Orvana Minerals Corp. · TSX:ORV

Orvana Minerals — Investor Presentation (May 2025)

30 slides from Orvana Minerals's investor presentation, May 14, 2025

  1. Slide 1: Producer Poised for Growth

    Slide 1: Producer Poised for Growth

    Producing in Spain and focused on restarting production in Bolivia PRODUCER POISED FOR GROWTH Don Mario - Bolivia Plant expansion – Conceptual Model TSX | ORV Corporate Presentation | May 14, 2025 May | 2025 ORVANA.COM 1 | 2025

  2. Slide 2: Forward Looking Statements

    Slide 2: Forward Looking Statements

    FORWARD LOOKING STATEMENTS All monetary amounts in U.S. dollars unless otherwise stated. personnel; the Company’s ability to obtain and maintain all necessary regulatory approvals and licenses; Orovalle’s ability to complete the Certain statements in this presentation constitute forward-looking stat

  3. Slide 3: Strategy Overview

    Slide 3: Strategy Overview

    STRATEGY OVERVIEW • Stable cash flow generation based on a production range of 37,000 – 41,000 Au oz OROVALLE • Continue Brownfield and Greenfield exploration Producing Unit drive to expand the resource base Toronto HEAD OFFICE Spain Orovalle Au, Cu, Ag • The Company expects to complete the construc

  4. Slide 4: Operations Outlook

    Slide 4: Operations Outlook

    OPERATIONS OUTLOOK FY2025 FY2026 FY2027 OROVALLE El Valle Production Brownfield & Greenfield Exploration Financing Completion Oxides Stockpile Production EMIPA Tailings Reprocessing Don Mario Plant Expansion Evaluation Cu lb 20M Aproximately Au oz Aproximately 20M Cu lb 70k Au oz production by 2026

  5. Slide 5: Snapshot - TSX:ORV

    Slide 5: Snapshot - TSX:ORV

    SNAPSHOT - TSX:ORV Common Shares O/S 136.6M Unrestricted Cash (03/31/25) USD 30.0M Options (05/14/25) None Total Debt (03/31/25) USD 39.3M Stock Price (05/14/25) CAD 0.56 Enterprise Value (05/14/25) USD 64.1M Market Capitalization (05/14/25) CAD 76.5M Monthly Avg. Trading Volume 1.3M Fiscal Year end

  6. Slide 6: El Valle Operations

    Slide 6: El Valle Operations

    EL VALLE OPERATIONS V SPAIN LOCATION Asturias, Northern Spain MINING El Valle Boinás and Carlés Mines Methods: Drift and fill; Sublevel Stoping PROCESSING El Valle Plant Circuits: Gravimetry, Flotation, CIL Output: Copper Concentrate & Au-Ag Dore FY2024 METAL PRODUCTION Au: 36.5K oz Ag: 107.9K oz Cu

  7. Slide 7: Production & Cost

    Slide 7: Production & Cost

    PRODUCTION & COST COC/AISC(*) per Au/oz sold V SPAIN Gold oz Production Copper lbs Production (thousands) By-product 46,259 4,518 $2,000 - $2,150 41,000 $2,052 36,488 $1,829 3,744 37,000 $1,580 $1,550 - $1,650 2,700 2,400 $1,687 $1,539 $1,294 1,953 H1 14,424 H1 FY 2023 FY 2024 FY 2025 FY 2023 FY 202

  8. Slide 8: Regional Exploration

    Slide 8: Regional Exploration

    Madrid REGIONAL EXPLORATION LOCATION V SPAIN Orovalle Mine Operations and Projects are located in Northern Spain Major Regional Gold Belts Spain GIJÓN PORT El Valle Plant: 89 kilometers by road to Gijon Port TARGETS Regional Targets based on 38,865 ha land package LA LINDE OVIEDO with 14 exploitatio

  9. Slide 9: Rio Narcea Gold Belt

    Slide 9: Rio Narcea Gold Belt

    RIO NARCEA GOLD BELT V LONG TERM EXPLORATION STRATEGY GOING NORTH FROM CURRENT OPERATIONS SPAIN ORTOSA GODAN TARGET TARGET ORTOSA GODAN CARLES TARGET CARLES MINE MINE EL VALLE - BOINAS MINE 12 Km OXIDES 10 Km N LEGEND SKARN Exploitation EL VALLE- BOINAS Concessions MINE Mine 2 Km Operations Ortosa-

  10. Slide 10: Ortosa – Godán

    Slide 10: Ortosa – Godán

    ORTOSA – GODÁN • Located close to Carlés deposit V SPAIN • Airborne Geophysics • Geochemistry / Surface sampling • 9,833 m of drilling in 37 historical holes (1981-2011) • 9,766 m of drilling in 24 holes by Orovalle (2021-2025) Exploitation Concessions ORTOSA Carles Operation Carles Deposit ORTOSA G

  11. Slide 11: Ortosa

    Slide 11: Ortosa

    ORTOSA V SPAIN ORW-3X 22ORW11 N 11.25 m @ 6.8 g/t Au 21ORW05 2.90 m @ 20.66 g/t Au 1.10 m @ 33.12 g/t Au N 22ORW07 6.05 m @ 22.16 g/t Au 1.60 m @ 27.43 g/t Au A’ Au (g/t) >=0.25 <1.00 >= 1.00 <2.25 300 m >= 2.25 <3.50 >=3.50 <5.00 >=5.00 <10.00 >=10.00 A Target area (Untested) 100 m Intercepts Longi

  12. Slide 12: Godan

    Slide 12: Godan

    Legend 23GOD05 3.70 m @ 5.91 g/t Au GODAN 23GOD06R 5.10 m @ 1.09 g/t Au 1.30 m @ 4.16 g/t Au V SPAIN GODAN 1.30 m @ 2.26 g/t Au 10.20 m @ 1.56 g/t Au 5.70 m @ 0.82 g/t Au Old Drillholes CARLES MINE Orovalle Drillholes Ongoing Drillhole 2.0 Km 0m ? DDH 25GOD08 A GODAN - 500 m 20CN1160 3.15 m @ 1.40 g

  13. Slide 13: Lidia

    Slide 13: Lidia

    EL VALLE- BOINAS MINE 21LIDIA02 99.3 m @ 0.48 g/t Au LIN-4x 22LIDIA04 • LIDIA V SPAIN Located in Navelgas Gold Belt, 20 km west from El Valle 196.5 m @ 0.53 g/t Au Including: 142.5 m @ 0.44 g/t Au Mine 1.90 m @ 3.14 g/t Au 22LIDIA05 • Exploration background: 20 Km 21LIDIA03 318.0 m @ 0.44 g/t Au ✓ D

  14. Slide 14: Taguas Project

    Slide 14: Taguas Project

    TAGUAS PROJECT V ARGENTINA • Located in high Andes of San Juan Province, Argentina • Consisting of 15 individual claims/concessions – 3,273.87 ha • Highly prolific area known for high-sulfidation epithermal Au-Cu-Ag deposits and porphyry Cu-Au systems • Orvana’s strategy in the Taguas project had be

  15. Slide 15: Deep Geophysics Survey – Taguas

    Slide 15: Deep Geophysics Survey – Taguas

    DEEP GEOPHYSICS SURVEY – TAGUAS V ARGENTINA • Objective: Identify potential targets up to a depth of 1,500 m • Planned 7 lines of 4.0 km • Area between Cerro Campamento and Cerros Taguas, defined by alteration footprint and current drilling data • IPEx method: • Designed by Geophysical Resources and

  16. Slide 16: Don Mario Profile

    Slide 16: Don Mario Profile

    DON MARIO PROFILE V BOLIVIA Don Mario Chiquitos, Santa Cruz Department Eastern Bolivia Main Infrastructure: • 2,000 tpd Processing Plant: CIL & Flotation • Tailings Storage Facility • Power Plant – Connected to National Gas Grid Production Started in 2003. In C&M since late 2019 Projects: • Oxides S

  17. Slide 17: Oxides Stockpile Project (OSP)

    Slide 17: Oxides Stockpile Project (OSP)

    The OSP consists of a plant OXIDES STOCKPILE PROJECT (OSP) • V National Instrument 43-101 Technical Report for the Don Mario BOLIVIA expansion to treat ore stockpiled at Property dated February 28, 2022 including OSP information is the Don Mario mine from previous available on www.sedarplus.ca and o

  18. Slide 18: Tailings Reprocessing Project (TRP)

    Slide 18: Tailings Reprocessing Project (TRP)

    TAILINGS REPROCESSING PROJECT (TRP) EMIPA is evaluating the potential reprocessing of tailings accumulated in V BOLIVIA the Don Mario Tailings Storage Facility ▪ Tailings mineral resource (*) Indicated: 4.42 Mt at Au 0.44 g/t; Cu 0.50%; Ag 4.83 g/t Inferred: 1.67 Mt at Au 0.45 g/t; Cu 0.38%; Ag 3.53

  19. Slide 19: Financial Performance

    Slide 19: Financial Performance

    FINANCIAL PERFORMANCE Financial Performance (US 000’s) FY 2022 FY 2023 FY2024 H1 FY2025 Year-end: September 30 Revenue $94,668 $99,122 $90,310 $48,459 Net Income (Loss) ($13,719) $2,708 ($4,952) $1,925 EBITDA (*) $6,277 $21,652 $16,865 $11,501 OCF, before Non-Cash WC changes $7,393 $16,291 $21,409 $

  20. Slide 20: Investment Opportunity

    Slide 20: Investment Opportunity

    INVESTMENT OPPORTUNITY • Three NI 43-101-supported Assets. All 100% controlled Orovalle (Spain): Producing asset located in safe jurisdiction Brownfield and greenfield portfolio Don Mario (Bolivia): Positioned to restart production in 2026 Managed by an experienced local team Taguas (Argentina): Adv

  21. Slide 21: Appendix

    Slide 21: Appendix

    ORVANA MINERALS CORP APPENDIX

  22. Slide 22: Mineral Resources GEO

    Slide 22: Mineral Resources GEO

    MINERAL RESOURCES GEO Gold Equivalent Ounces (M) 4.9 4.7 4.7 2.8 2.8 2.8 0.6 0.6 0.6 1.5 1.3 1.3 Orovalle September 30, 2022 September 30, 2023 September 30, 2024 Don Mario Taguas Gold Equivalent Ounces (GEO) (*) calculations were based on assumed metal prices of: Au/Ag/Cu prices (*) Gold Equivalent

  23. Slide 23: Orovalle Reserves & Resources

    Slide 23: Orovalle Reserves & Resources

    OROVALLE RESERVES & RESOURCES V SPAIN Mineral Reserves2 – Sept. 30, 2024 Tonnes Grade Contained Metal Au Cu Ag Au Ounces Cu Lbs Category (000’s) (g/t) (%) (g/t) (000’s) (000’s) Total Proven Reserves 382 2.41 0.48 8.75 30 4,025 Total Probable Reserves 1,730 2.84 0.22 3.52 158 8,530 Total P+P Reserves

  24. Slide 24: Notes to Orovalle Reserves & Resources

    Slide 24: Notes to Orovalle Reserves & Resources

    Notes to Mineral Reserves table: NOTES TO OROVALLE RESERVES & RESOURCES Notes to Mineral Resources table: V SPAIN 1. CIM (November 29, 2019) definitions and guidelines were followed for Mineral Reserve 1. CIM definitions and guidelines (November 29, 2019) were followed for Mineral Resources estimati

  25. Slide 25: Don Mario Resources

    Slide 25: Don Mario Resources

    DON MARIO RESOURCES V BOLIVIA Oxide Stockpile and Tailings Reprocessing Project’s Mineral Resources – Sept. 30, 2024 Tonnes Grade Contained Metal Au Cu Ag Au Ounces Ag Ounces Category (000’s) Cu Tonnes (g/t) (%) (g/t) (000’s) (000’s) Total Measured Resources (Oxides 2,184 1.84 1.89 49.3 129 41,283 3

  26. Slide 26: Don Mario Reserves

    Slide 26: Don Mario Reserves

    DON MARIO RESERVES V BOLIVIA Stockpile Mineral Reserves – Sept. 30, 2024 Estimated metal recoveries based on processing by sulphidation. Tonnes Grade Contained Metal Notes: Au 1. CIM (2014) definitions were followed for Mineral Reserves as Au Cu Ag Cu Ag Ounces Category (000’s) Ounces originally pre

  27. Slide 27: Taguas Resources

    Slide 27: Taguas Resources

    TAGUAS RESOURCES Taguas Mineral Resources – September 30, 2024 V ARGENTINA Tonnes Grade Contained Metal Au Ag Cu Au Ounces Ag Ounces Cu Lbs Location (000’s) (g/t) (g/t) (%) (000’s) (000’s) (million) Cerro Taguas (Indicated) 39,463 0.37 11.1 467 14,037 Cerro Taguas (Inferred) 98,162 0.30 9.2 0.14 936

  28. Slide 28: Taguas Project – PEA NI 43-101

    Slide 28: Taguas Project – PEA NI 43-101

    TAGUAS PROJECT – PEA NI 43-101 This PEA refers only to the oxidized gold-silver mineralization occurring near surface in Cerro Taguas. This PEA is dated December 2021, it doesn’t include the information of the FY2022 infill campaign. V ARGENTINA Estimate of Inferred Mineral Resource for Cerro Taguas

  29. Slide 29: Management

    Slide 29: Management

    MANAGEMENT Juan Gavidia Nuria Menéndez Binh Vu Raúl Álvarez Rubén Collar Guadalupe CEO since 2018 CFO since 2018 Collar & GM Orovalle since 2016 VP Legal Affairs Director of Exploration & Director of Operations Director of Geology 40 years work experience in Technical Services Orovalle Orovalle Gene

  30. Slide 30: Contact

    Slide 30: Contact

    70 York Street, Suite 1710 Toronto, Ontario Canada M5J 1S9 T 416-369-1629 www.orvana.com Nuria Menéndez Chief Financial Officer nmenendez@orvana.com

Source: Internet Archive copy of s2.q4cdn.com