Slide 1: Barruecopardo Tungsten Project
ORMONDE MINING ‐ AGM 2015 Presentation BARRUECOPARDO TUNGSTEN PROJECT 31 July 15

Slide 2: Disclaimer
ORMONDE MINING Disclaimer The content of this document has not been approved by an authorised person within the meaning of the Financial Services and Markets Act 2000 (as amended). Reliance on this document for the purpose of engaging in any investment activity may expose an individual to a signific

Slide 3: Operations – Low risk…
Operations – Low risk… Simple Mining: Open‐pit, contract mining, utilising and benefiting from experienced mining contractors in the region Simple Processing: Simple gravity processing provides for a plant (1.1mtpa) that can operate efficiently and with added benefit of ~40% spare capacity Env

Slide 4: Capex and Opex – Low Cost...
Capex and Opex – Low Cost... Barruecopardo Project Capex EURm DFS (Jacobs, 2012) reported project development Plant Engineering & Construction 32.5 Capex of €48.5M (including contingency) and Opex of €99.2 per mtu Project Services (land, power‐line, fencing, etc..) 4.5 Basic engineering design b

Slide 5: Global production cost curve – Low end…
Global production cost curve – Low end… Global tungsten production cost curve, 2014 ($/mtu WO3) Barruecopardo production cost % of total output - cumulative Source: Argus Media Ltd, February 2015 5

Slide 6: Price trough – Good time to develop
Price trough – Good time to develop US$/mtu for European APT $500 $450 $400 $350 Chinese domestic demand increases and Weakening commodity export quotas coming into effect price environment $300 $250 Price rebound after GFC, plus stockpiling $200 $150 $100 $50 * Argus Media Supply Concerns EU decl

Slide 7: Project preparation
ORMONDE Project preparation MINING – Pieces in place Oaktree Funding Package Feasibility Metallurgical Study Mining Testwork Concession Community Environmental Political Permit Reserves Support Support Land Environment Drilling Acquisition Baseline Resources Process Studies 7

Slide 8: Oaktree funding – Comprehensive and flexible
Oaktree funding – Comprehensive and flexible Comprehensive Funding Package USD 99.7 million package, split favourably ‐ large component of equity USD 44.2 million and project debt USD 55.5 million Package secures Barruecopardo’s full funding requirement plus a significant budget to conduct the e

Slide 9: Oaktree funding – Dilution minimisation
Oaktree funding – Dilution minimisation Minority Protection and Management Fee A number of important decisions requiring the consent of both parties provide minority protections for Ormonde Ormonde will receive an annual management fee of €1.0 million covering Ormonde’s current working capital r

Slide 10: Project Timeline – Rapid advancement
Project Project timeline Outline –Rapid Timeline advancement H2 2015 H1 2016 H2 2016 PLANT ENGINEERING & CONSTRUCTION Detailed Engineering Procurement Construction & Installation Commissioning LAND Rental and Expropriation WATER MANAGEMENT Construction and Pit de‐watering MINING PREPARATION Mining &

Slide 11: 2015 Q3 – Busy time ahead
2015 Q3 – Busy time ahead Freeze site layouts and process flow diagrams Place priority 1 equipment orders Negotiate construction management contract Finalise purchase of rented lands Advance land expropriation Place first environmental bond Obtain urban planning license Obtain water

Slide 12: Mine life – Clear potential to extend
Mine life – Clear potential to extend Current open pit captures only ~40% of the current total Resources Current drilling limited to an average of 250m below surface 12

Slide 13: Value adding
Value adding Objective of extending the currently defined 9 year mine life, through drilling programme Aim to achieve early evaluation of potential Stage 2 underground extension Thereafter, investigate licence areas in the vicinity of the Barruecopardo Mine Licences include many areas of his

Slide 14: Ormonde Mining - Focused
Ormonde Mining ‐ Focused Focused on Shareholder Value Bringing Barruecopardo Project online on budget and on time Aggressively growing the value of the Barruecopardo asset 14

Slide 15: Barruecopardo Tungsten Project
ORMONDE MINING ‐ AGM 2015 Presentation • Project Permitted • Project Funded • Project Upside BARRUECOPARDO TUNGSTEN PROJECT July 2015 15
Source: Internet Archive copy of ormondemining.com
More decks from Ormonde Mining PLC
Investor Presentation (November 2023)17 slides · November 2023
Shareholder Meeting (September 2019)26 slides · Sep 23, 2019
Shareholder Meeting (September 2018)19 slides · Sep 27, 2018
Investor Presentation (August 2018)24 slides · August 2018
Shareholder Meeting (September 2017)18 slides · Sep 18, 2017
Investor Presentation (March 2017)21 slides · March 2017