Pan African Resources Plc · LSE:PAF

Pan African Resources — Investor Presentation (June 2026)

46 slides from Pan African Resources's investor presentation, June 2026

  1. Slide 1: Investor Presentation

    INVESTOR PRESENTATION MINING FOR A FUTURE June 2026

  2. Slide 2: Disclaimer

    DISCLAIMER The name 'Presenter' refers to Pan African Resources PLC and its advisors, subsidiaries or affiliated companies. This presentation has not been filed, lodged, registered or approved in any jurisdiction and recipients of this document should keep themselves informed of and comply with and

  3. Slide 3: Forward Looking Statements

    FORWARD LOOKING STATEMENTS Statements in this presentation that address exploration activities, mining potential and future plans and objectives of Pan African Resources are forward-looking statements and forward-looking information that involve various risks, assumptions and uncertainties and are n

  4. Slide 4: Overview of Presentation

    OVERVIEW OF PRESENTATION Health and safety Group overview Our operating environment Key features-FY26 operational update Performance by operation Group AISC Capital projects Organic growth projects ESG: Our “Beyond compliance” approach FY26H1 Financials FY26 Focused on delivery Appendix LSE: PAF | J

  5. Slide 5: Health and Safety

    1. Health and safety 2. Group overview 2.1 Our operating environment 2.2 Key features 2.3 Performance by operation 2.4 Group AISC 2.5 Capital projects 2.6 Organic growth projects 3. ESG: Our “Beyond compliance” approach 4. FY26H1 Financials 5. FY26 Focused on delivery 6. Appendix HEALTH AND SAFETY

  6. Slide 6: Health and Safety

    HEALTH AND SAFETY HEALTH AND SAFETY FY26H1 GROUP SAFETY PERFORMANCE The Group has delivered sustained improvements in safety performance Ongoing safety focus across all operations across all operations, maintaining its leading position within the South African gold mining sector Safety milestones ac

  7. Slide 7: Group Overview

    1. Health and safety 2. Group overview 2.1 Our operating environment 2.2 Key features 2.3 Performance by operation 2.4 Group AISC 2.5 Capital projects 2.6 Organic growth projects 3. ESG: Our “Beyond compliance” approach 4. FY26H1 Financials 5. FY26 Focused on delivery 6. Appendix GROUP OVERVIEW

  8. Slide 8: Investment Highlights

    GROUP OVERVIEW INVESTMENT HIGHLIGHTS MAIN MARKET LSE LISTING AND INCLUSION IN FTSE250 and JSE Top40 Diversified portfolio of producing gold assets located in two major global mining jurisdictions (South Africa and Australia) Growing production closer to 300koz from a high-margin operating base, gene

  9. Slide 9: Corporate Snapshot

    GROUP OVERVIEW CORPORATE SNAPSHOT Share price performance Capital structure2 (share price 01 June 2026) JSE: PAN (ZAR) cps (ZAR) 2,501 PAN JSE share price vs Gold price : January 2009=100 LSE: PAF (GBP) pps (GBP) 115.1 Shares issued m 2,334 8,000 7,000 PAN +75X Market capitalisation US$m 3,591 Proje

  10. Slide 10: Group Overview

    GROUP OVERVIEW GROUP OVERVIEW A UNIQUE COMBINATION OF UNDERGROUND AND SURFACE MINING OPERATIONS GROUP OPERATIONS Tennant Mines South Africa Further near-term, low-cost production growth Australia Tennant Mines LSE: PAF | JSE: PAN | OTCQX: PAFRF/PAFRY www.panafricanresources.com 10

  11. Slide 11: Production Profile

    GROUP OVERVIEW PRODUCTION PROFILE GROWING GOLD PRODUCTION BY MORE THAN 40% WITHIN ONE YEAR $2,075/oz to $1,354/oz ~$1,870/oz $2,175/oz1 $1,259/oz $1,309/oz $1,354/oz 280-302koz 300 ~275koz ~35% production from surface 48-52koz ~34koz 250 AISC ~$2,543/oz* 197koz Gold production (koz) 206koz 1.5koz ~5

  12. Slide 12: Operational Snapshot

    GROUP OVERVIEW OPERATIONAL SNAPSHOT 60% of production 40% of production Shallow underground and Low-cost surface tailings – environmental clean-up and rehab benefits High-grade, long-life underground mines Surface / UG Surface Underground Asset Tennant Mines MTR Elikhulu BTRP Evander Barberton Locat

  13. Slide 13: Our Operating Environment

    GROUP OVERVIEW OUR OPERATING ENVIRONMENT 140 YEAR TRACK RECORD OF OPERATING SUCCESSFULLY IN SOUTH AFRICA ELECTRICITY ELECTRICITYAND ANDSA RENEWABLE REGULATORY ELECTRICITY AND SA REGULATORY REGULATORY ELECTRICITY FRAMEWORK, AND SA REGULATORY SECURITY AND STAKEHOLDER ENGAGEMENT FRAMEWORK ENERGY FRAMEW

  14. Slide 14: Key Features

    1. Health and safety 2. Group overview 2.1 Our operating environment 2.2 Key features 2.3 Performance by operation 2.4 Group AISC 2.5 Capital projects 2.6 Organic growth projects 3. ESG: Our “Beyond compliance” approach 4. FY26H1 Financials 5. FY26 Focused on delivery 6. Appendix GROUP OVERVIEW Key

  15. Slide 15: FY26 Operational Update

    KEY FEATURES FY26 OPERATIONAL UPDATE OPERATIONAL AND FINANCIAL PERFORMANCE ELECTRICITY AND SA REGULATORY ELECTRICITY AND SA REGULATORY ELECTRICITY AND SA REGULATORY PRODUCTION PERFORMANCE COST PERFORMANCE FINANCIAL PERFORMANCE FRAMEWORK FRAMEWORK FRAMEWORK Group gold production of ~275,000oz 40% Gr

  16. Slide 16: Gold Price Received and Margins

    KEY FEATURES GOLD PRICE RECEIVED AND MARGINS PROFITABILITY DRIVEN BY ZAR/KG GOLD PRICE AND COMPETITIVE UNIT COSTS PROFITABILITY GAP WIDENING ELECTRICITY AND SA REGULATORY AS ANNUAL PRODUCTION RAMPS Gold price received vs AISC FRAMEWORK UP CLOSER TO ~300KOZ in FY27 R/kg • Well-positioned to capitalis

  17. Slide 17: Performance by Operation

    1. Health and safety 2. Group overview 2.1 Our operating environment 2.2 Key features 2.3 Performance by operation 2.4 Group AISC 2.5 Capital projects 2.6 Organic growth projects 3. ESG: Our “Beyond compliance” approach 4. FY26H1 Financials 5. FY26 Focused on delivery 6. Appendix GROUP OVERVIEW Perf

  18. Slide 18: Tailings Retreatment and Surface Business

    PERFORMANCE BY OPERATION TAILINGS RETREATMENT AND SURFACE BUSINESS PROVEN TRACK RECORD OF DELIVERING NEW GOLD PRODUCTION ON BUDGET AND ON SCHEDULE 2013 2015 2018 2024 2025 BTRP ETRP Elikhulu MTR Tennant Mines Stage 1 Nobles Project Capacity (per month) 100kt 200kt 1.2Mt 0.8-1.1Mt 70kt Production (pe

  19. Slide 19: Tailings Operations – Elikhulu

    PERFORMANCE BY OPERATION PERFORMANCE BY OPERATION TAILINGS OPERATIONS – ELIKHULU • Water treatment plant expansion to be fully commissioned in June 2026 • Production of ~ 27,000oz in FY26H2 – on track for > 56,500oz • Substantial water cost savings for FY26 (FY25: 52,606oz) • Increased capacity from

  20. Slide 20: Tailings Operations – BTRP and Sheba Fault

    PERFORMANCE BY OPERATION PERFORMANCE BY OPERATION TAILINGS OPERATIONS – BTRP AND SHEBA FAULT • FY26H2 Production stable at ~5,500oz BTRP life-of-mine plan – new surface sources • on track for FY26 production of ~13,000oz (FY25: 15,224oz) • Increase in production cost as anticipated as residual mater

  21. Slide 21: Mogale Tailings Retreatment (MTR)

    PERFORMANCE BY OPERATION PERFORMANCE BY OPERATION MOGALE TAILINGS RETREATMENT (MTR) • Production of ~30,500oz in FY26H2, on track for ~52,000oz in FY26 • Increase of ~67% over FY25: 30,806oz • FY26H1 AISC of US$1,577/oz (FY25H1: US$1,428/oz) • LOM AISC of ~US$1,200/oz • MTR annual production of ~50,

  22. Slide 22: Mogale Socio-Economic Development and Environmental Rehabilitation

    PERFORMANCE BY OPERATION PERFORMANCE BY OPERATION MOGALE SOCIO-ECONOMIC DEVELOPMENT AND ENVIRONMENTAL REHABILITATION History >100 years of underground mining in the West Rand region of the Wits Basin • Production of over 2,000 tons of gold and 240Mt of low-grade gold-bearing tailings material in num

  23. Slide 23: Tennant Mines

    PERFORMANCE BY OPERATION – TENNANT MINES TENNANT MINES NEAR TERM GOLD PRODUCTION GROWTH IN AUSTRALIA TENNANT CREEK MINERAL FIELD Major historical province Long mine life Historically Australia’s highest- Nobles initial 8-year LOM, with grade gold province strategy to expand to >15 years Stage 1: Nob

  24. Slide 24: Australian Operations – Tennant Mines

    PERFORMANCE BY OPERATION PERFORMANCE BY OPERATION AUSTRALIAN OPERATIONS – TENNANT MINES • Nobles plant construction completed April 2025, first gold pour May 2025 • Completed ahead of schedule and within budget • Achieved nameplate capacity of 70ktpm during July 2025 • FY26H2 production  19% to ~18

  25. Slide 25: Proposed Acquisition of Emmerson Resources

    PROPOSED ACQUISITION OF EMMERSON RESOURCES PROPOSED ACQUISITION OF EMMERSON RESOURCES (ASX:ERM)1 AUSTRALIAN OPERATIONS – TENNANT MINES • The acquisition of Emmerson consolidates the Group’s position in the prospective Tennant Creek mineral field in the Northern Territory, Australia • Successful conc

  26. Slide 26: Evander Underground

    PERFORMANCE BY OPERATION – UNDERGROUND PERFORMANCE BY OPERATION EVANDER UNDERGROUND EVANDER 8 SHAFT complex • Production  68% to ~47,000oz (FY25: 27,829oz) • Recovered grade of ~11g/t (FY25: 6.8g/t) • FY26H1 AISC reduced to US$1,576/oz (FY25H1: US$2,153/oz) • Increased gold production positively im

  27. Slide 27: Barberton Mines

    PERFORMANCE BY OPERATION – UNDERGROUND PERFORMANCE BY OPERATION BARBERTON MINES Gold production  5% to ~72,000oz (FY25: 68,550oz) FY26H2 production improved to ~39,500oz (FY26H1: 32,774oz) following: • Mining of high-grade ore from the MRC and Rossiter orebodies • 3 Shaft winder upgrade completed,

  28. Slide 28: Group AISC

    1. Health and safety 2. Group overview 2.1 Our operating environment 2.2 Key features 2.3 Performance by operation 2.4 Group AISC 2.5 Capital projects 2.6 Organic growth projects 3. ESG: Our “Beyond compliance” approach 4. FY26H1 Financials 5. FY26 Focused on delivery 6. Appendix GROUP OVERVIEW Grou

  29. Slide 29: Group AISC – FY26H1

    GROUP AISC GROUP AISC – FY26H1 GUIDING FULL YEAR AISC OF ~US$1,870/oz IN FY2026* Lower cost operations Barberton Total lower Evander Mines’ Tennant cost % Group Elikhulu BTRP MTR underground Fairview Mines operations production AISC per kg 675,221 828,894 880,538 880,103 1,209,004 1,419,945 949,123

  30. Slide 30: FY2026 – AISC Outlook

    US$/oz GROUP AISC 1,000 0 2,000 500 2,500 3,000 3,500 1,500 Hochschild Mining Agnico Eagle GROUP AISC LSE: PAF | JSE: PAN | OTCQX: PAFRF/PAFRY Alamos Gold FY 2026 – AISC OUTLOOK Perseus Mining PAR - lower cost operations Centerra Gold Oceana Gold Eldorado Gold Barrick Source: BMO Capital Markets ‘Th

  31. Slide 31: Capital Projects

    1. Health and safety 2. Group overview 2.1 Our operating environment 2.2 Key features 2.3 Performance by operation 2.4 Group AISC 2.5 Capital projects 3. ESG: Our “Beyond compliance” approach 4. FY25 Financials 5. FY26 Focused on delivery 6. Appendix GROUP OVERVIEW Capital projects

  32. Slide 32: Capital Projects (USD)

    CAPITAL PROJECTS CAPITAL PROJECTS (USD) INVESTMENT IN ORGANIC GROWTH – MAINTAINING OUR FUTURE PRODUCTION GROWTH TRAJECTORY US$107m US$161m US$167m US$180m US$324m 350 300 250 200 US$m 150 100 50 0 2023 2024 2025 2026* 2027# Solar Projects 16 Tennant Mines 37 50 147 MTR 9 69 53 23 50 Elikhulu 17 16 7

  33. Slide 33: Organic Growth Projects

    1. Health and safety 2. Group overview 2.1 Our operating environment 2.2 Key features 2.3 Performance by operation 2.4 Group AISC 2.5 Capital projects 2.6 Organic growth projects 3. ESG: Our “Beyond compliance” approach 4. FY26H1 Financials 5. FY26 Focused on delivery 6. Appendix GROUP OVERVIEW Orga

  34. Slide 34: Soweto Tailings Retreatment (STR)

    ORGANIC GROWTH PROJECTS SOWETO TAILINGS RETREATMENT (STR) REMINING SOWETO CLUSTER TSFs Feasibility study completed in November 2025 for an integrated operation to treat Soweto Cluster TSFs • >108Mt of Mineral Reserves to be treated through the new processing facility, with an additional 25Mt availab

  35. Slide 35: Tennant Mines

    ORGANIC GROWTH PROJECTS TENNANT MINES WARREGO GOLD AND COPPER PROJECT Organic growth through Targeted exploration spend A number of near-term Consolidate stranded third- leveraging existing asset over next 2 years to increase prospects to drive further party resources and regional portfolio Mineral

  36. Slide 36: Tennant Mines - Warrego Gold and Copper Project

    ORGANIC GROWTH PROJECTS TENNANT MINES - WARREGO GOLD AND COPPER PROJECT ORGANIC GROWTH AT TENNANT CREEK, AUSTRALIA • Pan African controls 1,700km2 of highly prospective ground in NT, Australia • 100% owned assets and JV agreements with ERM • Experienced in-country management team in place • Hub and

  37. Slide 37: Evander Mines – Poplar Project

    ORGANIC GROWTH PROJECTS EVANDER MINES – POPLAR PROJECT UNMINED SHALLOW UNDERGROUND MINERAL RESOURCE POPLAR PROJECT • One of the largest unmined Mineral Resources within the Witwatersrand Basin • Estimated Mineral Resource 28.7 Mt at 6.99g/t for 6.46Moz gold • Located within current PAR Mining Right

  38. Slide 38: ESG: Our Beyond Compliance Approach

    1. Health and safety 2. Group overview 2.1 Our operating environment 2.2 Key features 2.3 Performance by operation 2.4 Group AISC 2.5 Capital projects 2.6 Organic growth projects 3. ESG: Our “Beyond compliance” approach 4. FY26H1 Financials 5. FY26 Focused on delivery 6. Appendix ESG Our “Beyond com

  39. Slide 39: ESG: Our Beyond Compliance Approach

    ESG: OUR “BEYOND COMPLIANCE” APPROACH ESG: OUR “BEYOND COMPLIANCE” APPROACH GOVERNANCE ENVIRONMENT SOCIAL SOCIAL AND COMPLIANCE SOCIAL SOCIAL RENEWABLE ENERGY PROJECTS STAKEHOLDER ENGAGEMENT SUSTAINABLE COMMUNITIES COMPLIANT WITH GRI REPORTING • Operating solar plants in Barberton • Engagement forum

  40. Slide 40: Our Operating Environment – Renewable Energy Roadmap

    ESG: OUR “BEYOND COMPLIANCE” APPROACH OUR OPERATING ENVIRONMENT OPERATING SUCCESSFULLY IN SOUTH AFRICA – RENEWABLE ENERGY ROADMAP Current Operations and Pipeline of Group Renewable Energy Projects We are committed to achieving a 15% renewable energy mix by 2027, in compliance with our SLBF framework

  41. Slide 41: FY26H1 Financials

    1. Health and safety 2. Group overview 2.1 Our operating environment 2.2 Key features 2.3 Performance by operation 2.4 Group AISC 2.5 Capital projects 2.6 Organic growth projects 3. ESG: Our “Beyond compliance” approach 4. FY26H1 Financials 5. FY26 - Focused on delivery 6. Appendix FY26H1 FINANCIALS

  42. Slide 42: Summarised Consolidated Financial Results

    FY26H1 FINANCIALS FY26H1 FINANCIALS SUMMARISED CONSOLIDATED FINANCIAL RESULTS Six months ended Six months ended Movement Salient features Units 31 December 2025 31 December 2024 % change Gold produced oz 128,296 84,705 51.5 Gold sold oz 127,296 79,926 59.3 Revenue US$ million 487.1 189.3 157.3 US$/o

  43. Slide 43: Dividends and Shareholder Returns

    FY26H1 FINANCIALS FY26H1 FINANCIALS DIVIDENDS AND SHAREHOLDER RETURNS Historic dividends – record of sector-leading returns to shareholders Maiden interim dividend of ZAR 280million for FY26H1 1,000,000,000 40 900,000,000 35 800,000,000 30 700,000,000 Cents per share 600,000,000 25 ZARm 500,000,000

  44. Slide 44: FY26 - Focused on Delivery

    1. Health and safety 2. Group overview 2.1 Our operating environment 2.2 Key features 2.3 Performance by operation 2.4 Group AISC 2.5 Capital projects 2.6 Organic growth projects 3. ESG: Our “Beyond compliance” approach 4. FY26H1 Financials 5. FY26 Focused on delivery 6. Appendix FY26 - FOCUSED ON D

  45. Slide 45: FY26: Focused on Delivery

    FY26 – FOCUSED ON DELIVERY FY26: FOCUSED ON DELIVERY KEY DELIVERABLES INCLUDE ✓ Continue with focus on health and safety initiatives in our proactive journey to ‘zero harm’ ✓ Focus on achieving production and cost guidance ✓ Execute capital projects designed to sustain and increase future gold produ

  46. Slide 46: Contact Details

    Contact Details: Hethen Hira Head of Investor Relations Phone: + 27 11 243 2900 Email: hhira@paf.co.za www.panafricanresources.com LSE: PAF | JSE: PAN | OTCQX: PAFRF/PAFRY www.panafricanresources.com 46

Pan African Resources — Investor Presentation (June 2026) on 6ix