Pan African Resources Plc · LSE:PAF

Pan African Resources — BMO Capital Markets Global Metals and Mining Conference 2024

44 slides from Pan African Resources's conference presentation, Feb 28, 2024

  1. Slide 1: Mining for a Future – Investor Presentation

    XXX MINING FOR A FUTURE INVESTOR PRESENTATION OTCQX: PAFRF/PAFRY | AIM: PAF | JSE: PAN www.panafricanresources.com 1

  2. Slide 2: Disclaimer and Forward Looking Statements

    XXX DISCLAIMER AND FORWARD LOOKING STATEMENTS The name 'Presenter' refers to Pan African Resources PLC and its advisors, subsidiaries or affiliated companies. This presentation has not been filed, lodged, registered or approved in any jurisdiction and recipients of this document should keep themselv

  3. Slide 3: Overview of Presentation

    XXX OVERVIEW OF PRESENTATION Health and safety Group overview Our operating environment H1 FY2024 – Key features Performance by operation Group AISC Capital projects (ZAR) ESG: Our “Beyond compliance” approach Financials Exploration – Republic of the Sudan FY2024 – Focused on execution Appendix OTCQ

  4. Slide 4: Health and Safety

    1. Health and safety 2. Group overview 2.1 Our operating environment 2.2 H1 FY2024 – Key features 2.3 Performance by operation 2.4 Group AISC 2.5 Capital projects (ZAR) 3. ESG: Our “Beyond compliance” approach 4. H1 FY2024 Financials 5. Exploration – Republic of the Sudan 6. FY2024 – Focused on exec

  5. Slide 5: Group Safety Performance

    HEALTH AND SAFETY XXX HEALTH AND SAFETY GROUP SAFETY PERFORMANCE Group TRIFR improved by 39.3% to 6.13 (H1 FY23: 8.54) per million-man hours Excellent operational safety performance • LTIFR remained stable at 2.54 (H1 FY23: 2.54) per million-man hours Evander Mines’ underground operations LTIFR and

  6. Slide 6: Group Overview

    1. Health and safety 2. Group overview 2.1 Our operating environment 2.2 H1 FY2024 – Key features 2.3 Performance by operation 2.4 Group AISC 2.5 Capital projects (ZAR) 3. ESG: Our “Beyond compliance” approach 4. H1 FY2024 Financials 5. Exploration – Republic of the Sudan 6. FY2024 – Focused on exec

  7. Slide 7: Group Overview: Underground and Surface Mining Operations

    GROUP OVERVIEW XXX GROUP OVERVIEW A UNIQUE COMBINATION OF UNDERGROUND AND SURFACE MINING OPERATIONS PAR Group gold production profile 300 000 ~250,000oz 250 000 ~220,000oz 201,777oz 205,688oz c.180,000 200 000 - 190,000oz 175,209oz 150 000 100 000 50 000 0 2021 2022 2023 2024 2025 2026 * Barberton B

  8. Slide 8: H1 FY2024 Gold Production

    GROUP OVERVIEW XXX GROUP OVERVIEW H1 FY2024 GOLD PRODUCTION  6.7% TO 98,458oz (H1 FY2023: 92,307oz) Moving towards a balanced mix of low-cost surface mining and high-grade, long-life u/g mines 35% - 45% SURFACE 65% - 55% U/G MTR + Soweto Cluster Evander Mines Ann Prod: 50-60koz FY25-FY26 estimated

  9. Slide 9: Group Overview

    1. Health and safety 2. Group overview 2.1 Our operating environment 2.2 H1 FY2024 – Key features 2.3 Performance by operation 2.4 Group AISC 2.5 Capital projects (ZAR) 3. ESG: Our “Beyond compliance” approach 4. H1 FY2024 Financials 5. Exploration – Republic of the Sudan 6. FY2024 – Focused on exec

  10. Slide 10: Our Operating Environment

    OUR OPERATING ENVIRONMENT XXX OUR OPERATING ENVIRONMENT 140 YEAR TRACK RECORD OF OPERATING SUCCESSFULLY IN SOUTH AFRICA ELECTRICITY AND SA REGULATORY SECURITY AND PUBLIC/PRIVATE STAKEHOLDER ENGAGEMENT FRAMEWORK COLLABORATION • National grid power to Group mining • Multi-facetted engagements with all

  11. Slide 11: Renewable Energy Roadmap

    OUR OPERATING ENVIRONMENT XXX OUR OPERATING ENVIRONMENT OPERATING SUCCESSFULLY IN SOUTH AFRICA – RENEWABLE ENERGY ROADMAP Current pipeline of Group renewable energy projects 45% 40,0% 80MW of 40% Commission installed solar 8.75MW solar PV 35,4% PV renewable Commissioned Expand Evander 35% 1st 9.9MW

  12. Slide 12: Group Overview

    1. Health and safety 2. Group overview 2.1 Our operating environment 2.2 H1 FY2024 – Key features 2.3 Performance by operation 2.4 Group AISC 2.5 Capital projects (ZAR) 3. ESG: Our “Beyond compliance” approach 4. H1 FY2024 Financials 5. Exploration – Republic of the Sudan 6. FY2024 – Focused on exec

  13. Slide 13: H1 FY2024 Key Features

    H1 FY2024 KEY FEATURES XXX H1 FY2024 KEY FEATURES OPERATIONAL AND FINANCIAL PERFORMANCE PRODUCTION PERFORMANCE COST PERFORMANCE FINANCIAL PERFORMANCE Group gold production of 98,458oz  Group AISC  0.3% to US$1,287/oz Robust performance in H1 FY24 6.7% (H1 FY23 US$1,291/oz) – despite • Profit for t

  14. Slide 14: Group Overview

    1. Health and safety 2. Group overview 2.1 Our operating environment 2.2 H1 FY2024 – Key features 2.3 Performance by operation 2.4 Group AISC 2.5 Capital projects (ZAR) 3. ESG: Our “Beyond compliance” approach 4. H1 FY2024 Financials 5. Exploration – Republic of the Sudan 6. FY2024 – Focused on exec

  15. Slide 15: Performance by Operation: Elikhulu

    PERFORMANCE BY OPERATION XXX PERFORMANCE BY OPERATION TAILINGS OPERATIONS – ELIKHULU • Production  8.8% to 28,106oz (H1 FY23: 25,830oz) Elikhulu LOM production profile* • Improved overall metallurgical recovery of 34.9% (H1 FY23: 32.3%) 80 000 • AISC of US$979/oz (H1 FY23: US$947/oz) – one of the l

  16. Slide 16: Performance by Operation: BTRP and Royal Sheba

    PERFORMANCE BY OPERATION XXX PERFORMANCE BY OPERATION TAILINGS OPERATIONS – BTRP AND ROYAL SHEBA • Production remained consistent at 9,864oz (H1 FY23: 10,012oz) BTRP LOM extension: Sheba Fault Project • Lowest cost of production in the Group • Royal Sheba and Western Cross orebodies – orebodies open

  17. Slide 17: Performance by Operation: Mintails

    PERFORMANCE BY OPERATION XXX PERFORMANCE BY OPERATION TAILINGS RETREATMENT OPERATIONS – MINTAILS October 2022 – Closure of transaction to acquire total share claims and capital of • 800ktpm processing plant design based on successful Elikhulu and BTRP operations Mogale Gold and Mintails SA Soweto Cl

  18. Slide 18: Mogale Plant Construction Timeline to Commissioning

    PERFORMANCE BY OPERATION XXX PERFORMANCE BY OPERATION MOGALE TAILINGS RETREATMENT PLANT CONSTRUCTION IN PROGRESS – TIMELINE TO COMMISSIONING PROPOSED PROJECT EXECUTION TIMELINE ACTIVITY ESTIMATED DATE Completion and finalisation of DFS Completed  Engineering optimisation activities Completed  Deta

  19. Slide 19: Mogale Socio-Economic Development and Environmental Rehabilitation

    PERFORMANCE BY OPERATION XXX PERFORMANCE BY OPERATION MOGALE SOCIO-ECONOMIC DEVELOPMENT AND ENVIRONMENTAL REHABILITATION History >100 years of underground mining in the West Rand region of the Witwatersrand Goldfield • Production of over 2,000 tons of gold and 240 Mt of low-grade gold-bearing tailin

  20. Slide 20: Building a World Class Surface Tailings Retreatment Business

    PERFORMANCE BY OPERATION XXX PERFORMANCE BY OPERATION BUILDING A WORLD CLASS SURFACE TAILINGS RETREATMENT BUSINESS Elikhulu and Mintails production profile 140 000 Forecast 120 000 Gold production (oz) 100 000 Actual 80 000 60 000 40 000 20 000 0 2022 2023 2024 2025 2026 2027 2028 2029 2030 2031 203

  21. Slide 21: Evander Underground

    PERFORMANCE BY OPERATION XXX PERFORMANCE BY OPERATION EVANDER UNDERGROUND EVANDER 8 SHAFT • Production  11.1% to 21,307oz in H1 FY24 (H1 FY23: 19,173oz) • Tons milled  16% to 89,7Kt u/g tons milled at 7.4g/t (H1 FY23: 73,9Kt at 8.1g/t) • AISC of US$1,228/oz (H1 FY23: US$1,052/oz) – increase due to

  22. Slide 22: Evander Gold Mine – Significant Capital Investment

    PERFORMANCE BY OPERATION XXX PERFORMANCE BY OPERATION EVANDER GOLD MINE – SIGNIFICANT CAPITAL INVESTMENT FOR LONG-TERM SUSTAINABILITY Underground refrigeration plant Equipping of vent shaft at 17 Level Grout plant constructed at 8 Shaft • Phase 1 of refrigeration plant at 24 Level – commissioned in

  23. Slide 23: Evander Solar Plant and Water Retreatment Plant

    PERFORMANCE BY OPERATION XXX PERFORMANCE BY OPERATION EVANDER GOLD MINE – SIGNIFICANT CAPITAL INVESTMENT FOR LONG-TERM SUSTAINABILITY Evander Solar Plant Water Retreatment Plant • 9.9 MW Solar renewable energy plant – commissioned in May 2022 • EGM water retreatment plant was commissioned in June 20

  24. Slide 24: Fairview Mine

    PERFORMANCE BY OPERATION XXX PERFORMANCE BY OPERATION FAIRVIEW MINE Initiatives implemented to improve gold production • Continuous operations cycle • Gold production  17% to 22,194oz (H1 FY23: 19,041oz) • Average u/g RoM volumes from MRC and Rossiter orebodies improved to an average of 10,000tpm (

  25. Slide 25: Barberton Mines' Smaller Underground Operations

    PERFORMANCE BY OPERATION XXX PERFORMANCE BY OPERATION BARBERTON MINES’ SMALLER UNDERGROUND OPERATIONS SHEBA MINE Gold production  19% to 11,139oz (H1 FY23: 9,359oz) • Improved production is attributed to MRC orebody and three higher grade Zwartkoppie (ZK) ore blocks, as well as the South Wall adit

  26. Slide 26: Operational Overview

    1.0 Health and safety 2.0 Group overview 2.1 Our operating environment 2.2 H1 FY2024 – Key features 2.3 Performance by operation 2.4 Group AISC 2.5 Capital projects (ZAR) 3.0 ESG: Our “Beyond compliance” approach 4.0 H1 FY2024 Financials 5.0 Exploration – Republic of the Sudan 6.0 FY2024 – Focused o

  27. Slide 27: Group AISC

    GROUP AISC XXX GROUP AISC H1 FY2024 – GUIDING AISC OF US$1,325/oz – US$1,350/oz IN FY2024* Lower cost operations Evander Barberton Total lower surface Evander Mines’ cost % Group sources BTRP Elikhulu underground Fairview operations production AISC per kg (ZAR/kg) 1,187,909 390,830 588,435 738,070 8

  28. Slide 28: Group AISC – FY2024 AISC Outlook vs Peers

    US$/oz GROUP AISC 500 1 500 2 000 3 000 0 1 000 2 500 B2Gold Corp Endeavour Mining GROUP AISC Perseus Mining OTCQX: PAFRF/PAFRY | AIM: PAF | JSE: PAN FY 2024 – AISC OUTLOOK Source: Individual company websites and presentations West African Resources Gold Fields - Group Newmont Alamos Gold PAR - lowe

  29. Slide 29: Group Overview

    1. Health and safety 2. Group overview 2.1 Our operating environment 2.2 H1 FY2024 – Key features 2.3 Performance by operation 2.4 Group AISC 2.5 Capital projects (ZAR) 3. ESG: Our “Beyond compliance” approach 4. H1 FY2024 Financials 5. Exploration – Republic of the Sudan 6. FY2024 – Focused on exec

  30. Slide 30: Capital Projects (ZAR)

    CAPITAL PROJECTS (ZAR) XXX CAPITAL PROJECTS (ZAR) INVESTMENT IN ORGANIC GROWTH AND MTR – INCREASING OUR PRODUCTION PROFILE 3 500 3 000 2 500 ZARm 2 000 1 500 1 000 500 0 2021 2022 2023 2024 FC MTR Project 156 1 400 (US$ 76m) Elikhulu - Mostly expansion 64 168 305 270 (US$ 15m) Evander 195 430 1 088

  31. Slide 31: ESG: Our Beyond Compliance Approach

    1. Health and safety 2. Group overview 2.1 Our operating environment 2.2 H1 FY2024 – Key features 2.3 Performance by operation 2.4 Group AISC 2.5 Capital projects (ZAR) 3. ESG: Our “Beyond compliance” approach 4. H1 FY2024 Financials 5. Exploration – Republic of the Sudan 6. FY2024 – Focused on exec

  32. Slide 32: ESG: Our Beyond Compliance Approach

    ESG XXX ESG: OUR “BEYOND COMPLIANCE” APPROACH GOVERNANCE ENVIRONMENT SOCIAL SOCIAL AND COMPLIANCE WATER RECYCLING STAKEHOLDER ENGAGEMENT SUSTAINABLE COMMUNITIES FULLY COMPLIANT WITH GRI REPORTING Responsible and sustainable water use • Engagement forums with communities and Barberton Blueberries far

  33. Slide 33: H1 FY2024 Financials

    1. Health and safety 2. Group overview 2.1 Our operating environment 2.2 H1 FY2024 – Key features 2.3 Performance by operation 2.4 Group AISC 2.5 Capital projects (ZAR) 3. ESG: Our “Beyond compliance” approach 4. H1 FY2024 Financials 5. Exploration – Republic of the Sudan 6. FY2024 – Focused on exec

  34. Slide 34: Summarised Consolidated Financial Results

    H1 FY2024 FINANCIALS XXX H1 FY2024 FINANCIALS SUMMARISED CONSOLIDATED FINANCIAL RESULTS Six months ended Six months ended Movement Salient features Units 31 December 2023 31 December 2022 % Gold produced1 oz 98,458 92,307 6.7 Gold sold oz 98,458 90,439 8.9 Revenue US$ million 193.9 156.5 23.9 US$/oz

  35. Slide 35: Dividends and Shareholder Returns

    H1 FY2024 FINANCIALS - DIVIDENDS AND RETURNS XXX H1 FY2024 FINANCIALS DIVIDENDS AND SHAREHOLDER RETURNS Historic dividend yield – record of returning cash to shareholders 7% 6,3% 5,9% 6% 5,6% 5,3% 5,1% 5,0% 5% 4,6% 4% 3,8% 3% 2% 1,2% 1% 0,0% 0% June 14 June 15 June 16 June 17 June 18* June 19 June 2

  36. Slide 36: Exploration – Republic of the Sudan

    1. Health and safety 2. Group overview 2.1 Our operating environment 2.2 H1 FY2024 – Key features 2.3 Performance by operation 2.4 Group AISC 2.5 Capital projects (ZAR) 3. ESG: Our “Beyond compliance” approach 4. H1 FY2024 Financials 5. Exploration – Republic of the Sudan 6. FY2024 – Focused on exec

  37. Slide 37: Exploration – Republic of the Sudan

    EXPLORATION – REPUBLIC OF THE SUDAN XXX EXPLORATION – REPUBLIC OF THE SUDAN WHY SUDAN? PROGRESS IN FY2024 Third largest gold producer in Africa (after Ghana and SA) and Exploration activities resumed in Q1 FY24, following a detailed 10th in the world (2021) risk assessment of the in-country operatin

  38. Slide 38: Focused on Execution

    1. Health and safety 2. Group overview 2.1 Our operating environment 2.2 H1 FY2024 – Key features 2.3 Performance by operation 2.4 Group AISC 2.5 Capital projects (ZAR) 3. ESG: Our “Beyond compliance” approach 4. H1 FY2024 Financials 5. Exploration – Republic of the Sudan 6. FY2024 – Focused on exec

  39. Slide 39: FY2024: Focused on Execution

    FY2024 – FOCUSED ON EXECUTION XXX FY2024: FOCUSED ON EXECUTION KEY DELIVERABLES INCLUDE • Continue with focus on health and safety initiatives in our proactive journey to ‘zero harm’ • Monitor the Group’s optimisation and improvement initiatives intended to increase production and reduce costs • Suc

  40. Slide 40: Thank you

    XXX Thank you Contact: Hethen Hira, Head of investor relations Email: Hhira@paf.co.za www.panafricanresources.com OTCQX: PAFRF/PAFRY | AIM: PAF | JSE: PAN www.panafricanresources.com 40

  41. Slide 41: Appendix

    1. Health and safety 2. Group overview 2.1 Our operating environment 2.2 H1 FY2024 – Key features 2.3 Performance by operation 2.4 Group AISC 2.5 Capital projects (ZAR) 3. ESG: Our “Beyond compliance” approach 4. H1 FY2024 Financials 5. Exploration – Republic of the Sudan 6. FY2024 – Focused on exec

  42. Slide 42: Company Snapshot

    APPENDIX XXX COMPANY SNAPSHOT Corporate Information Board and Executives As at 2 February, 2024 CORPORATE OFFICE COMPANY SECRETARY KEITH SPENCER The Firs Building Jane Kirton • Chairman JSE (PAN) ZAR434cps 2nd Floor, Office 204 St James’s Corporate Services • Appointed: 8 October 2007 AIM (PAF) GBP1

  43. Slide 43: Reserves and Resources

    APPENDIX XXX RESERVES AND RESOURCES GROWTH PORTFOLIO – ROBUST PROJECT PIPELINE Tonnes Grade Gold Gold Gold Mineral Resources* Mt g/t t Moz Barberton hard rock 24.5 4.2 102.1 3.3 BTRP 22.3 1.2 26.0 0.8 Evander underground 111.1 9.1 1 009.0 32.4 Elikhulu 163.4 0.3 44.2 1.4 Elikhulu 259.8 0.3 78.5 2.5

  44. Slide 44: ESG: Our Beyond Compliance Approach

    ESG XXX ESG: OUR “BEYOND COMPLIANCE” APPROACH OUR COMMITMENT TO SUSTAINABLE DEVELOPMENT – WE HAVE IDENTIFIED 14 UN SDGS TOWARDS WHICH WE CAN HAVE THE MOST MEANINGFUL IMPACT Equity, debt and surplus cash from our operating activities FINANCIAL CAPITAL Infrastructure, orebodies and tailings retreatmen

Pan African Resources — BMO Capital Markets Global Metals and Mining Conference 2024 on 6ix