor Presentation (November 2026)35 slides · Nov 6, 2026
Investor Presentation (September 2026)35 slides · Sep 21, 2026
Investor Presentation (April 2026)33 slides · Apr 7, 2026
Investor Presentation (November 2025)32 slides · Nov 28, 2025
Investor Presentation (October 2025)32 slides · Oct 1, 2025
Investor Presentation (May 2025)30 slides · May 14, 2025