  1. Slide 1: Annual General Meeting

    Annual General Meeting 27 September 2018 Turnkey crush and screen plant - Barruecopardo Tungsten Project, Spain 1

  2. Slide 2: Disclaimer

    ORMONDE MINING Disclaimer The content of this document has not been approved by an authorised person within the meaning of the Financial Services and Markets Act 2000 (as amended). Reliance on this document for the purpose of engaging in any investment activity may expose an individual to a signific

  3. Slide 3: Summary

    Summary ▪ Ormonde’s primary activity is through its 30% interest in the Barruecopardo Tungsten Project, Spain o Mine construction well advanced and commissioning commenced o Projected construction costs remain within €53.6M budget o Initial production scheduled for Feb-19, followed by ramp-up phase

  4. Slide 4: Tungsten price - past 12 months

    Tungsten price - past 12 months APT closures / reductions related to environmental inspections in Jiangxi Province Correction / consolidation following steep rise in Q3-17 Chinese production (up from 2016 low of $160 returns, weak trading demand during summer, general fall in metal prices Chinese Ne

  5. Slide 5: Tungsten Outlook

    Tungsten Outlook ▪ Generally positive supply-demand outlook: o “Pricing momentum is forecast to accelerate in Q1 2019 on the back of potential Chinese government-enforced environmental inspections reducing tungsten supply during the period, as well as restocking activity early in the year and furthe

  6. Slide 6: Project Outline 2017 - Site overview and status

    September Project Outline 2017 –Timeline Site overview and status Dam earthworks Workshop Contractor area • Ramp up of construction and implementation • Advancing detailed engineering, procurement, major contract tenders • Early construction works such as dams construction and site facilities (works

  7. Slide 7: Project Outline 2018 - Site overview and status

    September Project Outline 2018 –Timeline site overview and status Crush & Screen Process ROM Pad Plant Plant Water Treatment Plant Main Water Dam Workshop Dam A Offices HT Substation ✓ Crush & Screen Plant: Construction completed, in commissioning ✓ Process Plant: 80% complete, commissioning to comm

  8. Slide 8: Site Fly-Over Video

    SiteProject Fly-Over Outline VideoTimeline 8

  9. Slide 9: Construction: Crush & screen plant complete

    Construction: Project Outline Crush Timeline & screen plant complete 1.1 million tonnes per year of ore, blocks up to 80cm ROM (“Run of Mine”) stockpile Primary crusher Crushed ore stockpile & reclaim tunnel Primary screen Secondary, tertiary & quaternary crushers Secondary screens Fine ore (up to 5

  10. Slide 10: Construction: Process plant well advanced

    Construction: Project Outline Process Timeline plant well advanced 10

  11. Slide 11: Construction: Process plant well advanced

    Construction: Project Outline Process Timeline plant well advanced 11

  12. Slide 12: Construction: Process plant well advanced

    Construction: Project Outline Process Timeline plant well advanced 12

  13. Slide 13: Construction: Process plant well advanced

    Construction: Project Outline Process Timeline plant well advanced ▪ High quality equipment suppliers including Metso, FL Smidth, Weir Minerals, IHC, Holman Wilfley, etc. ▪ Process pipework and electrical installations commenced ▪ Erection of preconcentration screen structure also underway 13

  14. Slide 14: Process plant: preconcentration circuit

    Process Project plant Outline installed Timeline equipment Preconcentration circuit – gravity separation using jigs & spirals: ▪ Crushed feed is screened, with material over 1mm size going to jigs, and below 1mm size going to spirals ▪ Both methods use the simple properties of water, gravity and the

  15. Slide 15: Process plant: upgrade circuit

    Process Project plant Outline installed Timeline equipment Upgrade circuit: ▪ Shaking tables to remove silicates ▪ Small flotation circuit to remove sulphides Shaking table ▪ Tungsten concentrate then thickened, dried and cooled to produce a saleable product ▪ (saleable product 65% WO3, Barruecopard

  16. Slide 16: Commissioning in progress

    Commissioning Project Outline in Timeline progress ✓ Crush & Screen Plant: Commissioning in progress ✓ Water Treatment Plant: Initial commissioning complete ✓ Water Pipeline: Commissioned, pit dewatering underway ✓ Process Plant: Early Dec-18 to Feb-19 Stockpile feed conveyor ROM pad Crushed ore sto

  17. Slide 17: Funding status

    Funding Project status Outline Timeline EGM Circular Saloro Forecast ITEM Variance (Grouped) (31 Aug 18) €M €M €M Capex (plus related VAT) 56.5 54.7 - 1.8 Holding Costs, inc. Management & Monitoring Fees 8.1 11.8 3.7 Transaction Costs & Interest During Construction 7.5 7.9 0.4 Other Costs 6.0 7.0 1.

  18. Slide 18: Looking ahead: next months

    Looking Project ahead: Outline next Timeline 12 months ▪ Q4’18 – Q1’19: o Process plant completion by Dec-18 • Capex expected to remain on budget o Commissioning of crush and screen plant, water management system, site services to be completed o Production readiness activities, including: • grade co

  19. Slide 19: Annual General Meeting

    Annual General Meeting 27 September 2018 Turnkey crush and screen plant - Barruecopardo Tungsten Project, Spain 19