Element 25 Limited · ASX:E25

Element 25 — NWR Critical Minerals Presentation (May 2026)

28 slides from Element 25's conference presentation, May 13, 2026

  1. Slide 1: Building a Global Manganese Business

    Building a Global Manganese Business Sustainable manganese ore and HPMSM for global steel and battery markets. Presentation – NWR Critical Minerals (13 May 2026) ASX : E25 OTCQX : ELMTF

  2. Slide 2: Disclaimer

    Disclaimer This presentation (Presentation) contains only a brief overview of Element 25 Limited and its associated entities (Element 25 or E25) and their respective activities and operations. The contents of this presentation, including matters relating to the geology of Element 25's projects, may

  3. Slide 3: Element 25 Introduction

    Element 25 Introduction Long Life 100% Owned Manganese Mine E25 Construction Ready Mine Expansion Strong Feasibility Study/Financials ELMTF ESG Leading Innovative HPMSM Flowsheet ISSUED SHARES 326M Tier 1 Jurisdiction Tier 1 Project Customers & Partners TOTAL DEBT NIL 3

  4. Slide 4: Strategic Vision to Create Shareholder Value

    Strategic Vision to Create Shareholder Value Butcherbird Expansion Louisiana HPMSM Expand Globally 1.1Mt p.a. Manganese Concentrate USA Critical Raw Materials HPMSM Expansion - EU & Asia Build and commission a large-scale processing Construct the first US HPMSM processing facility Multiple HPMSM mod

  5. Slide 5: The Butcherbird Manganese Project

    The Butcherbird Manganese Project

  6. Slide 6: The Butcherbird Manganese Project

    The Butcherbird Manganese Project World Class Large Scale Long-Life Mine Production Resource >18 years production >270M tonnes 1.1M tonnes per year ▪ Unique geology - very clean metallurgically – no toxic contaminants. ▪ Located in Australia, a Tier-1 jurisdiction with strong ESG regulation. ▪ Produ

  7. Slide 7: Large, Long-Life Manganese Mine in Western Australia

    Large, Long-Life Manganese Mine in Western Australia CONSTRUCTION READY Manganese ore loadout • Granted Mining Lease during Stage 1 pilot • Fully Permitted operations. Mining Lease - M52/1074 Mining Reserve: 101.4Mt @ 10.4% Mn1 • Early Procurement Commenced • Existing infrastructure in place (bore f

  8. Slide 8: Simple Geology: Low-Cost, Low-Impact Operations

    Simple Geology: Low-Cost, Low-Impact Operations Classification Tonnes (Mt) Mn (%) Contained Mn (Mt) RESOURCE GROWTH POTENTIAL Resource 274 10.0 27.4 • Large resource offers long term Reserve 101.4 10.4 10.5 operating potential. • Mineralisation outside existing resource provides upside. • Ore suitab

  9. Slide 9: Butcherbird to Expand to 1.1Mt p.a. Production

    Butcherbird to Expand to 1.1Mt p.a. Production New, re-designed and expanded processing facility to optimise and scale the process. LOGWASHER Key Metrics Unit Value Ore Mined Ktpa 6,100 Concentrate Prod. Ktpa 1,100 SCREEN DMS PLANT Concentrate Grade Mn 31.6% Undiscounted AUD (pa) $70.5 Cashflow Mine

  10. Slide 10: Butcherbird Expansion Project - Process Plant

    Butcherbird Expansion Project - Process Plant Washing Circuit: Clay removal from laterite feed • The logwasher is an agitated scrubber which acts to break up and wash clays out of the feed material. • The clay contains very little manganese so its removal upgrades the concentrate to approach the tar

  11. Slide 11: Butcherbird Expansion Delivers Robust Economics

    Butcherbird Expansion Delivers Robust Economics AUSTRALIAN FEDERAL GOVERNMENT (NAIF) TO PROVIDE $50 MILLION FINANCE PACKAGE FOR BUTCHERBIRD EXPANSION PROJECT • Northern Australia Infrastructure Facility (NAIF) to provide up to AU$50 million senior debt facility for Element 25’s Butcherbird Manganese

  12. Slide 12: Manganese Is Comparatively Abundant But Not Everywhere…

    Manganese Is Comparatively Abundant But Not Everywhere… • Manganese deposits heavily concentrated in Manganese ore global distribution: challenging jurisdictions. • Australia is the only allied country with significant manganese reserves and production. • Australian manganese production declining wi

  13. Slide 13: Butcherbird Expansion – Low Costs Underpin Strong Margins

    Butcherbird Expansion – Low Costs Underpin Strong Margins Historical Mn Ore Price Cycles – US$/dmtu CIF China 36.5% Mn Index High Grade Index (historical) (historical) BBX AISC Cost (2025 FS) BBX Sale Price 44% Index Basis (Yrs 1-5 2025 FS) Reference: Project Blue 2025 15 Reference: Company ASX Rele

  14. Slide 14: Butcherbird Expansion Project – On Track for Production

    Butcherbird Expansion Project – On Track for Production • Detailed engineering well advanced utilizing Integrated project Team (IPT) approach. • Long lead time procurement progressed with orders placed for crusher and logwasher equipment. • Key construction and operational contracts being finalised

  15. Slide 15: Butcherbird Expansion Project Timeline Guidance

    Butcherbird Expansion Project Timeline Guidance BBX Project Plan Summary 2026 2027 Quarter 1 2 3 4 1 2 3 4 Month J F M A M J J A S O N D J F M A M J J A S O N D Major Milestones Finalise Funding Commissioning Commercial Production Major Activities All Approvals and Permitting Project Financing Detai

  16. Slide 16: High Purity Manganese Strategy

    High Purity Manganese Strategy

  17. Slide 17: Manganese Is Abundant But Refining Capacity Is Not…

    Manganese Is Abundant But Refining Capacity Is Not… Refined battery grade manganese capacity is heavily concentrated in China. Manganese South Africa Ore China Other Refined Manganese Breaking the Chinese Supply Chain Dominance • Refined manganese (HPMSM) capacity is heavily concentrated with >95% o

  18. Slide 18: Improved, Cost-Competitive, Cleaner Process Technology

    Improved, Cost-Competitive, Cleaner Process Technology The Element 25 Process brings significant changes & improvements: E25 technology enhances ESG profile by: • Eliminating waste residues. • Eliminating toxic Reagents like fluorine. • Increased efficiency and lower costs. Fewer Reagents Lower Emis

  19. Slide 19: Global Refining Capacity in the Longer Term

    Global Refining Capacity in the Longer Term ** Flagship Louisiana HPMSM Facility: EU EU & UK policy shifts are MoU signed with Nissan • Supply chain security needs driving competing with the IRA Chemical Corporation to capital flows into US projects. for investment in battery jointly develop HPMSM •

  20. Slide 20: Global EV Sales Outlook Remains Strong

    Global EV Sales Outlook Remains Strong Global passenger-vehicle sales by drivetrain EV market share continues to grow: • Electric vehicles to reach over 50% market penetration by 2030 according to Bloomberg NEF. • Short term policy settings have reduced uptake in some markets but medium-term demand

  21. Slide 21: Transition to Higher Manganese Battery Cathodes

    Transition to Higher Manganese Battery Cathodes LMFP, LMR, LMNO and NMX cathode chemistries offer improved safety, higher energy density, reduced cost per kWh and greater supply chain flexibility. High Mn means reduced reliance on Ni and Co: Reduced nickel and very low to no cobalt content. Referenc

  22. Slide 22: Louisiana Battery Grade HPMSM

    Louisiana Battery Grade HPMSM

  23. Slide 23: DoE MESC Grant - Supporting Local Raw Material Supply

    DoE MESC Grant - Supporting Local Raw Material Supply Local Supply Chain Mn Ore Comminution • Process and supply chain developed to maximise U.S. industry US$166M Reductant involvement. Leach Grant • Working with partners GM and Acid Stellantis to supply low carbon HPMSM for EV batteries. Purificati

  24. Slide 24: Global Sustainable Secure Manganese Supply

    Global Sustainable Secure Manganese Supply • 18.3 Year Reserve within granted Mining Lease Long Mine Life • 274Mt Resource global resource with exploration upside • Feasibility Study and project permitting complete Construction Ready • Northern Australia Infrastructure Facility (NAIF) finance of up

  25. Slide 25: The Planned Element 25 HPMSM facility in Louisiana, USA

    The Planned Element 25 HPMSM facility in Louisiana, USA For Illustration Purposes Only 27 *Subject to successful project financing and permitting

  26. Slide 26: Contact Details

    Contact Details Justin Brown Media Inquiries: Managing Director Nathan Ryan Email: admin@e25.com.au Email: nathan.ryan@nwrcommunications.com.au Phone: +61 (8) 6375 2525 Phone: +61 (0) 420 582 887 ASX : E25 OTCQX : ELMTF

  27. Slide 27: Butcherbird Manganese Mine - Resources & Reserves

    Butcherbird Manganese Mine - Resources & Reserves 1 Ore Reserve Deposit Classification Tonnes (Mt) Grade (Mn%) Contained Mn (Mt) • Current Reserve: Proved 11.3 11.8 1.33 Yanneri Ridge • Only utilises approximately ~40% of Probable 70.4 10.2 7.15 Coodamudgi Proved - - - global Mineral Resource; Proba

  28. Slide 28: Competent Person’s Statement

    Competent Person’s Statement The information in this report that relates to Exploration Results and Exploration Targets is based on information compiled by Mr Justin Brown who is a member of the Australasian Institute of Mining and Metallurgy. At the time that the Exploration Results and Exploration