PT Merdeka Copper Gold Tbk · IDX:MDKA
PT Merdeka Copper Gold Tbk — Mines and Money Asia (April 2017)
16 slides from PT Merdeka Copper Gold Tbk's conference presentation, April 2017

Slide 1: Asia’s newest major gold producer
Asia’s newest major gold producer Tujuh Bukit Oxide Gold Silver Heap Leach Mines and Money Asia Company Spotlight Presentation Paul “Muddy” Willis April 2017 PT Merdeka Copper Gold Tbk. 1

Slide 2: Disclaimer
Disclaimer PT Merdeka Copper Gold Tbk (“PT MCG”) make no representation or warranty (express or implied) as to the accuracy, reliability or completeness of the information. All statements in this document, other than statements of historical facts that address future timings, activities, events and

Slide 3: What is the stage of the Project?
What is the stage of the Project? In Production and Listed on Indonesian Stock Exchange - MDKA 1. Gold Heap Leach Project 2. Porphyry Copper Project 3. Growth Options Low Capex, Low Opex & Low Risk Bulk Underground Mine Identified and executable options to Updated Scoping Study Q2 2017 IN PRODUCTION

Slide 4: Where is the Project located?
Where is the Project located? East Java, Indonesia…..an outstanding mineral address PT Merdeka Copper Gold Tbk. 4

Slide 5: What is being mined at the Project?
What is being mined at the Project? Significant Mineral Resources and Ore Reserves Mineral Resource Estimate – December 2016 1. Gold Heap Leach Project Low Capex, Low Opex & Low Risk 99 Mt @ 0.8 g/t Au & 24.8 g/t Ag IN PRODUCTION Containing: 2.5 Moz Au & 79 Moz Ag • Initial CAPEX US$137m • Ore Reser

Slide 6: Updated Ore Reserve Estimates – December 2016
What is being mined at the Project? Updated Ore Reserve Estimates – December 2016 Tujuh Bukit Heap Leach Tonnes Gold Silver Gold Silver Additional Comments Project (Mt) (g/t) (g/t) (oz) (Moz) Pit A Proven 12.106 0.86 17.6 331,000 6.807 1. LOM Mining Sequence • Pit B West, Pit E Probable 4.507 0.79 1

Slide 7: What is being mined at the Project?
What is being mined at the Project? Production Commenced March 2017 PT Merdeka Copper Gold Tbk. 7

Slide 8: What is being mined at the Project?
What is being mined at the Project? Production Commenced March 2017 PT Merdeka Copper Gold Tbk. 8

Slide 9: What is being mined at the Project?
What is being mined at the Project? Production Commenced March 2017 PT Merdeka Copper Gold Tbk. 9

Slide 10: What is being mined at the Project?
What is being mined at the Project? Production Commenced March 2017 PT Merdeka Copper Gold Tbk. 10

Slide 11: What is being mined at the Project?
What is being mined at the Project? First Gold Pour March 2017 PT Merdeka Copper Gold Tbk. 11

Slide 12: 1. Expanding the Oxide Gold Heap Leach Project
What are the upsides for the Company? 1. Expanding the Oxide Gold Heap Leach Project Oxide Expansion Study due for completion Q3 2017 • Increase Heap Leach Pad capacity ~ 50Mt (current 36Mt) • Increase Crushing and Agglomeration capacity ~ 6Mtpa (current 4Mt) • ADR Processing Plant and Environmental

Slide 13: 2. Updated Scoping Study June 2017 then moving to PFS
What are the upsides for the Company? 2. Updated Scoping Study June 2017 then moving to PFS MRE Tujuh Bukit Cut-off Tonnes Gold Copper Gold Copper Porphyry Project 1 (% Cu) (Mt) (g/t) (% Cu) (M oz) (M lbs) Resources Measured 0.2 Indicated 0.2 Inferred 0.2 1,942 0.45 0.45 28.124 19,285 Resources Infe

Slide 14: Copper grade vs gold grade comparison
What are the upsides for the Company? 2. Updated Scoping Study June 2017 then move to PFS 1.2% Golpu 1.0% Grasberg Copper grade 0.8% (%) Northparkes Tujuh Bukit Global Tujuh Bukit Upper High 0.6% Resource Grade Zone Oyu Tolgol Tampakan 0.4% Batu Hijau Frieda River Ok Tedi Cadia Valley Didipio Namosi

Slide 15: What are the risks involved with the Project?
What are the risks involved with the Project? Construction Risk • Completed Financing and Permits • Completed Operational Risk • Ramp Up Production Rate • Mitigated with experienced operational team Environmental Risk • Unplanned discharge • Mitigated with environmental control dams and detox system

Slide 16: Building Indonesia’s next world class mining company
What is the vision for the Company? Building Indonesia’s next world class mining company 1. Gold Heap Leach Project 2. Porphyry Copper Project 3. Growth Options Low Capex, Low Opex & Low Risk Bulk Underground Mine Identified and executable options to Updated Scoping Study June 2017 IN PRODUCTION Def
Source: company website
More decks from PT Merdeka Copper Gold Tbk
9M 2026 Earnings Presentation26 slides · Nov 23, 2026
H1 2026 Earnings Presentation25 slides · Sep 28, 2026
H1 2025 Earnings Presentation19 slides · Sep 26, 2025
9M 2024 Earnings Presentation22 slides · Dec 20, 2024
H1 2024 Earnings Presentation11 slides · Oct 1, 2024
Investor Presentation (August 2024)34 slides · August 2024