Camino Minerals Corporation · TSXV:COR

Camino Minerals — Investor Presentation (March 2025)

30 slides from Camino Minerals's investor presentation, March 2025

  1. Slide 1: Camino Corp March 2025

    CAMINOCORP.COM TSX.V : COR | OTCQB : CAMZF MARCH 2025

  2. Slide 2: Cautionary Notes and Forward-Looking Statements

    Cautionary Notes and Forward-Looking Statements Forward Looking Statements: Forward-looking information in this presentation includes statements with respect to the proposed acquisition of the Project; the closing of the Transaction and satisfaction of the related conditions to close; the anticipate

  3. Slide 3: Experienced Board and Management

    EXPERIENCED BOARD AND MANAGEMENT 3 JAY CHMELAUSKAS, BASc Geol. Eng., MBA CHRIS ADAMS CEO, President, Director Lead Independent Director • Former CEO of start-up to production companies Jinshan Goldmines Corp. (China), now • Former Senior Managing Director and head of Macquarie’s mining finance China

  4. Slide 4: Los Chapitos Puquios - The Lassonde Curve

    HIGH VALUE LOS CHAPITOS DRILLING CONFIRMS DEPOSITS POTENTIAL LOW VALUE EXPLORATION DISCOVERY THE LASSONDE CURVE SPECULATORS LEAVE FEASIBILITY OPERATIONAL IMPROVEMENT y INSTITUTIONAL INVESTMENT CONSTRUCTION RAMPUP ONGOING MINING MintinG ff EXPLAINED RESERVE DEPLETION

  5. Slide 5: Camino Strategy – Cashflow and Production Re-rating

    55 CAMINO STRATEGY – CASHFLOW AND PRODUCTION RE-RATING 1. CONSTRUCT – The Puquios Copper Mine in Chile (with Nittetsu); Cashflow in the Current Copper Cycle. • Construct (with permits in place) the copper mine to generate cashflow as early as 2027. • Finance and operate the mine with Camino and Nitt

  6. Slide 6: Construction & Production Chile

    66 CONSTRUCTION & PRODUCTION CHILE

  7. Slide 7: Puquios Copper Mine Purchase with Nittetsu

    7 PUQUIOS COPPER MINE PURCHASE WITH NITTETSU Joint Venture with Nittetsu Mining • 50:50 Joint Venture Nittetsu is a Japanese corporation listed on the Tokyo Stock • Each partner has rights to 50% of Cathode Offtake Exchange with 84-year history as a mining and trading company. • CAMINO will manage P

  8. Slide 8: Puquios Pre Feasibility Study Results

    8 PUQUIOS PRE FEASIBILITY STUDY RESULTS Mining 14 Year Mine Life Resources & Reserves Open Pit Mining - 9.8 mt Pre-strip Life of Mine Strip Ratio of 1.56x Tonne Grade Containe Resource s d Metal Plant Capability 5.75 kptd crushing capacity Classificati 9,000 tpa Copper Cathode Production (SX-EW) on

  9. Slide 9: Ausenco 2025 PFS Update from 2021 DFS – Feasibility Studies

    9 9 AUSENCO 2025 PFS UPDATE FROM 2021 DFS – FEASIBILITY STUDIES

  10. Slide 10: Resources

    10 RESOURCES Notes to accompany Mineral Resource table: Based on 389 drill holes 1. Mineral Resources are classified using the 2014 CIM Definition total of 46,731 m of core Standards. 1988 - 2021 2. The Qualified Person for the estimates is Mr. Cristian Quiñones, RM and RC drilling CMC, AsGeoMin SpA

  11. Slide 11: Reserves

    11 RESERVES Notes to the Mineral Reserve Table: Recovered In-Pit Reserve and Diluted Grade to Crushing Stage 1. The Mineral Reserves estimates were prepared by Jesse Aarsen, P.Eng. (who is also an Independent Qualified Person), reported using Ore (kt) NSR (US$/t) CuT % the 2014 CIM Definition Standa

  12. Slide 12: Upside Potential: Additional Sulphide Tonnage Below Open Pit

    12 UPSIDE POTENTIAL: ADDITIONAL SULPHIDE TONNAGE BELOW OPEN PIT LOCAL OXIDE, SULPHIDE RESOURCES, AND LEACHING TECHNOLOGY Local Oxide Miners in the Area: Sulphide Resources potential below Oxide Open-Pit • Identifying local miners with potential to provide • Potential to use innovative leaching techn

  13. Slide 13: Development Peru

    13 13 DEVELOPMENT PERU

  14. Slide 14: Los Chapitos Copper

    14 LOS CHAPITOS COPPER Potentially the Next Low-Capital Copper Oxide Mine to Build • Los Chapitos has over 26,000 meters of drilling completed intercepting mantos and breccia structures of oxide and sulphide copper mineralization. • 23,000 HA of contiguous exploration ground with three mineralized s

  15. Slide 15: Multiple Mineralized Trends – Diva, Atajo, La Estancia

    15 Multiple Mineralized Trends – DIVA, ATAJO, LA ESTANCIA 23,000 ha LOS CHAPITOS Pad 1 to Pad 4 extend over 350m strike length of Diva Trend DRILLING HIGHLIGHTS Significant copper intercept highlights (not true thickness) for Pad 1, Pad 2A, and Pad 4 include: DCH-001 (Pad 1) 55.3m @ 0.73% Cu from 7.

  16. Slide 16: Los Chapitos Copper – Lourdes – 2022 Drilling Highlights

    LOS CHAPITOS COPPER – Lourdes – 2022 Drilling Highlights Camino Intercepts Satellite High-Grade Copper with Lourdes Mineralized Zone 55.5m at 0.93% Cu from Surface, including 7.5m of • 55.5m @ 0.93% Cu from surface, including 7.5m @ 2.58% 2.58% Cu at Los Chapitos, Peru Cu in DCH-97 • 65.2m @ 0.70% C

  17. Slide 17: Copper Trends & Targets - Los Chapitos Copper, Peru

    COPPER TRENDS & TARGETS - LOS CHAPITOS COPPER, PERU Location of the main exploration objectives 2025. The Pampero Target is in the red circle. 17

  18. Slide 18: Established Mining District - Los Chapitos Copper, Peru

    18 ESTABLISHED MINING DISTRICT - LOS CHAPITOS COPPER, PERU • Rio Tinto increasing claims contiguous to Camino in 2023 and 2024. Rio Tinto targeting large scale copper sulphide deposit along the La Estancia fault that continues on Camino claims for 12km then extends onto RT’s adjacent claims. • Mina

  19. Slide 19: Infrastructure to Build a Mine

    19 INFRASTRUCTURE TO BUILD A MINE (SIMILAR TO MARCONA AND MINA-JUSTA) 1. Power: 510KV lines over the property. Sub- station in nearby Chala. 2. Water: Seawater processing 15km to project. 3. Access: 40 minutes from Pan American Highway (mining and transport Town of Chala). Source: Esri, Garmin, GEBC

  20. Slide 20: Exploration Peru & Chile

    20 20 EXPLORATION PERU & CHILE

  21. Slide 21: Exploration Upside at Puquios

    21 EXPLORATION UPSIDE AT PUQUIOS 21 (10,700 HA EXPLORATION & 2,894 HA EXPLOITATION)

  22. Slide 22: Los Chapitos Drilling Campaign – Winter 2024/2025

    22 LOS CHAPITOS DRILLING CAMPAIGN – WINTER 2024/2025 FIVE NEW EXPLORATION TARGETS IDENTIFIED AT LA ESTANCIA FAULT Camino has also discovered additional copper zones at Pilar Maria along the Diva Trend and the Rumi Puka fault. Notable mineralization at multiple targets, including: • Pampero: Up to 3.

  23. Slide 23: Maria Cecilia

    23 MARIA CECILIA MAJOR PORPHYRY SYSTEM PROLIFIC COPPER BELT • Newly Permitted Maria Cecilia central porphyry drilled in June 2024 • One drill hole has been completed to a depth of 700 meters with results expected in late August 2024 • Targeting oxide and sulphide copper mineralization outcropping at

  24. Slide 24: The Maria Cecilia Porphyry Complex

    THE MARIA CECILIA Twin 1 PORPHYRY COMPLEX Twin 2

  25. Slide 25: Maria Cecilia NI43-101 Resource Statement (2020)

    25 MARIA CECILIA NI43-101 RESOURCE STATEMENT (2020) Mineral Resource Statement for Toropunto and Emmanuel projects (8.9 US$/t NSR cut-off), Ancash Department, Peru, SRK Consulting (Peru) S.A., December 2020 Project Category Tonnes (Mt) CuEq (%) Cu (%) Au (g/t) Ag (g/t) Mo (ppm) (%) Toropunto Inferre

  26. Slide 26: Our Commitment to ESG

    26 OUR COMMITMENT TO ESG Camino Corp. is dedicated to developing our projects to bring sustainable and long-lasting social and economic benefits for the host communities and all stakeholders. We engage in meaningful consultation and honest dialogue with representatives of the communities surrounding

  27. Slide 27: Camino Investment Opportunity

    27 CAMINO INVESTMENT OPPORTUNITY • ”Shovel-Ready” copper asset that has been with Private Equity. • Scarce Asset Profile consisting of Production, Development and Exploration copper projects in Chile & Peru. • Extreme undervaluation compared to Historical Investments and Peer Value Comparison. • Man

  28. Slide 28: Camino – Undervalued by Comparison

    28 CAMINO – UNDERVALUED BY COMPARISON

  29. Slide 29: Camino Corporation – Puquios Acquisition & Development

    29 CAMINO CORPORATION – PUQUIOS ACQUISITION & DEVELOPMENT CURRENT CAPITAL STRUCTURE PUQUIOS TIMELINE Shares Outstanding 44,545,045 April 1 - 3, 2025 Closing of Puquios Transaction Warrants (@ $0.60 Exercise Price) 5,555,556 Options 2,641,667 Pre-Construction Detailed Engineering Fully Diluted 52,742

  30. Slide 30: Investor Relations Contact

    30 JAY CHMELAUSKAS BASC, MBA INVESTOR RELATIONS CEO, PRESIDENT & DIRECTOR INFO@CAMINOCORP.COM JAYC@CAMINOCORP.COM WWW.CAMINOCORP.COM 1.604.493.2058

Camino Minerals — Investor Presentation (March 2025) on 6ix